Loading...
HomeMy WebLinkAbout6/19/2002 - STAFF REPORTS (15) DATE: June 19, 2002 TO: City Council FROM: Public Works Director/City Engineer APPROVE CALTRANS SUPPLEMENTAGREEMENT NO. M011 FOR GENE AUTRY TRAIL RR BRIDGE WIDENING ENVIRONMENTAL USING FEDERAL STIP GRANT FUNDING RECOMMENDATION: It is recommended that the City Council approve Caltrans Supplement Agreement No. M011, in the amount of$10,000($7,000 Federal/$3,000 Local),forthe Environmental for the Gene Autry Trail Railroad Bridge Widening Project using Federal STIP grant funds, State Project No. RPSTPL-5282 (018); City Project No.2002-03. SUMMARY: The most recent Agency-State MasterAgreement No.08-5282 for Federal Aid was executed on March 18, 1998 and Program Supplement Agreement No.M011 to that MasterAgreement authorizes the federal grant reimbursement from Caltrans upon completion of the project. BACKGROUND: In January 2001 the City applied to the Riverside County Transportation Commission(RCTC) for a $1,842,000 federal STIP grant to widen the existing Southern Pacific Railroad Bridge and connector road to Interstate 10 from 2 to 6 lanes.The grant was approved by RCTC and the California Transportation Commission (CTC) and was placed on the Federal Transportation Improvement Plan (FTIP) on September 25, 2001. The grant application requested federal funding forthe project in 3 main elements: $7,000 Environmental/$280,000 for Engineering Design(PS&E)/$1,555,000 Construction($1,842,000federal/$789,000local for a grand total of $2,631,000. CVAG has agreed to fund the local match from Regional Measure A funds. This current allocation is for the initial environmental phase of work. The City has also received Caltrans authorization for the PS&E Design stage so RFP's can now be issued to consultants for the design of the bridge and roadway widening project, which is being coordinated with the current Gene Autry/1-10 Interchange widening project. An Offsetting Budget Adjustment will establish an account in fund 261-4491 for this work. ROBERT L. MOHLER DAVID J. BARAKIAN Grants and Government Affairs Manager PublicWorks Director/City Engineer APPROVEDF�' City Manager REVIEWED BY DEn OF FINANCE- ATTACHMENTS:1. Minute Order, 2. Caltrans Program Supplemental Agreement No. M011 IM PROGRAM 'SUPPLEMENT NO. M011 Date:April 29, 2002 to Location:08-RI V-O-pSp ADMINISTERING AGENCY-STATE AGREEMENT Project Number: j RPSTPL-5282(018) FOR FEDERAL-AID PROJECTS NO. 08-5282 E.A. Number:08-412444 This Program Supplement is hereby incorporated into the Agency-State Agreement for Federal Aid which was entered into between the Agency and the State on 03/18/98 and is subject to all the terms and conditions thereof This Program Supplement is adopted in accordance with Article I of the aforementioned Master Agreement under authority of Resolution No. , approved by the Agency on (See copy attached). The Agency further stipulates that as a condition to payment of funds obligated to this project,it accepts and will comply with the covenants or remarks setforth on the following pages. PROJECT LOCATION: on Gene Autry Trail from Whitewater River Wash to the Interstate 10 interchange TYPE OF WORK:bridge and roadway connector widening LENGTH: o(MILES) Estimated Cost Federal Funds Matching Funds RPBO $6,197.00 LOCAL State OTHER $10,000.00 $3'000.00 $803.00 $0.00 CITY OF PALM SPRINGS STATE OF CALIFORNIA Department of Transportation By By _ Chief, Office of Project Implementati Date - - �aA "Division of Local Assistance Attest Date Title I hereby certify upon my personal knowledge that budgeted funds are available for this encumbrance: Accounting Offic (/' i Date -30 . U " $7,000.00 Chapter statutes Item Ye 2ur Progr Be Category Fund Source AMOUNT 106 2001 2660-101-890 2001- 20.30.600.620 S 262042 892-F 6,197.00 106 2001 2660-101-042 2001-2002 20.30.600.620 S 262042 042-T 803.00 IqA z Program Supplement 08-5282-M011- ISTEA Page 1 of 5 08-RIV-0-PSP 04/29/2002 RPSTPL-5282(018) SPECIAL COVENANTS OR REMARKS 1. The ADMINISTERING AGENCY will reimburse the State for the ADMINISTERING AGENCY share of costs for w-Qrk requested to be performed by the State. 