HomeMy WebLinkAbout04508 - G & M CONSTRUCTION TILE WORK DEMUTH PARK RESTROOM MO7093 CP98-20 • G & M Construction
Demuth Park Restroom
AGREEMENT #4508
M070941 6-5-02
AGREEMENT
THIS AGREEMENT made this dayof
in the year 2002, by and between the City of Palm Springs, charter city, organized and existing
in the County of Riverside, under and by virtue of the laws of the State of California, hereinafter
designated as the City, and G & M Construction, Inc. hereinafter designated as the Contractor.
The City and the Contractor, in consideration of the mutual covenants hereinafter set forth, agree
as follows:
ARTICLE 1 --THE WORK
The Contractor shall complete the Work as specified or indicated under the Bid Schedule(s) of
the City's Contract Documents entitled:
DEMUTH PARK RESTROOM FACILITIES - (Tile Work)
CITY PROJECT NO. 98-20
The Work includes furnishing and installing building paper, lathing and plastering for backing for
exterior tile walls, ceramic wall tile over Portland cement concrete scratch and brown coat base,
anti-graffiti coatings, and finish painting: and all Appurtenant work as shown on the Project
Drawings and as required in the Technical Specifications.
ARTICLE 2 -- COMMENCEMENT AND COMPLETION
The Work to be performed under this Contract shall commence on the date specified in the
Notice to Proceed by the City, and the Work shall be fully completed within the time specified in
the Notice to Proceed.
The City and the Contractor recognize that time is of the essence of this Agreement, and that the
City will suffer financial loss if the Work is not completed within the time specified in Article 2,
herein, plus any extensions thereof allowed in accordance with the applicable provisions of the
Standard Specifications, as modified herein. They also recognize the delays, expense, and
difficulties involved in proving in a legal proceeding the actual loss suffered by the City if the
Work is not completed on time. Accordingly, instead of requiring any such proof, the City and the
Contractor agree that as liquidated damages or delay (but not as a penalty), the Contractor shall
pay the City the sum of $ 425.00 for each calendar day that expires after the time specified in
Article 2, herein.
ARTICLE 3 -- CONTRACT PRICE
The City shall pay the Contractor for the completion of the Work, in accordance with the Contract
Documents, in current funds the Contract Price(s) named in the Contractor's Bid and Bid
Schedule(s) ($13,500.00).
Co"GIB Uv,1 �1'J�111 rr n
0 •
ARTICLE 4 --THE CONTRACT DOCUMENTS
The Contract Documents consist of the Notice Inviting Bids, Instructions to Bidders, the accepted
Bid and Bid Schedule(s) this Agreement, Worker's Compensation Certificate, Standard
Specifications, Special Provisions, the Drawings, Addenda numbers (None) to (None), inclusive,
and all Change Orders and Work Change Directives which may be delivered or issued after the
Effective Date of the Agreement and are not attached hereto.
ARTICLE 5 -- PAYMENT PROCEDURES
The Contractor shall submit Applications for Payment in accordance with provisions of the
Standard Specifications as amended by the Special Provisions. Applications for Payment will be
processed by the Engineer or the City as provided in the Contract Documents.
ARTICLE 6 -- NOTICES
Whenever any provision of the Contract Documents requires the giving of a written Notice, it shall
be deemed to have been validly given if delivered in person to the individual or to a member of
the firm or to an officer of the corporation for whom it is intended, or if delivered at or sent by
registered or certified mail, postage prepaid, to the last business address known to the giver of
the Notice.
ARTICLE 7 -- MISCELLANEOUS
Terms used in this Agreement which are defined in the Standard Specifications as amended by
the Special Provisions will have the meanings indicated in said Standard Specifications and
Special Provisions. No assignment by a party hereto of any rights under or interests in the
Contract Documents will be binding on another party hereto without the written consent of the
party sought to be bound; and specifically, but without limitation, monies that may become due
and monies that are due may not be assigned without such consent (except to the extent that the
effect of this restriction may be limited by law), and unless specifically stated to the contrary in
any written consent to an assignment, no assignment will release or discharge the assignor from
any duty or responsibility under the Contract Documents.
The City and the Contractor each binds itself, its partners, successors, assigns, and legal
representatives, to the other party hereto, its partners, successors, assigns, and legal
representatives, in respect of all covenants, agreements, and obligations contained in the
Contract Documents.
(Signatures on Next Page)
IN WITNESS WHEREOF, the parties have executed and entered into this Agreement as of the
date first written above.
CITY OF PALM SPRINGS
AT T a municipal corporation
City Clerk City Manager
Agreement o* F/under $25,000
Reviewed and approved by
Procurement & Contracting
Initials
P.O. Number
CONTRACTOR: Check one:_Individual_Partnership icorporation
Corporations require two notarized signatures: One from each of the following: A. Chairman of Board, President, or any Vice
President:AND B. S cretary Assistant Secretary,Treasurer,Assistant Treasurer,or Chief Financial Officer).
f �
By: / By:
Signa r notarized) Signature(notarized) )
Name: tQ1,C lgpiril Name: JD:c AJart rY14oAN Tr
Title: C"FES. Title: I SE0_9ETW2Y %a&*5L*E.r¢
State yf _. _r..tay] State Yf �)ss -'
Count�1jof-�t��..,.�.�en-o„�n) Iss I \ Count of nl5r5l (�
Ond�.-Y afore me,/l�" l..l.J On 4s�� befor
personally appeared l l? ' personally appeared
personally known to me (dr-pr ed-to-me-on-[hasMo ' personally known to me ( prove o me on h'e- f-
satisfactary-evidencspto be the pton(�whose name(s5}is re sa#isfaetoq-ewdenc2)Yo be the person(s#)whose name(d,J' / re-
subscribed to the within instrument and acknowledged to me subscribed to the within instrument and acknowledged to me
that he/she/they executed the same in his/herlAeir authorized that he/she/they-executed the same in his/her/their authorized
capacity(ies), and that by his/hi signature(i) on the capacity(ies)- and that by hisfher/their signatureO on the
instrument the person( ),or the entity upon behalf of which the instrument the person(R), or the entity upon behalf of which the
person(s Iacted,executed the instrument. person()acted,executed the instrument.'
WITNESS my hand
�jand
official seal. WITNESS my hand and official seal. I )
Notary Signature:UCH - r La Notary Signature:
Notary Seal Notary Seal:
.e
M 19 -yyyvAArRrTd1�i�u1-�
w�
WJC t)Ni�1. A 90t�@( � oT�� g4,AAll 096, va6L
I A�rs
, M'_ % O 1765572 CM1265 2
/ NC1AYtBC CALIF
OTh9Y 11LC-CALII'ORnIA 0 e� � CJY
a) l
111VEnSIDE COUNTY
�I ' -,"-,' rv,�N/ I sy t.nmsn upsrn9 Juro 2� e00A� ¢IL M7 C,mivr.Cxji Ju•ie 24 900,,17
AViHE4O'WMAI S-Pf TWsr; Ic'"q"y
Jo f - s
•
��;. .. � ,�.. ,w. . , ��
"� .,,
CITY OF PALM SPRINGS
NOTICE INVITING BIDS
For constructing:
DEMUTH CENTER RESTROOM FACILITIES
(Tile Work)
City Project 98-20
N-1 NOTICE IS HEREBY GIVEN that informal bids for the DEMUTH CENTER RESTROOM
FACILITIES (Tile Work) will be received at the office of the Director of Procurement and
Contracting of the City of Palm Springs, California, until 5:00 P.M., Friday, April 19, 2002.
N-2 DESCRIPTION OF THE WORK: The Work of this Contract comprises ceramic tile,
painting, and appurtenant work as shown in the Project Drawings, consisting of the following:
1) Furnishing and installing building paper, lathing and plastering for backing for exterior
ceramic tile walls
2) Furnishing and installing ceramic wall the over Portland cement concrete scratch and brown
coat base
3) Furnishing and installing anti-graffiti coatings on all exterior ceramic tile walls
4) Furnishing and installing finish painting
N-3 STANDARD SPECIFICATIONS:
All work included in this contract shall comply with the attached technical specifications.
N-4 ADDRESS AND MARKING OF BIDS: Informal bids shall be delivered or mailed to the
Director of Procurement and Contracting at 3200 East Tahquitz Canyon Way, Palm Springs,
CA 92262.
