Loading...
HomeMy WebLinkAbout4/3/2002 - STAFF REPORTS (19) DATE: April 3, 2002 TO: City Council FROM: Director of Public Works/City Engineer TRAMVIEW ROAD STREET AND SEWER IMPROVEMENT PROJECT RECOMMENDATION: It is recommended that the City Council approve a budget amendment transferring wasterwater treatment plant reserves into a capital project account; and, award contract to G & M Construction in the amount of$388,750.00 for Bid Schedules A and B,for the Tramview Road Street&Sewer Improvement Project, City Project 01-19. SUMMARY: Award of this contract will remove and replace the existing sewer system within Tramview Road from Indian Canyon Drive to Granada Avenue, and reconstructthat portion of Tramview Road, facilities that have been damaged over the years by adjacent Tamarisk trees. This is a Community Development Block Grant (CDBG) project. BACKGROUND: On April 4, 2001, Council approved the 2001/2002 CDBG budget, including within the Program the Tramview Road Street and Sewer Improvement Project, as submitted by the Engineering Department. Tramview Road from Indian Canyon Drive to Granada Avenue has been affected by the adjacent row of Tamarisk trees for the past 30 years. Over this period of time, tree roots have broken up the street and have caused damage to the underlying sewer system. The plans and specifications for this project were prepared by staff from the Public Works and Engineering Department, and on February 20, 2002, Council approved and adopted the plans and specifications for this project, and authorized advertisement for construction bids. The project consisted of two Bid Schedules, Bid Schedule A represents the removal and replacement of the sewer system, reconstruction of Tramview Road, and installation of an irrigation and root control system between the roadway and the existing Tamarisk trees. Bid Schedule B represents construction of a new access ramp and sidewalk from Tramview Road up and around the existing parking lot in the Desert Highland park. On February 22 and March 1, 2002, the project was advertised for bids, and at 2:00 P.M. on March 19, 2002, the Department of Procurement and Contracting received bids from the following contractors: Contractor Bid Sch. A Bid Sch. B Total 1. G & M Construction; $382,650.00 $6,100.00 $388,750.00 Palm Springs, CA 2. Hemet Mfg. Co., Inc.; $414,297.00 $5,480.00 $419,777.00 Hemet, CA 3. Dateland Construction Co. $432,332.00 $6,115.00 $438,447.00 Coachella, CA i7A Ruth Hardy Park Sidewalk Improvements April 3, 2002 Page 2 The Engineer's estimate was $517,325 for Bid Schedule A; and $6,150 for Bid Schedule B, for a total estimate of$523,475. The low bidder is G & M Construction, from Palm Springs, California. The company is a corporation and its officers are George Marantz, President; Michael Marantz,Vice-President; and Dianne Marantz, Secretary. As part of the Council's consideration and approval of the Tramview project in the 2001/2002 CDBG Program, it was discussed that the appropriated CDBG funds would be used to fund the necessary street repairs, while the associated sewer replacementand reconstruction costs would be funded from Wastewater Treatment Plant reserves. Therefore, at this time it will be necessary to approve a budget amendment to transfer$160,000 from Wastewater Treatment Plant reserves into a capital project account for this project. This amount will fund the balance of the project not covered by CDBG funds, as well as construction administration and inspections costs. Sufficient funds are available in account 137-4802-63538 (Palm Springs Engineering -Tramview Improvements)and will be available in 420-6820- 57014 (Tramview Sewer Improvements). DAVID J. BARAKIAN Director of Public Works/City Engineer APP ROVE D!�� City Manager ATTACHMENTS: 1. Resolution 2. Minute Order REVIEWED BY DEPT.OF FINANCE r MINUTE ORDER NO. AWARDING CONTRACT TO G & M CONSTRUCTION IN THE AMOUNT OF $388,750.00 FOR BID SCHEDULES A AND B, FOR THE TRAMVIEW ROAD STREET & SEWER IMPROVEMENT PROJECT, CITY PROJECT 01-19 I HEREBY CERTIFYthatthis Minute Order, awarding contractto G&M Construction in the amount of$388,750.00 for Bid Schedules A and B, for the Tramview Road Street & Sewer Improvement Project, City Project 01-19,was adopted by the City Council of the City of Palm Springs, California, in a meeting thereof held on the 3ftl day of April, 2002. PATRICIA A. SANDERS City Clerk 16745 RESOLUTION NO. OFTHE CITY COUNCIL OF THE CITY OF PALM SPRINGS, CALIFORNIA,AMENDING THE BUDGET FOR THE 2001-02 FISCAL YEAR WHEREAS Resolution 20062 approving the budget forthe fiscal year2001-02 was adopted on June 6, 2001; and WHEREAS the City Manager has recommended, and the City Council desires to approve, certain amendments to said budget; NOW THEREFORE BE IT RESOLVED that the Director of Finance is authorized to record inter-fund cash transfers as required in accordance with this Resolution, and that Resolution 20062, adopting the budget for the 2001-02 fiscal year is hereby amended as follows: SECTION 1. ADDITIONS Fund Activity Account Amount 420 6820 57014 $160,000 Wastewater Wastewater Tramview Sewer Treatment Plant Collection Improvements The Wastewater Treatment Plant reserves will be allocated into a capital project account that will be used to fund the removal and replacement of the damaged sewer system within Tramview Road. SECTION 2. SOURCE Fund Activity Account Amount 420 29302 $160,000 Wastewater Retained Earnings Treatment Plant Adopted this day of _, 2002. AYES: NOES: ABSENT: ATTEST: CITY OF PALM SPRINGS, CALIFORNIA By: City Clerk City Manager REVIEWED AND ADOPTED AS TO FORM: 107 Cosso