2 . All project repair, replacement and maintenance involving the physical condition and the operation of project improvements referred to in Article III MAINTENANCE, of the aforementioned Master Agreement will be the responsibility of the ADMINISTERING AGENCY and shall be performed at regular intervals and as required for efficient operation of the completed project improvements. 3 . This PROJECT is programmed to receive funding from the 1998 State Transportation Improvement Program (STIP) , as amended. Funding may be provided under one or more components. A component (s) specific fund allocation is required, in addition to other requirements, before reimbursable work can occur for the component (s) identified. Each allocation will be assigned an effective date and identify the amount of funds allocated per component(s) . This PROGRAM SUPPLEMENT has been prepared to allow reimbursement of eligible PROJECT expenditures for the component (s) allocated. The start of reimbursable expenditures is restricted to the later of either 1) the effective date of the Master Agreement, 2) the effective date of the PROGRAM SUPPLEMENT, or 3) the effective date of the component specific allcr-&-t.ion, 4 . STATE and ADMINISTERING AGENCY agree that additional funds made available by future allocations will be encumbered on this PROJECT by use of a STATE approved Allocation Letter and Finance Letter. ADMINISTERING AGENCY agrees that STATE funds available for reimbursement will be limited to the amount allocated by the California Transportation Commission (CTC) and/or the STATE. 5. This PROJECT is subject to the timely use of funds provisions enacted by Senate Bill 45 (SB 45) , approved in 1997, and subsequent CTC guidelines and State procedures approved by the CTC and STATE, as outlined below: Funds allocated for the environmental & permits, plan specifications & estimate, and right-of-way components are / y*4 ? Program Supplement08-5282-M011- ISTEA Page 2 of 5 08-R1V-')-PSP 04/29/2002 RPSTPL-5282(018) SPECIAL COVENANTS OR REMARKS available for expenditure until the end of the second fiscal year following the year in which the funds were allocated. Funds allocated for the construction component are subject to an award deadline and contract completion deadline. ADMINISTERING AGENCY agrees to award the contract within 12 months of the construction fund allocation and complete the construction or vehicle purchase contract within 36 months of award. 6 . Upon ADMINISTERING AGENCY request, the CTC and/or STATE may approve supplementary allocations, time extensions, and fund transfers between components . An approved time extension will revise the timely use of funds criteria, outlined above, for the component (s) and allocation(s) requested. Approved supplementary allocations, time extensions, and fund transfers between components, made after t'ie execution of this PROGRAM SUPPLEMENT will be documented and considered subject to the terms and conditions thereof. Documentation for approved supplementary allocations, time extensions, and fund transfers between components, will be a STATE approved Allocation Letter, Fund Transfer Letter, Time Extension Letter, and Finance Letter, as appropriate. 7 . This PROJECT will be administered in accordance with the CTC STIP guidelines, as adopted or amended, and the STATE Procedures for Administering Local Grant Projects in the State Transportation Improvement Program (STIP) , the Local Assistance Program Guidelines, and the Local Assistance Procedures Manual . The submittal of invoices for project costs shall be in accordance with the above referenced publications and the following. 