CITY OF PALM SPRINGS
SPECIFICATIONS
PART III - TECHNICAL SPECIFICATIONS
DIVISION 1 - GENERAL REQUIREMENTS
Section 01011 - Summary of Work
Section 01092 - Reference Standards
& Abbreviations
Section 01201 - Project Meetings
Section 01301 - Contractor Submittals
Section 01401 - Quality Control
Section 01505 - Mobilization
Section 01511 - Temporary Utilities
Section 01541 - Protection of Existing
Facilities
Section 01551 - Site Access and Parking
Section 01561 - Temporary Environmental
Controls
Section 01601 - Materials & Equipment
Section 01701 - Contract Closeout
DIVISION 2 - SITEWORK
NOT USED
DIVISION 3 - CONCRETE
NOT USED
DIVISION 4 - MASONRY
NOT USED
DIVISION 5 - METALS
NOT USED
DIVISION 6 - WOOD & PLASTICS
NOT USED
DIVISION 7 - THERMAL & MOISTURE CONTROL
NOT USED
DIVISION 8 - DOORS & WINDOWS
NOT USED
DIVISION 9 - FINISHES
DEMUTH CENTER RESTROOM FACILITIES CONTENTS
CITY PROJECT NO. 98-20 PART III
5/24/02
0
Section 09200 - Lath and Plaster
Section 09311 - Ceramic Tile
Section 09831 - Anti-graffiti coating
Section 09900 - Painting
DIVISION 10 - SPECIALITIES
NOT USED
DIVISION 11 - EQUIPMENT
NOT USED
DIVISION 12 - FURNISHINGS
NOT USED
DIVISION 13 - SPECIAL CONSTRUCTION
NOT USED
DIVISION 14 - CONVEYING SYSTEMS
NOT USED
DIVISION 15 - MECHANICAL
NOT USED
DIVISION 16 - ELECTRICAL
NOT USED
PART IV - APPENDICES
NOT USED
DEMUTH CENTER RESTROOM FACILITIES CONTENTS
CITY PROJECT NO 98-20 PART III
5124/02
SECTION 01011
SUMMARY OF WORK
1 . 01 GENERAL
A. The Work to be performed under this Contract shall consist
of furnishing all plant, tools, equipment, materials,
supplies, and manufactured articles for the Project. It
shall also include the furnishing of all transportation
and services, including fuel, power, water, and essential
communications, and for the performance of all labor,
work, or other operations required for the fulfillment of
the Contract in strict accordance with the Contract
Documents .
1 . 02 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of this Contract comprises furnishing and
installing ceramic tile, metal trim, and exterior coatings
on the exterior walls of a new prefabricated restroom
facility at the Demuth Park on Mesquite Avenue in Palm
Springs, California. The Contractor' s work on site
includes, but is not limited to:
1) Furnishing and installing building paper, lathing and
plastering for backing for exterior ceramic tile walls
2) Furnishing and installing ceramic wall tile over Portland
cement concrete scratch and brown coat base
3) Furnishing and. installing anti-graffiti coatings on all
exterior ceramic tile walls
1 .03 BEGINNING AND COMPLETION OF THE WORK
A Time is of the essence of the Contract . The Contractor
shall begin the Work on the date specified in the written
Notice to Proceed from the City, and shall complete all of
the Work included in the Contract within 20 working days
after delivery on site of the prefabricated restroom
building. Time stated for completion shall include final
cleanup of the premises .
1. 04 CONTRACT METHOD
A. The Work, hereunder will be constructed under a single
lump sum contract .
DEMUTH CENTER RESTROOM FACILITIES MEASUREMENT AND PAYMENT
CITY PROJECT NO, 98-20 SECTION 01026-PAGE 1
5/24/02
1 . 05 ORDER OF THE WORK
A. The Work shall be carried on at such places on the project
and also in such order or precedence as may be found
necessary by the City' s representative to expedite
completion of the Project. After work has begun on any
portion of a designated part of the Project, it shall be
carried forward to its final completion as rapidly as
practicable. The order and time to complete shall conform
to the requirements of the approved Contractor' s schedule
as submitted under the provisions for "Contractor' s
Schedules" in Section 01301, "Contractor Submittals . "
1 . 06 BASE LINES AND GRADES
A. Contractor' s Layout: The Contractor shall furnish at its
own expense all such stakes, templates, platforms, ranges,
gages, equipment, tools, materials, and all labor as
required in laying out any and all parts of the Work.
1 .07 CONTRACTOR USE OF PROJECT SITE
A. The Contractor' s use of the project site shall be limited
to its construction operations, including on-site storage
of materials, on-site fabrication facilities, and field
offices .
1 .08 CITY USE OF THE PROJECT SITE
A. When the Contractor' s work involves rehabilitation of or
extension to the existing facilities, the City may utilize
all or part of the existing site during the entire period
of construction for the conduct of the City' s normal
operations . The Contractor shall cooperate with the City
Engineer to minimize interference with the Contractor ' s
operations and to facilitate the City' s operations . In
any event, the City and the Engineer and their authorized
representatives shall be allowed access to the project
site at all times during the period of construction.
END OF SECTION
DEMUTH CENTER RESTROOM FACILITIES MEASUREMENT AND PAYMENT
CITY PROJECT NO, 98-20 SECTION 01026-PAGE 2
5124/02
SECTION 01092
REFERENCE STANDARDS
AND ABBREVIATIONS
1 . 01 GENERAL
A. Titles of Sections and Paragraphs : Captions accompanying
specification sections and paragraphs are for convenience
of reference only, and do not form a part of the
Specifications .
B. Applicable Publications : Whenever in these specifications
references are made to published specifications, codes,
standards, or other requirements, it shall be understood
that wherever no date is specified, only the latest
specifications, standards, or requirements of the
respective issuing agencies which have been published as
of the date that the Work is advertised for bids, shall
apply; except to the extent that said standards or
requirements may be in conflict with applicable laws,
ordinances, or governing codes . No requirements set forth
herein or shown on the drawings shall be waived because of
any provision of, or omission from, said standards or
requirements .
1 .02 REFERENCE SPECIFICATIONS, CODES, AND , STANDARDS
A. Without limiting the general provisions of other portions
of the specifications, all work specified herein shall
conform to or exceed the requirements of all applicable
codes and the applicable requirements of the following
documents to the extent that the provisions of such
documents are not in conflict with the requirements of
these Specifications nor the applicable codes .
B. References herein to codes shall mean the following listed
codes, as adopted by the City of Palm Springs, including
all addenda, modifications, amendments, or other lawful
changes thereto:
Uniform Building Code, 1997 Edition, as published by
the International Conference of Building Officials
(ICBO)
Uniform Plumbing Code, 1997 Edition, as published by
the International Association of Plumbing and
Mechanical Officials (IAPMO)
REFERENCE STANDARDS
DEM LITH CENTER RESTROOM FACILITIES AND ABBREVIATIONS
CITY PROJECT NO. 98-20 SECTION 01092 -PAGE 1
5/24/02
0 0
Uniform Mechanical Code, 1997 Edition, as Published
by the International Conference of Building Officials
(ICBO)
National Electrical Code, 1994 Edition, as Published
by the National Fire Protection Association (NFPA)
California Code of Regulations, Title 19 Public
Safety, and Title 24 Building Standards .
C. In case of conflict between codes, reference standards,
drawings and the other Contract Documents, the most
stringent requirements shall govern. All conflicts shall
be brought to the attention of the Engineer for
clarification and directions prior to ordering or
providing any materials or labor. The Contractor shall
bid the most stringent requirements .
D. Applicable Standard Specifications : The contractor shall
construct the Work specified herein in accordance with the
requirements of the Contract Documents and the referenced
portions of those referenced codes, standards, and
specifications listed herein; except, that whenever
references to "Standard Specifications" are made, the
provisions therein for measurement and payment shall not
apply-
E. References in the Contract Documents to "Standard
Specifications" shall mean the Standard Specifications for
Public Works Construction ( "Green Book") , 2000 Edition
including all current supplements, addenda, and revisions
thereof.
F. Applicable Safety Standards : References herein to "Cal-
OSHA" shall mean State of California, Department of
Industrial Relations, Construction Safety Orders, as
amended to Date, and all changes and amendments thereto
which are effective as of the date of construction.
G. References herein to "OSHA Standards" shall mean Title 29,
Part 1910, Occupational Safety and Health Standards, Code
of Federal Regulations] (OSHA) , including all changes and
amendments thereto.
1 .03 ABBREVIATIONS AND ACRONYMS
A. Wherever in these Specifications references are made to
the standards, specifications, or other published data of
the various national, regional, or local organizations,
REFERENCE STANDARDS
CITYU R CENTER , 98-20 OM FACILITIES AND ABBREVIATIONS
CITY PROJECT NO. 98-20
5/24/02 SECTION 01092-PAGE 2
such organizations may be referred to by their acronym or
abbreviation only. As a guide to the user these
specifications, the following acronyms or abbreviations
which may appear in these specifications shall have the
meanings indicated herein.
