Loading...
HomeMy WebLinkAbout2/20/2002 - STAFF REPORTS (6) DATE: February 20, 2002 TO: City Council FROM: Director of Public Works/City Engineer CONTRACT CHANGE ORDER NO. 3 TO COMMERCIAL DIVERSIFIED, INC. FOR REPAIR OF 538 NORTH PALM CANYON DRIVE, THE PALM CANYON THEATER. RECOMMENDATION: That City Council approve Contract Change Order No. 3 to Commercial Diversified, Incorporated, in the amount of$2, 087.08, for a total Contract Amount of$289,577.47, for the Palm Canyon Theater Fire Damage Repair, City Project Number 00-20. SUMMARY: Change Order No. 3 will provide for additional framing at the men's restroom door due to substandard existing framing, additional work to patch and finish the ceiling area in the storage rooms and a credit due to City Crews relocating sprinkler control locks, in lieu of the construction contractor. BACKGROUND: On June 20, 2001 City Council awarded Commercial Diversified, Incorporated the contract for the fire damage repair work at the Palm Canyon Theater, and upgrade work not covered by insurance,which included replacement of and upgrades to various items within the Theater. 1. In doing the demolition work at the men's restroom, a substandard, light gauge metal frame was discovered at the non load bearing interior partition. The internal restroom doorwas inadequately framed and the existing wood stud wall had been poorly furred out with metal framing which formed an unstable surface upon which to apply the gypsum board. It is recommended that new wood framing be installed at the door and a new doorjamb with applied stop and no casing installed. New wood furring to the interior partition is also proposed to be installed to provide adequate substrate for installation of the gypsum board. 2. Change Order No. 1 provided for installation of new 5/8" gypsum board ceiling, west of the breezeway, however, the change order did not provide for nail filling, texturing and painting of the gypsum board ceiling. The Change Order No. 1 work has been completed and it is now being recommended that the new ceiling be painted with the nail holes filled. 3. The initial contract provided for the contractor to relocate an existing sprinkler control box, near the east gable. This control box was relocated to the new enclosure along with another control box by City crews. Therefore, decrease in the contract amount is appropriate crediting The City for the cost of the work that was not performed by the contractor. Palm Canyon Theater Fire Damage Repair February 20, 2002 Page 2 Sufficient funds are available in Palm Canyon Theater Fire Repair, Account#261-1395- 54024. �� DAVID J. BARAKIAN Director of Public Works/City Engineer APP OVE& �a— City Manager ,d ATTACHMENTS: 1. Minute Order 2. Change Order REVIEWED BY DEn DF FINANCE r January 28, 2002 C.P. 0020 Palm Canyon Theater Change Order No. 3 CITY OF PALM SPRINGS CONTRACT CHANGE ORDER CHANGE ORDER NO, 3 TO: Commercial Diversified Inc. 72033 Twenty-nine Palms Highway Twenty-nine Palms, CA 92277 FAX: (760) 367.6860 Date: 17 December, 2001 Project No: 0020 Project: Palm Canyon Theatre Fire Damage Repair Change Order No: Three (3) Contract Purchase No: Account No: 261-1395-54024 M.O. #6871............. .... ......................................... Agr. # 4375 A— CHANGE IN WORK: Increase in contract quantities: Increase to existing items in contract: 1. Framing: Install new wood framing at door, consisting, but not limited to, king studs, trimmer studs, cripple studs and header. Install new doorjamb with applied stop and no casing. Install new wood furring to interior partition to provide adequate substrate for installation of gypsum board. 2. Finish gypsum board ceiling in storage room areas approx. 