8 . The ADMINISTERING AGENCY shall invoice STATE for environmental & permits, plans specifications & estimate, and right-of-way costs no later than 180 days after the end of last eligible fiscal year of expenditure. For construction costs, the ADMINISTERING AGENCY has 180 days after project completion to make the final payment to the contractor and prepare the final Report of Expenditures and final invoice, and submit to STATE for verification and payment. 9 . All obligations of STATE under the terms of this Agreement are / 0V Program Supplement08-5282-M011- ISTEA Page 3 of 5 G8-RIV-C-PSP 04/29/2002 RPSTPL-5282(018) SPECIAL COVENANTS OR REMARKS subject to the appropriation of resources by the Legislature and the encumbrance of funds under this Agreement. Funding and reimbursement are available only upon the passage of the State Budget Act containing these STATE funds . 10 . The ADMINISTERING AGENCY is required to have an audit in accordance with the Single Audit Act and OMB A-133 if it receives a total of $300, 000 or more in federal funds in a single fiscal year. The federal funds received under this project are a part of the Catalogue of Federal Domestic Assistance (CFDA) 20 .205, Highway Planning and Research. OMB A-133 superceded OMB A-128 in 1996 . A reference to OMB A-128 in a Master Agreement (if any) is superceded by this covenant to conform to OMB A-133 . ll. The ADMINISTERING AGENCY agrees that payment of Federal funds will be limited to the amounts approved by the Federal Highway Administration (FHWA) in the Federal-Aid Project Authorization/Agreement or Amendment/Modification (E-76) and accepts any resultant increases in ADMINISTERING AGENCY funds as shown on the Finance Letter, any modification thereof as approved by the Division of Local Assistance, Office of Project Implementation. 12 . Award information shall be submitted by the ADMINISTERING AGENCY to the District Local Assistance Engineer immediately after the project contract award. Failure to do so will cause a delay in the State processing invoices for the construction phase. Please refer to Section 15 .7 "Award Package" of the Local Assistance Procedures Manual. 13 . STATE and ADMINISTERING AGENCY agree that any additional funds which might be made available for new phase (s) of work by future Federal obligations will be encumbered on this PROJECT by use of a STATE approved "Authorization to Proceed" and Finance Letter. ADMINISTERING AGENCY agrees that Federal funds available for reimbursement will be limited to the amounts obligated by the Federal Highway Administration. 14 . ADMINISTERING AGENCY agrees that it will only proceed with work authorized for specific phase (s) with an "Authorization to Proceed" and will not proceed with future phase (s) of this project prior to receiving an "Authorization to Proceed" from the STATE for that phase (s) unless no further State or Federal funds / q*4 Program Supplement08-5282-MO11- ISTEA Page 4 of 5 OR-RN 0-PSP 04/29/2002 RPSTPL-5282(018) SPECIAL COVENANTS OR REMARKS are needed for those future phase (s) . 15 . The ADMINISTERING AGENCY will advertise, award and administer this project in accordance with the most current published Local Assistance Procedures Manual. I �P Program Supplement08-5282-M011- ISTEA Page 5 of 5 MINUTE ORDER NO. APPROVING CALTRANS PROGRAM SUPPLEMENT AGREEMENT NO. M011, IN THE AMOUNT OF $10,000 ($7,000 FEDERAL/ $3,000 LOCAL), FOR THE ENVIRONMENTAL FOR THE GENE AUTRY TRAIL RAILROAD BRIDGE WIDENING PROJECT USING FEDERAL STIP GRANT FUNDS; STATE PROJECT NO. RSTPL-5282 (018); CITY PROJECT NO. 2002-03. I HEREBY CERTIFY that this Minute Order approving Caltrans Program Supplement Agreement No. M011, in the amount of $10,000 ($7,000 Federal/ $3,000 Local) for the Environmental for the Gene Autry Trail Railroad Bridge Widening Project, using Federal STIP Grant funds; State Project No. RSTPL-5282 (018); City Project No.2002-03,was adopted by the City Council of the City of Palm Springs, California, in a meeting thereof held on the 1g1h day of June, 2002. PATRICIA A. SANDERS City Clerk 1 1