ACI American Concrete Institute
AGO Associated General Contractors
ANSI American National Standards Institute, Inc.
APA American Plywood Association
ASTM American Society for Testing and Materials
AWPA American Wood Preservers Association
AWPI American Wood Preservers Institute
AWS American Welding Society
AWWA American Water Works Association
Cal-OSHA California Construction Safety Orders
CBM Certified Ballast Manufacturer ' s
CLPCA California Lathing & Plastering Contractors
Association
CRSI Concrete Reinforcing Steel Institute
ETL Electrical Test Laboratories
ICBO International Conference of Building Officials
IEEE Institute of Electrical and Electronics Engineers
IES Illuminating Engineering Society
IPCEA Insulated Power Cable Engineers Association
MBMA Metal Building Manufacturer' s Association
NBS National Bureau of Standards
NEC National Electrical Code
NEMA National Electrical Manufacturer ' s Association
NFPA National Fire Protection Association
NFPA National Forest Products Association
OSHA Occupational Safety and Health Admin. (Federal)
PCA Portland Cement Association
RIS Redwood Inspection Service
SMACCNA Sheet Metal and Air Conditioning
Contractors National Association
SSPC Steel Structures Painting Council
SSPWC Standard Specifications for Public Works
Construction
UBC Uniform Building Code
UL Underwriters Laboratories, Inc.
WCLIB West Coast Lumber Inspection Bureau
WCRSI Western Concrete Reinforcing Steel Institute
WIC Woodwork Institute of California
WRI Wire Reinforcement Institute, Inc.
WWPA Western Wood Products Association
END OF SECTION
REFERENCE STANDARDS
CITYU R CENTER . 98-20 OM FACILITIES AND ABBREVIATIONS
CITY PROJECT NO. 98-20
5/24/02 SECTION 01092 -PAGE 3
SECTION 01201
PROJECT MEETINGS
1 . 01 GENERAL
A The Contractor, along with the Contractor' s Superintendent
or Project Manager, as a minimum, shall attend all
meetings scheduled by the Engineer for coordination and
collection and dissemination of information related to the
Work.
1 .02 PRECONSTRUCTION CONFERENCE
A. Prior to the commencement of Work at the site, a Pre-
construction conference will be held at a mutually agreed
time and place which shall be attended by the Contractor,
its superintendent, and its sub-contractors as
appropriate. Other attendees will be:
1 . Engineer and/or the City' s Project Representative.
2 . Representatives of City.
3 . Others as requested by Contractor, City, or Engineer.
B. Unless previously submitted to the Engineer, the
Contractor shall bring to the conference one copy of each
of the following:
1 . Tentative Construction Schedule .
2 . Shop Drawing/Sample/Substitute or "Or Equal"
submittal schedule.
3 . Schedule of values for progress payment purposes .
C. The purpose of the conference is to designate responsible
personnel and establish a working relationship. Matters
requiring coordination will be discussed and procedures
for handling such matters established. The complete agenda
will be furnished to the Contractor prior to the meeting
date, which may include the following:
1 . Contractor' s tentative schedules .
2 . Transmittal, review, and distribution of Contractor' s
submittals .
3 . Processing applications for payment .
DEMUTH CENTER RESTROOM FACILITIES PROJECT MEETINGS
CITY PROJECT NO, 98-20 SECTION 01201-PAGE 1
5124/02
4 . Maintaining of record documents .
5 . Critical work sequencing.
6 . Field decisions and Change Orders .
7 . Use of project site, office and storage areas,
security, housekeeping, and City' s needs .
8 . Major equipment deliveries and priorities .
9. Contractor' s assignments for safety and first aid.
D. The Engineer will preside at the pre-construction
conference and will arrange for keeping the minutes and
distributing the minutes to all persons in attendance .
1 . 03 PROGRESS MEETINGS
A. After commencement of Work, weekly project coordination
conferences will be held at a mutually agreed time and
place, which shall be attended by the Contractor, its
superintendent, and its sub-contractors as appropriate .
Other attendees may include :
1 . The Engineer and/or City' s Project Representative
2 . Representatives of the City
3 . The Manufacturer' s Representative
4 . Others as requested by Contractor, City or Engineer.
B. The purpose of the Progress Meetings is to maintain
open communication and resolve problems . The complete
agenda will be furnished to the Contractor prior to meeting
date . Subjects may include:
1 . Contractor' s updated schedules
2 . Transmittal, review and distribution of Contractor' s
submittals
3 . Processing applications for payment
4 . Updating of record documents
5 . Critical work sequencing
6 . Field decisions and Change Orders
C. The Engineer will preside at the Progress Meetings and
will arrange for keeping the minutes and distributing the
minutes to all persons in attendance .
END OF SECTION
DEMUTH CENTER RESTROOM FACILITIES PROJECT MEETINGS
CITY PROJECT NO, 98-20 SECTION 01201-PAGE 2
5124/02
SECTION 01301
CONTRACTOR SUBMITTALS
1 . 01 GENERAL
A. The term "submittal" as used herein shall mean any
drawing, calculation, specification, product data,
samples, manuals, requests for substitutes, spare parts,
photographs, survey data, record drawings, bonds, or
similar items required to be submitted to the Engineer
under the terms of the contract .
B. All subcontractor and supplier or fabricator submittals
shall be carefully reviewed by an authorized
representative of the Contractor, prior to submittal to
the Engineer. Each submittal of the Contractor or its
subcontractors and suppliers or fabricators shall be
dated, signed, and certified by the Contractor, as being
correct and in strict conformance with the Contract
Documents . In the case of shop drawings, each sheet shall
be so dated, signed, and certified. No consideration for
review by the Engineer of any Contractor submittals will
be made for any items which have not been so certified by
the Contractor.
C. The Engineer' s review of Contractor submittals shall not
relieve the Contractor of the entire responsibility for
the correctness of details and dimensions . The Contractor
shall assume all responsibility and risk for any misfits
due to any errors in Contractor submittals . The
Contractor shall be responsible for the dimensions and the
design of adequate connections and details .
D. A preliminary schedule of values (lump sum price
breakdown) shall be submitted at the time of the
preconstruction conference for all of the work hereunder
to serve as the basis for progress payments during
construction.
1 . 02 PROPOSED SUBSTITUTES OR "OR EQUAL" ITEMS
A. For convenience in designation in the Contract Documents,
a brand or trade name may be specified. The use of any
substitute material, product, or equipment which is equal
in quality and utility and possesses the required
characteristics for the purpose intended will be
permitted, subject to the following requirements :
DEMUTH CENTER RESTROOM FACILITIES CONTRACTOR SUBMITTALS
CITY PROJECT NO. 98-20 SECTION 01301-PAGE 1
5/24/02
•
1 . The burden of proof as to the quality and utility of
any such substitute material, product, or equipment
shall be upon the Contractor.
2 . The Engineer will be the sole judge as to the quality
and utility of any such substitute material, product,
or equipment and its decision shall be final .
B. The supporting documentation for any proposed substitute
or "or-equal" item must be submitted within 20 days after
the bid opening; otherwise the Contractor agrees to
furnish one of the brand name products specified.
1 . 03 SHOP DRAWINGS
A. Wherever called for in the Contract Documents, or where
required by the Engineer, the Contractor shall furnish to
the Engineer for review, 4 copies of each shop drawing
submittal. The term "Shop Drawings" as used herein shall
be understood to include detail design calculations, shop
drawings, fabrication and installation drawings, erection
drawings, lists, graphs, operating instruction, catalog
sheets, data sheets, and similar items . Unless otherwise
required, said Shop Drawings shall be submitted to the
Engineer at a time sufficiently early to allow review of
same by the Engineer, and to accommodate the rate of
construction progress required under the Contract.
B. Ali Shop Drawings shall be accompanied by the Engineer' s
standard submittal transmittal form. This form may be
obtained in quantity from the Engineer at reproduction
cost . Any submittal not accompanied by such a form, or
where all applicable items on the form are completed, will
be returned for re-submittal .
C. Normally, a separate transmittal form shall be used for
each specific items or class of material or equipment for
which a submittal is required. Transmittal of a submittal
of various items using a single transmittal form will be
permitted only when the items taken together constitute a
manufacturer ' s "package" or are so functionally related
that expediency indicates review of the group or package
as a whole. A multiple-page submittal shall be collated
into sets, and each set shall be stapled or bound, as
appropriate, prior to transmittal to the Engineer.