600 sf, including, but not limited to, nail filling, texturing and painting. Top 12" of wall shall be finished, but no other areas. Decrease in contract quantities: 1. Omit relocation of sprinkler control box: Commercial Diversified shall leave in place existing sprinkler control box at the east gable. City parks maintenance subcontractors shall be responsible for moving both sprinkler boxes. The City was charged $400 for this work, therefore this amount shall be deducted from this contract. See attached invoice. B — CHANGES IN COST: Increase to contract costs: Increase to items already in contract: 1. Framing at male restroom Lump sum agreed price $687.08 2. Finish gyp bd ceiling Engineer's Estimate $1,800.00 To be based on cost of work (Time, materials, equipment, overhead and profit) as per Article 11 January 28, 2002 C.P. 0020 Palm Canyon Theater Change Order No. 3 Decrease to items already in contract: 1. Omit relocation of sprinkler control box Lump sum $(400.00) TOTAL NET CHANGE ORDER #3 — $2,087.08 C: REASONS FOR CHANGES: 1. Additional framing at male restroom: Demolition at the male restroom uncovered substandard light gauge metal framing at the non load bearing interior partition. The internal restroom door was inadequately framed with no king studs, trimmer studs or header. The existing wood stud wall had been poorly furred out with metal framing, forming an unstable surface upon which to apply new gypsum board. 2. Finish gypsum board ceiling: Change Order#1 omitted work to finish the ceiling area not in the original contract. As funds were limited, it was determined that upgrades to the structure were critical, but finish work in these storage areas was not. Subsequently, the city has decided to undertake this work in order to satisfy the tenants, who are unhappy with these rooms being left unfinished. 3. Relocation of sprinkler control box: Subsequent to the preparation of the contract documents, a second sprinkler control box was installed on the east elevation adjacent to an existing box as part of the construction of the fountain. The relocation of the first box to the interior of the new doghouse structure is included in the contract, however relocation of the second is not. City representatives determined that the city maintenance crew would relocate both boxes, therefore resulting in a credit to the construction contract. D. CHANGE IN CONTRACT TIME 1. Framing — No additional working days will be added to the contract length 2. Finish gyp bd ceiling — This work will not be undertaken until completion of all contract items on 01/25/02. 3 additional working days, after authorization of this change order, shall be allowed to complete this additional work. January 28, 2002 C.P. 0020 Palm Canyon Theater Change Order No. 3 SOURCE OF FUNDS: Palm Canyon Theatre Fire Damage Repair Account No: 261-1395-54024 Summary of Costs Contract Time Original Contract Amount: $ 252,000.00 Original Completion Date: 11/30/01 This Change Order: $ 2,087.08 Days Added for this C.C.O.: 3 Previous Change Order(s): $ 35,490.39 Previous Days Added: 36 Revised Contract Amount: $ 289,577.47 Revised Completion Date: I have received a copy of the Change Order City Approval: and the above AGREED PRICES are acceptable to the contractor. Submitted By Reuel A. Young, Interactive Design Corp. By: Date Title: Approved By BY: Date City Engineer Title Approved By Date Date City Manager Distribution: Original Conformed Copies Conformed — File Copy Engineering (1) Engineering File (1) Finance (1) Purchasing Agent (1) Contractor (1) Risk Management (1) City Clerk (1) Completion date to be established after change order authorization. MINUTE ORDER NO. APPROVING CONTRACT CHANGE ORDER NO. 3 TO COMMERCIAL DIVERSIFIED, INCORPORATED, IN THE AMOUNT OF $2,087.08, FOR A TOTAL CONTRACT AMOUNT OF $289,577.47, FOR THE PALM CANYON THEATER FIRE DAMAGE REPAIR, CITY PROJECT NUMBER 00-20. I HEREBY CERTIFY that this Minute Order, approving Contract Change Order No. 3 to Commercial Diversified, Incorporated, in the amount of$2,087.08, for a total contract amount of$289,577.47, for the Palm Canyon Theater Fire Damage Repair, City Project Number 00-20, was adopted by the City Council for the City of Palm Springs, California, in a meeting thereof held on the 201h day of February 2002. PATRICIA A. SANDERS City Clerk 49