HomeMy WebLinkAbout7/3/2002 - STAFF REPORTS (24) DATE: ,J��29!►'l� �1y * 4ZO031W
TO: City Council
FROM: Director of Procurement and Contracting
AWARD TRADE CONTRACTS FOR CONSTRUCTION OF THE DOWNTOWN PARKING
STRUCTURE
RECOMMENDATION:
That City Council award trade contracts for construction of the downtown parking
structure.
SUMMARY:
In order to meet the tight turnaround times required to build the downtown parking
structure, bid openings for the trade bids required to begin construction were
scheduled to be opened June 18, 2002. In several instances no bids were received
and, therefore, under the Procurement Ordinance, staff has proceeded to negotiate
trade contracts. A complete summary of the recommended awards will be distributed
to City Council at the meeting. Construction is projected to begin July Vand be
completed by Thanksgiving.
BACKGROUND:
City Council previously approved and adopted the plans, specifications and working
details for the downtown parking structure and authorized solicitation for construction
trade bids and quotes.
Site Demolition, Utility Relocation and Earthwork trade work is scheduled to be
complete by the end of June. Construction is scheduled to begin July 1'. Award of
trade bids at the meeting of June 261h is necessary to meet the project time lines.
Funds are available in account#4463-50201 - Downtown Parking Structure.
.,
HAROLD E. GOOD, CPPO
Director of Procurement & Contracting
APPROVED:
City Manager
ATTACHMENT:
Minute Order
DATE: July 3, 2002
TO: City Council
FROM: Director of Procurement and Contracting
APPROVE AWARDING TRADE CONTRACT FOR METAL STUD FRAMING & PLASTER
RECOMMENDATION:
That City Council approve awarding contract in the amount of$178,130 for metal stud framing and
plaster for the Downtown Parking Structure, (Bid Package#13) to Berger Brothers, Inc., in a form
acceptable to the City Attorney.
SUMMARY:
No bids were received for providing Metal Stud Framing and Plaster construction services (Bid
Package#13) by the bid deadline of June 18, 2002. Public Contract Code allows negotiation of
a contract when no bids are received. As a result of a negotiation process, staff recommends
award to Berger Brothers. The estimated (budget) cost for this trade package was $185,400.
BACKGROUND:
No bids were received for the Metal Stud Framing and Plaster, Trade Bid Package #13, on June
18th. Pursuant to the Public Contract Code, staff entered into negotiations with Sierra Plastering
and Masino Plastering, Inc., as well as Berger Brothers, Inc., for price proposals to perform the
work encompassed in Trade Bid #13.. Sierra's best price was $208,000. Masino Plastering did
not submit final pricing because of a sub-contracting issue. Berger Brothers, Inc., is a firm which
has successfully worked on major projects with Turner Construction Company in the past,and staff
recommends award to Berger Brothers, Inc. in the amount of$178,130.
The Bid and Award Schedule submitted by the Executive Director - Airports, at the City Council
meeting of June 19, 2002, has been updated to include the anticipated award of this contract. A
copy is attached.
Funds are available in account#p✓4463-50201.
HAROLD E. GOOD
Director of Procurement & Contracting
APPROVED:
��✓':1..---
City Manager
Attachment: Bid and Award Schedule
Minute Order REVIEWED BY DEPT.OF FINANCE
MINUTE ORDER NO.
APPROVING AWARDING TRADE CONTRACT TO
BERGER BROTHERS, INC., IN THE AMOUNT OF
$178,130 FOR PROVIDING METAL STUD
FRAMING AND PLASTER CONSTRUCTION
SERVICES (BID PACKAGE #13) AT THE
DOWNTOWN PARKING STRUCTURE.
I HEREBY CERTIFY that this Minute Order awarding the trade contract to Berger Brothers,
Inc., in the amount of$178,130 for providing Metal Stud Framing and Plaster, (Bid Package
#13) at the Downtown Parking Structure was adopted by the City Council of the City of
Palm Springs, California in a meeting thereof held on the 3rd of July, 2002.
PATRICIA A. SANDERS
City Clerk
-2-
CITY OF PALM SPRINGS DOWNTOWN PARKING STRUCTURE (7/13/02) Bid and Award Schedule
Bid Package # Scope of Work Estimate Bid Difference
#1 Selective Demolition $85,645 95,680 $10,035
#2 Earthwork 97,425 39,500 (57,925)
#3 Site Utilities 54,875 59,500 4,625
#4 Elevator (Only two) 180,000 98,000 (82,000)
#5 Landscape&Irrigation 35,180 51,870 16,690
#6 Asphalt Paving 48,076 48,076 No bid
#7 Concrete&Reinforcing 2,029,480 2,024,000 (5,480)
#9 Masonry 372,896 388,500 15,604
#10 Miscellaneous Metals 160,050 174,360 * 14,310
#11 Waterproofing 23,350 23,350 No bid
412 Glass&Glazing 7,000 7,000 No bid
#13 Metal Stud Framing&Plaster 185,400 178.130 (7,270)
#14 Painting 38,975 38,975 No bid
#15 Parking Control Equipment 15,000 24,432 9,432
#16 Parking Structure Signage 10,000 10,000 No bid
#17 Plurnbing 61,517 159,000 97,483
#18 Fire Protection 126,800 65,540 (61,260)
#19 HVAC 16,500 14,060 (2,440)
#20 Electrical 194,382 239,400* 45,018
#21 Shade Structures 117,000 117,000 No bid
#22 Site Concrete 121,419 121,419 No bid
#23 Pavers 38,031 38,031 0
Asbestos 5,325 5,325 0
Sheet Light Fixtures 31,500 24,292 (7,208)
DWA 125,000 105,568 (19,432)
Other Utilities 25,000 25,000 No cost yet
Doors 4,000 4,606 606
Pave One Lane Indian 30,000 30,000 No bid
Small Storm Drain 10,000 10,000 No bid
8" Water Line Relocate 30,000 30,000 No bid
Subtotal(Trades) 4,279,836 4,250,644 (29,212)
Plus Contingencies 415,000 415,000
*Includes Change Order TOTAL 4,694,826 4,672,884 F(2:19Z42I
City of Palm Springs
Department of Procurement & Contracting
Phone (760)323-8239 Fax (760)323-8372
haroldena ci. alm-springs.ca.us
MEMORANDUM y
To: City Council i
From: Director of Procurement & Contracting;via City M ager
Subject: Downtown Parking Structure
Additional Information Re: City Council Agenda - Item #20 - July 3, 2002
It is anticipated that Council will be requested to award contracts for two trades: Bid
Package #13 - Metal Stud Framing & Plaster and Bid Package #22 - Site Concrete.
Final pricing is expected to be received by 4:00 p.m. on Tuesday, July 2, 2002.
�} I
H:\USERMPPUBLIMDOWNTOWN PARKING STRUCTURE\Memo to councilmpd
Page 1