D. Except as may otherwise be provided herein, the Engineer
will return prints of each submittal to the Contractor
with its comments noted thereon, within 21 calendar days
following their receipt by the Engineer. It is considered
DEMUTH CENTER RESTROOM FACILITIES CONTRACTOR SUBMITTALS
CITY PROJECT NO, 98-20 SECTION 0130'1-PAGE
5/24/02
reasonable that the Contractor shall make a complete and
acceptable submittal to the Engineer by the second
submission of a submittal item. The City reserves the
right to withhold monies due the Contractor to cover
additional cost of the Engineer' s review beyond the second
submittal.
E. If 3 copies of a submittal are returned to the Contractor
marked "APPROVED" or "ACCEPTED" or "NO EXCEPTIONS TAKEN, "
formal revision and resubmission of said submittal will
not be required,
F. If one copy of the submittal is returned to the Contractor
marked "AMEND-RESUBMIT, " the Contractor shall revise said
submittal and shall resubmit 6 copies of said revised
submittal to the Engineer.
G. If one copy of the submittal is returned to the Contractor
marked "REJECTED-RESUBMIT, " the Contractor shall revise
said submittal and shall resubmit 6 copies of said revised
submittal to the Engineer.
H. Fabrication of an item may be commenced only after the
Engineer has reviewed the pertinent submittals and
returned copies to the Contractor marked either "NO
EXCEPTIONS TAKEN" or "APPROVED" or "ACCEPTED" or "MAKE
CORRECTIONS NOTED. " Corrections indicated on submittals
shall be considered as changes necessary to meet the
requirements of the Contract Documents and shall not be
taken as the basis of claims for extra work.
1 . 04 SAMPLES
A. Unless otherwise specified, whenever in the Specifications
samples are required, the Contractor shall submit not less
than 3 units of each such sample item or material to the
Engineer for approval at no additional cost to the City.
B. Samples, as required herein, shall be submitted for
approval prior to ordering such material for delivery to
the job-site, and shall be submitted in an orderly
sequence so that dependent materials or equipment can be
assembled and reviewed without causing delays in the Work.
C. All samples shall be individually and indelibly labeled or
tagged, indicating thereon all specified physical
characteristics and manufacturer' s names for
identification and submittal to the Engineer for approval.
DEM UTH CENTER RESTROOM FACILITIES CONTRACTOR SUBMITTALS
CITY PROJECT NO. 98-20 SECTION 0 13 01-PAGE
5/24/02
• 0
D. Unless otherwise specified, all colors and textures of
specified items will be selected by the Engineer from the
manufacturer ' s standard colors and standard materials,
products, or equipment lines .
1 .05 RECORD DRAWINGS
A. The Contractor shall keep and maintain, at the job site,
one record set of Contract Drawings . On these, it shall
mark all project conditions, locations, configurations,
and any other changes or deviations which may vary from
the details represented on the original Contract Drawings,
including buried or concealed construction and utility
features which are revealed during the course of
construction.
B. Special attention shall be given to recording the
horizontal and vertical location of all buried utilities
that differ from the locations indicated, or which were
not indicated on the Contract Drawings . Said record
drawings shall be supplemented by any detailed sketches as
necessary or directed to indicate, fully, the Work as
actually constructed.
C. These master record drawings of the Contractor' s
representation of "as-built" conditions, including all
revisions made necessary by addenda, change orders, and
the like shall be maintained up-to-date during the
progress of the Work.
D. Final Record Drawings : Upon substantial completion of the
Work and prior to final acceptance by the City, the
Contractor shall complete and deliver the completed set of
Record Drawings to the Engineer for transmittal to the
City, conforming to the construction records of the
Contractor. This set of drawings shall consist of
corrected plans showing the reported location of the Work.
The information submitted by the Contractor and
incorporated by the Engineer into the Record Drawings will
be assumed to be reliable, and the Engineer will not be
responsible for the accuracy of such information, nor for
any errors or omissions which may appear on the Record
Drawings as a result .
DEMUTH CENTER RESTROOM FACILITIES CONTRACTOR SUBMITTALS
CITY PROJECT NO. 98-20 SECTION 01301-PAGE4
5/24/02
E. Effect on Final Payment : Final payment will not be
approved until the Contractor- prepared Final Record
Drawings have been delivered to the Engineer. Said
up-to-date, Record Drawings may be in the form of a set of
prints with carefully plotted information overlaid in
pencil .
END OF SECTION
DEM UTH CENTER RESTROOM FACILITIES CONTRACTOR SUBMITTALS
CITY PROJECT NO. 98-20 SECTION 01301-PAGE 5
5/24/02
SECTION 01401
QUALITY CONTROL
1 . 01 SITE INVESTIGATION AND CONTROL
A. The Contractor shall verify all dimensions in the field
and shall check all field conditions continuously during
construction. The Contractor shall be solely responsible
for any inaccuracies built into the Work.
B. The Contractor shall inspect related and appurtenant work
and shall report in writing to the Engineer any conditions
which will prevent proper completion of the Work. Any
required removal, repair, or replacement caused by
unsuitable conditions shall be done by the Contractor at
its sole cost and expense.
1 . 02 INSPECTION OF THE WORK
A. General : The Work shall be conducted under the general
observation of the Engineer and shall be subject to
intermittent inspection by representatives of the City to
assure strict compliance with the requirements of the
Contract Documents . The presence of an inspector,
however, shall not relieve the Contractor of the
responsibility for the proper execution of the Work in
accordance with all requirements of the Contract
Documents . Compliance is distinctly a duty of the
Contractor, and said duty shall not be avoided by any act
or omission on the part of an inspector.
B. All materials and articles furnished by the Contractor
shall be subject to rigid inspection, and no material or
articles shall be used in the Work until it has been
inspected and accepted by the Engineer for the City.
1 . 03 SAMPLING AND TESTING
A. Unless otherwise specified, all sampling and testing shall
be in accordance with the methods prescribed in the
current standards of the ASTM or other specified published
standards, as applicable to the class and nature of the
article or materials considered; however, the City
reserves the right to use any generally-accepted system of
sampling and testing which, in the opinion of the Engineer
will assure the City that the quality of the workmanship
is in full accord with the Contract Documents .
DEMUTH CENTER RESTROOM FACILITIES QUALITY CONTROL
CITY PROJECT NO 98-20 5/24/02 SECTION 01401-PAGE 1
B. Any waiver by the City of any specific testing or other
quality assurance measures, whether or not such waiver is
accompanied by a guarantee of substantial performance as a
relief from the specified testing or other quality
assurance requirements as originally specified, and
whether or not such guarantee is accompanied by a
performance bond to assure execution of any necessary
corrective or remedial Work, shall not be construed as a
waiver of any prescriptive or performance requirements of
the Contract Documents .
C. Notwithstanding the existence of such waiver, and in
addition to any testing and inspection performed by any
other inspector on behalf of the City or any other public
agency having jurisdiction, the Engineer shall have the
right to make independent investigations and tests, and
failure of any portion of the Work to meet any of the
requirements of the Contract Documents, shall be
reasonable cause for the Engineer to require the removal
or correction and reconstruction of any such work in
accordance with the General Conditions .
1 . 04 TIME OF INSPECTIONS AND TESTS
A. Samples and test specimens required under the Contract
Documents shall be furnished by the Contractor and
prepared for testing in ample time for the completion of
the necessary tests and analyses before the subject
materials or articles are to be used. The Contractor
shall furnish all required test specimens at its own
expense. Except as otherwise provided in the Contract
Documents, performance of the required tests will be by
the City, and all costs therefor will be borne by the
City; except, that the cost of any test which shows
unsatisfactory results shall be borne by the Contractor.
B. Whenever the Contractor is ready to backfill, bury, cast
in concrete, hide, or otherwise cover or make inaccessible
any work under the Contract, the Contractor shall notify
the Engineer not less than 24 hours in advance of
beginning any such work of backfilling, burying, casting
in concrete, hiding, covering, or making inaccessible any
portion of the Work to be inspected, so that the required
inspections can be scheduled and performed. Failure of the
Contractor to notify the Engineer at least 24 hours in
advance of any such inspections shall be reasonable cause
for the Engineer to require sufficient delay in the
Contractor' s schedule to allow time for such inspections
and any remedial or corrective work required, and all
costs of such delays, including its impact or effect upon
DEMUTH CENTER RESTROOM FACILITIES QUALITY CONTROL
CITY PROJECT NO. 98-20 SECTION 01401-PAGE 2
5/24/02
0 •
other portions of the Work shall be borne by the
Contractor.
END OF SECTION
DEMUTH CENTER RESTROOM FACILITIES QUALITY CONTROL
CITY PROJECT NO, 98-20 SECTION 0 1401-PAGE
5/24102
SECTION 01505
MOBILIZATION
1 . 01 GENERAL
A. Mobilization shall include the obtaining of all bonds,
insurance, and permits; moving onto the site of all plant
and equipment; and the furnishing and erecting of plants,
temporary buildings, and other construction facilities;
all as required for the proper performance and completion
of the Work. Mobilization shall include but not be limited
to the following principal items :
1 . Moving on to the site of all Contractor' s plant and
equipment required for first month' s operations .
2 . Installing temporary construction power, wiring, and
lighting facilities per Section 01511 .
3. Establishing fire protection system per Section 01511 .
4 . Developing and installing construction water supply
per Section 01511 .
5 . Providing on-site sanitary facilities and potable
water facilities as specified per Section 01511 .
6. Obtaining and paying for all required permits .
7 . Posting all OSHA required notices and establishment of
safety programs .
8 . Have the Contractor' s superintendent at the job site
full time.
9. Submittal of detailed Preliminary Construction Schedule
at the Pre-construction meeting for the City' s and
Engineer' s approval, per Section 01301
B. In addition to the requirements specified above, all
submittals shall conform to the applicable requirements of
Section 01301 "Contractor Submittals . "
DEMUTH CENTER RESTROOM FACILITIES MOBILIZATION
CITY PROJECT NO. 98-20 SECTION 01505-PAGE 1
5/24/02
0
1 . 02 PAYMENT FOR MOBILIZATION
A. The Contractor ' s attention is directed to the condition
that 5 percent of the total Contract Price will be
deducted from any money due the Contractor as initial
progress payments until all mobilization items listed
above have been completed as specified. The
aforementioned amount will be retained by the City as the
agreed, estimated value of completing all of the
mobilization items listed. Any such retention of money for
failure to complete all such mobilization items as a
lump-sum item shall be in addition to the retention of any
payments due to the Contractor as specified in the
Contract Documents .
B. Payment for mobilization will be made in the form of a
single, lump-sum, non-proratable allowance determined by
the Engineer, and no part thereof will be approved for
payment under the Contract until all mobilization items
listed above have been completed as specified.
END OF SECTION
DEMUTH CENTER RESTROOM FACILITIES MOBILIZATION
CITY PROJECT NO. 98-20 SECTION 01505-PAGE 2
5124/02
SECTION 01511
TEMPORARY UTILITIES
1 . 01 GENERAL
A. It shall be the Contractor' s responsibility to provide
plant and equipment that is adequate for the performance
of the Work under this Contract within the time specified.
All such work shall be subject to inspection and approval
by the Engineer at any time within the duration of the
Contract.
B. All work hereunder shall conform to the applicable
requirements of Cal-OSHA Construction Safety Orders .
1 . 02 POWER AND LIGHTING
A. Power: The Contractor shall use existing electrical power
from existing panel and/or outlets located in adjacent
building.
B. Construction Lighting: All Work conducted at night or
under conditions of deficient daylight shall be suitably
lighted to insure proper Work and to afford adequate
facilities for inspection and safe working conditions .
C. Approval of Electrical Connections : Ail temporary
connections for electricity shall be subject to approval
of the Engineer and the power company representative, and
shall be removed in like manner at the Contractor' s
expense prior to final acceptance of the Work by the City.
D. Separation of Circuits : Unless otherwise permitted by the
Engineer, circuits separate from lighting circuits shall
be used for all power purposes .
E. Construction Wiring: All wiring for temporary electric
light and power shall be properly installed and maintained
and shall be securely fastened in place.
1 . 03 WATER SUPPLY
A. General : The City will furnish, without charge, reasonable
quantities of water required by the Contractor in
performance of the Work under the Contract; however, the
Contractor shall provide all facilities necessary to
convey the water from the City-designated source to the
points of use in accordance with the requirements of the
Contract Documents .
DEMUTH CENTER RESTROOM FACILITIES TEMPORARY UTILITIES
CITY PROJECT NO. 98-20 SECTION 0 1511-PAGE 1
5124/02
1 .04 SANITATION
A. Toilet Facilities : Contractor' s employees may use existing
toilet facilities adjacent to the site .
B. Sanitary and Other Organic Wastes : The Contractor shall
establish a regular daily collection of all sanitary and
organic wastes . All wastes and refuse from sanitary
facilities provided by the Contractor or organic material
wastes from any other source related to the Contractor' s
operations shall be disposed of away from the site in a
manner satisfactory to the Engineer and in accordance with
all laws and regulations pertaining thereto.
1 . 05 TELEPHONE COMMUNICATIONS
A. The Contractor shall provide and maintain at all times
during the progress of the Work, a telephone number where
the Contractor' s on-site representative can be contacted
at all times while the Work is in progress .
END OF SECTION
DEMUTH CENTER RESTROOM FACILITIES TEMPORARY UTILITIES
CITY PROJECT NO. 98-20 SECTION 0 1511-PAGE
5/24102
SECTION 01541
PROTECTION OF EXISTING FACILITIES
1 . 01 GENERAL
A. The Contractor shall protect all existing utilities and
improvements not designated for removal and shall restore
damaged or temporarily relocated utilities and
improvements to a condition equal to or better than they
were prior to such damage or temporary relocation, all in
accordance with requirements of the Contract Documents .
B. The Contractor shall verify the exact locations and depths
of all utilities shown and the Contractor shall make
exploratory excavations of all utilities that may
interfere with the Work. All such exploratory excavations
shall be performed as soon as practicable after award of
contract and, in any event, a sufficient time in advance
of construction to avoid possible delays to the
Contractor' s work. When such exploratory excavations show
the utility location as shown to be in error, the
Contractor shall so notify the Engineer.
C. The number of exploratory excavations required shall be
that number which is sufficient to determine the alignment
and grade of the existing utility line.
1 .02 RIGHTS-OF-WAY
A. The Contractor shall not do any work that would affect any
oil, gas, sewer, or water pipeline; any telephone,
telegraph, or electric transmission line; any fence; or
any other structure, nor shall the Contractor enter upon
the rights-of-way involved until notified by the Engineer
that the City has secured authority therefor from the
proper party. After authority has been obtained, the
Contractor shall give said party due notice of its
intention to begin work, and shall give said party
convenient access and every facility for removing,
shoring, supporting, or otherwise protecting such
pipeline, transmission line, ditch, fence, or structure,
and for replacing same.
END OF SECTION
DEMUTH CENTER RESTROOM FACILITIES PROTECTION OF EXISTING FACILITIES
CITY PROJECT NO 98-20 SECTION 01541-PAGE 1
5/24102
SECTION 01551
SITE ACCESS AND PARKING
1 . 01 GENERAL
A. The Contractor shall take all necessary precautions for
the protection of the Work and the safety of the public.
All barricades and obstructions shall be illuminated at
night, and all lights shall be kept burning from sunset
until sunrise. The Contractor shall station such guards
or flaggers and shall conform to such special safety
regulations relating to traffic control as may be required
by the public authorities within their respective
jurisdictions . All signs, signals, and barricades shall
conform to the requirements of Caltrans "Manual of Traffic
Controls - Warning Signs, Lights, and Devices for Use in
Performance of Work Upon Highways . "
1 . 02 HIGHWAY LIMITATIONS
A. The Contractor shall make its own investigation of the
condition of available access routes to and from the site
of the Work. If suitable access is not available, it shall
be the Contractor' s responsibility to construct and
maintain any access or haul roads required for its
construction operations .
1 . 03 PARKING
A. The area for Contractor' s employees will be limited to
the west side of the parking lot adjacent to the project
site. Specific spaces will be identified by the City.
1 . 04 MATERIAL AND DUMPSTER LOCATION
A. An area convenient to access the area of work will be
identified by the City in co-operation with the
Contractor.
END OF SECTION
DEMUTH CENTER RESTROOM FACILITIES SITE ACCESS AND PARKING
CITY PROJECT NO 98-20 SECTION 01551-PAGE 1
5/24/02
SECTION 01561
TEMPORARY ENVIRONMENTAL CONTROLS
1 . 01 EXPLOSIVES AND BLASTING
A. The use of explosives on the Work will NOT be permitted.
1 . 02 DUST ABATEMENT
A. The Contractor shall furnish all labor, equipment, and means
required and shall carry out effective measures wherever and as
often as necessary to prevent its operation from producing dust
in amounts damaging to property, cultivated vegetation, or
domestic animals, or causing a nuisance to persons living in or
occupying buildings in the vicinity. The Contractor shall be
responsible for any damage resulting from any dust originating
from its operations . The dust abatement measures shall be
continued until the Contractor is relieved of further
responsibility by the Engineer.
B. The Contractor shall be responsible for maintaining the project
site and providing adequate dust control 24 hours a day,
everyday, through the duration of the project, in conformance
with City requirements, Section 7-8 of the Standard
Specifications, and to the satisfaction of the City Engineer.
1 .03 RUBBISH CONTROL
A. During the progress of the Work, the Contractor shall keep the
site of the Work and other areas used by it in a neat and clean
condition, and free from any accumulation of rubbish. The
Contractor shall dispose of all rubbish and waste materials of
any nature occurring at the Work site, and shall establish
regular intervals of collection and disposal of such materials
and waste.
B. Contractor shall also keep its haul roads free from dirt,
rubbish, and unnecessary obstructions resulting from its
operations . Disposal of all rubbish and surplus materials shall
be off the site of construction in accordance with local codes
and ordinances governing locations and methods of disposal, and
in conformance with all applicable safety laws .
DEMUTH CENTER RESTROOM FACILITIES TEMPORARY ENVIRONMENTAL CONTROLS
CITY PROJECT NO. 98-20 SECTION 01561-PAGE 1
5124/02
1 .04 CHEMICALS
A. All chemicals used during project construction or furnished for
project operation, whether defoliant, soil sterilant, herbicide,
pesticide, disinfectant, polymer, reactant or of other
classification, shall show approval of either the U. S .
Environmental Protection Agency or the U. S . Department of
Agriculture . Use of all such chemicals and disposal of residues
shall be in strict accordance with the printed instructions of
the manufacturer.
END OF SECTION
DEMUTH CENTER RESTROOM FACILITIES TEMPORARY ENVIRONMENTAL CONTROLS
CITY PROJECT NO. 98-20 SECTION 01561-PAGE 2
5/24102
SECTION 01601
MATERIALS AND EQUIPMENT
1 . 01 GENERAL
A. The word "Products, " as used herein, is defined to include
purchased items for incorporation into the Work, regard-
less of whether specifically purchased for project or taken
from Contractor' s stock of previously purchased products .
The word "Materials, " is defined as products which must be
substantially cut, shaped, worked, mixed, finished, refined,
or otherwise fabricated, processed, installed, or applied to
form units of work. The word "Equipment" is defined as
products with operational parts, regardless of whether
motorized or manually operated, and particularly including
products with service connections (wiring, piping, etc. ) .
Definitions in this paragraph are not intended to negate the
meaning of other terms used in Contract Documents, including
"specialties, " "systems, " "structure, " "finishes, "
"accessories, " "furnishings, " "special construction, " and
similar terms, which are self-explanatory and have
recognized meanings in the construction industry.
1 .02 QUALITY ASSURANCE
A. Source Limitations : To the greatest extent possible for each
unit of work, the Contractor shall provide products,
materials, or equipment of a singular generic kind from a
single source.
B. Compatibility of Options : Where more than one choice is
available as options for Contractor ' s selection of a
product, material, or equipment, the Contractor shall select
an option which is compatible with other products,
materials, or equipment already selected. Compatibility is
a basic general requirement of product/material selections .
1 . 03 MATERIALS
A. Quantities . - The Contractor shall submit with each of its
billing invoices, a corrected list of quantities, verified
by the Engineer, for unit price items listed in the Bid
Schedule or Schedule of Values .
B. Placing Orders . - The Contractor shall place the order (s)
for all long-lead supplies, materials, and equipment, for
any traffic signing, striping, legends, and traffic control
facilities within 3 working days after the award of Contract
by the City.
DEMUTH CENTER RESTROOM FACILITIES MATERIALS AND EQUIPMENT
CITY PROJECT NO. 98-20 SECTION 01601-PAGE 1
5/24/02
0 •
C. The Contractor shall furnish the Engineer with a statement
from the vendor (s) that the order (s) for said supplies,
materials, and equipment has been received and accepted by
said vendor (s) within 15 working days from the date of said
award of Contract .
1 . 04 SERVICING OF EQUIPMENT
A. All equipment designated to be installed in the Work,
whether temporarily stored at the site or installed in
place, shall be serviced on a regularly scheduled basis, and
a written log of services shall be maintained and submitted
as a record document to the Engineer.
END OF SECTION
DEMUTH CENTER RESTROOM FACILITIES MATERIALS AND EQUIPMENT
CITY PROJECT NO. 98-20 SECTION 01601-PAGE 2
5/24/02
SECTION 01701
CONTRACT CLOSEOUT
1 . 01 FINAL, CLEANUP
A. The Contractor shall promptly remove from the vicinity of
the completed Work, all rubbish, debris, unused materials,
concrete forms, construction equipment, and temporary
structures and facilities used during construction. Final
acceptance of the Work by the City will be withheld until
the Contractor has satisfactorily complied with the
foregoing requirements for final cleanup of the project
site.
1 . 02 CLOSEOUT TIMETABLE
A. The Contractor shall establish dates for equipment
testing, acceptance periods, (as required under the
Contract) . Such dates shall be established not less than
one week prior to beginning any of the foregoing items, to
allow the City, the Engineer, and their authorized
representatives and consultants sufficient time to
schedule attendance at such activities .
B. All temporary buildings and sheds shall be removed from
the project site within 7 days after completion of the
Work as defined in the Contract Documents . All temporary
utilities and other temporary services shall remain in
service for 7 days following completion of the Work, and
shall be discontinued within 7 days after said completion
of the Work.
1 . 03 FINAL SUBMITTALS
A. The Contractor, prior to requesting its final progress
payment, shall submit the following items to the Engineer
for transmittal to the City:
1 . Written guarantees or warranties, where required
2 . Operating manuals and instructions
3 . Maintenance stock items; spare parts; special tools
4 . Completed final Record Drawings
S . Bond for correction and repair period
DEMUTH CENTER RESTROOM FACILITIES CONTRACT CLOSEOUT
CITY PROJECT NO. 98-20 SECTION 01701 -PAGE 1
5124/02
6. Certificates of inspection and acceptance by local
governing agencies having jurisdiction
7 . Releases executed by property owners or residents
adjacent to the project site attesting that the
Contractor has restored any damage done to their
property during construction.
8 . Releases from all parties who are entitled to claims
against the subject project, property, or improvement
pursuant to the provisions of law.
1 . 04 COMPLETION OF THE WORK
A. Completion of the Work, as the term is used in this
Contract shall mean substantial completion of the Work and
acceptance by the City. Substantial completion shall mean
substantial performance of the Contract, which shall exist
where there has been no willful departure from the terms
of the Contract, and no omission in essential points, and
the Contract has been honestly and faithfully performed in
its material and substantial particulars, and the only
variance consists of technical or relatively unimportant
omissions or defects, and the Work can be used or occupied
for the purpose for which it was intended.
B. The date of substantial completion of the Project shall be
the date when the construction is sufficiently completed,
in accordance with the Contract Documents, as modified by
any change orders agreed to by the parties, so that the
City can occupy or utilize the project for the use for
which it was intended, and the legislative body of the
City has accepted the Project as evidenced by execution
and recording of a Notice of Completion.
1 . 05 REMAINING PUNCH LIST ITEMS
A. Upon attaining completion/substantial completion as
determined by the City' s representative and upon
acceptance of the Work by the City, by agreement between
the parties some small remaining punch list items may
remain to be completed by the Contractor, as provided
under the provisions for "Completion of the Work" in
Paragraph 1 . 04A, herein.
B. The City shall have the right to retain an additional
amount of money from the final progress payment due the
Contractor, equal to 1 . 5 times the Engineer' s estimate of
the value of such uncompleted punch list items . The
Contractor hereby agrees to complete all such outstanding
DEMUTH CENTER RESTROOM FACILITIES CONTRACT CLOSEOUT
CITY PROJECT NO. 98-20 SECTION 01701 -PAGE 2
5/24102
punch list items within 30 calendar days following the
date of the Notice of Completion and acceptance of the
Work by the City.
C. Failure of the Contractor to complete or correct all such
outstanding punch list work to the satisfaction of the
Engineer within 30 calendar days following acceptance and
Notice of Completion, shall constitute a waiver by the
Contractor of all rights to any and all claims it may have
to all monies withheld by the City under the Contract to
cover the value of such uncompleted or uncorrected items .
1 . 6 CORRECTION AND REPAIR
A. The Contractor shall comply with the following correction
and repair requirements :
ARTICLE 13 -- WARRANTY AND GUARANTEE; TESTS AND INSPECTIONS; CORRECTION,
REMOVAL, OR ACCEPTANCE OF DEFECTIVE WORK
13.1 Warranty and Guarantee:
The CONTRACTOR warrants and guarantees to the CITY and the ENGINEER that all work will be in
accordance with the Contract Documents and will not be defective. Neither the right to inspect, nor the
presence of inspectors, the ENGINEER, consultants, or testing agencies hired by the CITY or the
ENGINEER, nor their general review or approval shall relieve the CONTRACTOR from its obligations to
perform the WORK in accordance with the Contract Documents. All defective WORK, whether or not in
place.
13.2 Notice of Defects:
Prompt notice of all defective Work of which the CITY or the ENGINEER have actual knowledge will be
given to the CONTRACTOR.All defective Work may be rejected, corrected, or accepted as provided in this
Article 13.
13.3 Access to the WORK:
The CITY, the ENGINEER the ENGINEER's Consultants, other representatives and personnel of the CITY
and the ENGINEER, independent testing laboratories and governmental agencies with jurisdictional
interests shall have access to the WORK at reasonable times for their observation, inspecting, and testing.
The CONTRACTOR shall provide them with proper and safe conditions for such access and advise them of
the CONTRACTOR's site safety procedures and programs so that they may comply therewith as
applicable..
13.4 Tests and Inspections:
a. The CONTRACTOR shall give the ENGINEER timely notice of readiness of the WORK for all
required inspections, tests or approvals, but in no event less than 24 hours notice. The CONTRACTOR
shall cooperate with inspection and testing personnel to facilitate required inspections or tests.
b. The CITY will employ and pay for the services of an independent testing laboratory to perform all
inspections,tests,or approvals required by the Contract Documents except:
1. for inspections,tests or approvals covered by paragraph 13.4c below;
2. that costs Incurred in connection with tests or inspections conducted pursuant to paragraph 13.51b
below shall be paid as provided in said paragraph 13.51b; and
DEMUTH CENTER RESTROOM FACILITIES CONTRACT CLOSEOUT
CITY PROJECT NO. 98-20 SECTION 01701 -PAGE 3
5/24/02
3. as otherwise specifically provided in the Contract Documents.
C. If Laws or Regulations of any public body having jurisdiction require any Work (or part thereof)
specifically to be inspected,tested or approved by an employee or other representative of such public body,
the CONTRACTOR shall assume full responsibility for arranging and obtaining such inspections, tests or
approvals, pay all costs in connection therewith, and furnish the ENGINEER the required certificates of
inspection, or approval.The CONTRACTOR shall also be responsible for arranging and obtaining and shall
pay all costs in connection with any inspections, tests or approvals required for the CITY's and the
ENGINEER's acceptance of materials or equipment to be incorporated in the Work, or of materials, mix
designs, or equipment submitted for approval prior to the CONTRACTOR's purchase thereof for
incorporation in the WORK
d. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by the
CONTRACTOR without written concurrence of the ENGINEER, it shall, if requested by the ENGINEER, be
uncovered for observation.
e. Uncovering Work as provided In paragraph 13.4d shall be at the CONTRACTOR's expense unless
the CONTRACTOR has given the ENGINEER timely notice of the CONTRACTOR's intention to cover the
same and the ENGINEER has not acted with reasonable promptness in response to such notice.
13.5 Uncovering Work:
a. If any WORK is covered contrary to the written request of the ENGINEER, it shall , if requested by the
ENGINEER, be uncovered for the ENGINEER's observation and replaced at the CONTRACTOR's
expense.
b. If the ENGINEER considers it necessary or advisable that covered Work be observed by the
ENGINEER or inspected or tested by others, the CONTRACTOR, at the ENGINEER's request, shall
uncover, expose, or otherwise make available for observation, inspection, or testing, as the ENGINEER
may require, that portion of the WORK in question, and shall furnish all necessary labor, material, and
equipment. If it is found that such Work is defective,the CONTRACTOR shall pay all claims, costs, losses
and damages caused by, arising out of or resulting from such uncovering, exposure, observation,
inspection, and testing and of satisfactory replacement or reconstruction, including but not limited to all
costs of repair or replacement of work of others); and the CITY shall be entitled to an appropriate decrease
in the Contract Price, and, if the parties are unable to agree as to the amount thereof, may make a claim
therefor as provided in the Contract Documents.
C. The CONTRACTOR shall permit on-site video taping,still photography,or motion picture photography
of the construction project. The CITY will notify the CONTRACTOR prior to the commencement of any
video taping and/or photography by the CITY personnel and/or its agents and shall make a reasonable
effort to give the CONTRACTOR at least 24 hours of its intent to video tape or photograph the project.The
CONTRACTOR shall cooperate with and shall coordinate with CITY personnel or their authorized
representatives in its efforts to carry out such video taping and/or photography. The CONTRACTOR shall
give notice to all employees and subcontractors of such video taping and/or photography to be out of view
of the camera, If requested to do so,during video taping and or photographing of the construction project.
13.6 CITY May Stop the WORK:
If the WORK is defective, or the CONTRACTOR fails to supply sufficient skilled workers or suitable
materials or equipment, or fails to furnish or perform the Work in such a way that the completed WORK will
conform to the Contract Documents, the CITY, acting independently or through the Project Representative,
may order the CONTRACTOR to stop the WORK, or any portion thereof, until the cause for such order has
been eliminated; however,this right of the CITY to stop the WORK shall not give rise to any duty on the part
of the CITY to exercise this right for the benefit of the CONTRACTOR or any surety or other party.
13.7 Correction or Removal of Defective WORK:
If required by the ENGINEER, acting directly or through the Project Representative, the CONTRACTOR
shall promptly, as directed, either correct all defective WORK, whether or not fabricated, installed or
completed, or, if the WORK has been rejected by the ENGINEER,the CONTRACTOR shall remove it from
the site and replace it with Work that is not defective The CONTRACTOR shall pay all claims, costs,
DEMUTH CENTER RESTROOM FACILITIES CONTRACT CLOSEOUT
CITY PROJECT NO 98-20 SECTION 01701 -PAGE
5/24/02
losses, and damages caused by or resulting from such correction or removal (including but not limited to all
costs of repair or replacement of the Work of others).
13.8 Correction Period:
a. If within one year after the date of Substantial Completion or such longer period of time as may be
prescribed by Laws or Regulations or by the terms of any applicable special guarantee required by the
Contract Documents or by any specific provision of the Contract Documents, any WORK is found to be
defective, the CONTRACTOR shall promptly, without cost to the CITY and in accordance with the CITY's
written instructions: (i) correct such defective WORK, or, if it has been rejected by the CITY, remove it from
the site and replace it with Work that Is not defective, and (ii) satisfactorily correct or remove and replace
any damage to other Work or the work of others resulting therefrom. If the CONTRACTOR does not
promptly comply with the terms of such instructions, or in an emergency where delay would cause serious
risk of loss or damage, the CITY may have the defective WORK corrected or the rejected WORK removed
and replaced, and all direct, indirect and consequential costs of such removal and replacement, including
claims, costs, losses and damages caused by or resulting from such removal and replacement (including
but not limited to all costs of repair or replacement of work of others)will be paid by the CONTRACTOR.
b. In special circumstances where a particular item of equipment is placed in continuous service before
Substantial Completion of all the WORK,the correction period for that item may start to run from an earlier
date if so provided in the Contract Documents.
C. Where defective Work(and damage to other Work resulting therefrom) has been corrected, removed
or replaced under this Article 13.8, the correction period hereunder with respect to such Work will be
extended for an additional period of one year after such correction or removal and replacement has been
satisfactorily completed.
d. Unless otherwise provided in the Supplementary General Conditions, the CONTRACTOR shall
provide a post-construction, correction and repair Performance Bond In the amount of 100 percent of the
Contract Price to cover all correction and repairs or other corrective work required hereunder, and shall
maintain such Bond in full force and effect for one full year following the Notice of Completion.
13.9 Acceptance of Defective WORK:
If, instead of requiring correction or removal and replacement of defective Work,the CITY(and, prior to the
ENGINEER's recommendation of final payment, also the ENGINEER) prefers to accept it,the CITY may do
so. The CONTRACTOR shall pay all claims, costs, losses and damages attributable to the CITY's
evaluation of and determination to accept such defective WORK (such costs to be subject to approval by
the ENGINEER as to reasonableness). If any such acceptance occurs prior to the ENGINEER's
recommendation of final payment, a Change Order will be issued incorporating the necessary revisions in
the Contract Documents with respect to the WORK; and the CITY shall be entitled to an appropriate
decrease in the Contract Price, and, if the parties are unable to agree as to the amount thereof, the CITY
may make a claim therefor as provided in the Contract Documents. If the acceptance occurs after such
recommendation,an appropriate amount will be paid by the CONTRACTOR to the CITY.
13.10The CITY May Correct Defective Work:
If the CONTRACTOR fails within a reasonable time after written notice from the ENGINEER to correct
defective Work or to remove and replace rejected Work as required by the ENGINEER in accordance with
Article 13.7, or if the CONTRACTOR fails to perform the Work in accordance with the Contract Documents,
or if the CONTRACTOR fails to comply with any other provision of the Contract Documents, CITY may,
after 7 days' written notice to the CONTRACTOR, correct and remedy any such deficiency. In exercising
the rights and remedies under this paragraph the CITY shall proceed expeditiously. In connection with such
corrective and remedial action, the CITY may exclude the CONTRACTOR from all or part of the site, take
possession of all or part of the Work, and suspend the CONTRACTOR's services related thereto, take
possession of the CONTRACTOR's tools, appliances, construction equipment and machinery at the site
and incorporate in the Work all materials and equipment stored at the site or for which the CITY has paid
the CONTRACTOR but which are stored elsewhere. The CONTRACTOR shall allow the CITY, the CITY's
representatives, agents and employees, the CITY's other contractors and the ENGINEER and the
ENGINEER's Consultants access to the site to enable the CITY to exercise the rights and remedies under
this paragraph.All claims, costs, losses and damages incurred or sustained by the CITY in exercising such
rights and remedies will be charged against the CONTRACTOR and a Change Order will be issued
incorporating the necessary revisions in the Contract Documents with respect to the Work; and the CITY
DEMUTH CENTER RESTROOM FACILITIES CONTRACT CLOSEOUT
CITY PROJECT NO 98-20 SECTION 01701 -PAGE
5/24/02
shall be entitled to an appropriate decrease in the Contract Price, and, if the parties are unable to agree as
to the amount thereof, the CITY may make a claim therefor as provided in the Contract Documents. Such
claims, costs, losses and damages will include but not be limited to all costs of repair or replacement of
work of others destroyed or damaged by correction, removal or replacement of the CONTRACTOR's
defective Work. The CONTRACTOR shall not be allowed an extension of the Contract Times because of
any delay in the performance of the Work attributable to the exercise by the CITY of the CITY's rights and
remedies hereunder.
B. The Contractor shall make all repairs and replacements
promptly upon receipt of written order from the City. If
the Contractor fails to make such repairs or replacements
promptly, the City reserves the right to do the work or to
have the work done by others and the Contractor and its
Surety shall be liable to the City for the cost thereof.
END OF SECTION
DEMUTH CENTER RESTROOM FACILITIES CONTRACT CLOSEOUT
CITY PROJECT NO. 98-20 SECTION 01701 -PAGE 6
5124/02
SECTION 09200
LATH AND PLASTER
PART 1 - GENERAL
1 . 1 DESCRIPTION:
A. Provide Lathing and Plastering for backing for exterior
ceramic tile walls where shown on the drawings, as
specified herein, and as needed for a complete and
proper installation.
1 . 2 RELATED WORK:
A. Related Work Specified Elsewhere :
1 . Documents affecting work of this Section include,
but are not necessary limited to the Standard
Specifications and these technical provisions .
2 . Section 09311 - Ceramic Tile
1 . 3 WORK INCLUDED:
A. Work includes lath and cement plaster for:
1 . Exterior base coats for ceramic tile wall
surfaces .
1 . 4 QUALITY ASSURANCE:
A. Regulatory Requirements :
1 . Comply with applicable codes and regulations of
governmental agencies having jurisdiction.
2 . Where requirements of applicable codes,
regulations and standards conflict with this
specification, comply with the more stringent
provisions .
1 . 5 PROJECT CONDITIONS :
A. Environmental Requirements :
1 . Protect cement plaster from uneven and excessive
evaporation during hot, dry weather. Protect
adjacent surfaces from plastering material by
masking to avoid unnecessary cleaning.
DEMUTH CENTER RESTROOM FACILITIES LATH AND PLASTER
CITY PROJECT NO 98-20 SECTION 09200- PAGE 1
5/24/02
PART 2 - PRODUCTS
2 . 1 PLASTER MATERIALS :
A. Portland Cement : ASTM C 150, Type 1 .
B. Aggregates : ASTM C 144 clean and well graded sand.
C. Water: Potable.
2 . 2 LATH MATERIALS :
A. Stucco-Rite stucco lath: Type SFB self-furring metal
lath with type 1, Grade "D" double waterproofed
breather building paper backing, laminated to the back
of absorbent paper separator as manufactured by K-Lath,
1801 South Mountain Ave . , Monrovia, CA 91016 or equal .
B. Moldings, Trim and Screeds : as denoted and detailed on
the Drawings shall consist of extruded aluminum alloy
6063 T5 with clear anodized finish as manufactured by
Fry Reglet Corporation, 625 S . Palm Ave . , Alhambra CA
91803 . All joints shall be cut accurately and installed
with tight neat joints . All corners and intersections
shall be coped and mitered. Install trim in accordance
with details on the drawings complete with clear
anodized . 040 breakmetal aluminum and clear silicone
sealant .
C. Expansion joints : Install back-to-back aluminum "J"
trim with colored elastomeric sealant to match grout
color as detailed on the drawings . Install in locations
as noted to align with joints in base sheathing joints .
D. Horizontal reveals : Provide as detailed on the drawings
with . 040 breakmetal aluminum strip, silicone sealant
and pop rivets .
E. Exposed exterior corners : Provide as detailed on the
drawings with . 040 breakmetal aluminum angle, silicone
sealant and pop rivets .
DEMUTH CENTER RESTROOM FACILITIES LATH AND PLASTER
CITY PROJECT NO. 98-20 SECTION 09200 - PAGE2
5/24/02
2 . 3 MIXES :
A. General : Mix factory prepared cement plaster in
accordance with manufacturer ' s instructions . Use
mechanical mixer free of hardened materials .
B. Proportions : Conform to recommendation of the
California Lathing and Plastering Contractors
Association, Inc. (CLPCA) for the first and second
coats . Mix plaster proportions in accordance with
Table 47-F of UBC.
1 . Base Coats :
a. One part portland cement .
b. One twelfth part lime.
C. Two to four parts sand.
PART 3 - EXECUTION
3 . 1 LATHING:
A. Stucco Lath: Fasten to horizontal surfaces with
fasteners scheduled in U. B. C . Do not continue lath
across expansion joints . Maintain weather resistant
building paper continuous under joints .
1 . Apply with weatherproof backing.
2 . Provide 4" wide continous metal lath strips over
flanges of all screeds and 18" long strips,
diagionally at head and jamb intersecting corners
at all doors .
B. Protect aluminum trim and moldings an with non-staining
tape or other suitable material .
3 . 2 APPLICATION:
A. Wet base with fine fog spray to produce uniform moist
conditions . Apply bonding agent in strict accordance
with manufacturer' s directions .
B. Machine apply base coats . Apply scratch and brown
coats over stucco lath at all exterior walls to receive
ceramic tile . Straighten all surfaces to true planes,
free of imperfections . First coat thickness 3/8 inch
thick. Second coat total thickness 3/4 inch.
DEMUTH CENTER RESTROOM FACILITIES LATH AND PLASTER
CITY PROJECT NO. 98-20 SECTION 09200- PAGE 3
5/24/02
3 . 3 CURING:
A. Scratch coat : Keep moist 48 hours .
B. Brown coat : Cure at least seven days . Keep moist 48
hours .
3 . 4 ADJUSTING AND CLEANING:
A. Remove plaster and protective materials from adjacent
surfaces .
B. Completely clean all expansion joint slots of any
adhered plaster materials .
END OF SECTION
DEMUTH CENTER RESTROOM FACILITIES LATH AND PLASTER
CITY PROJECT NO. 98-20 SECTION 09200- PAGE4
5/24/02
SECTION 09311
CERAMIC TILE
PART 1 - GENERAL
1 . 1 DESCRIPTION:
A. Provide Ceramic Tile where shown on the drawings, as
specified herein, and as needed for a complete and proper
installation.
B. Work includes ceramic wall tile installed over portland
cement scratch and brown coat base .
1 . 2 RELATED WORK:
A. Related Work Specified Elsewhere :
1 . Documents affecting work of this Section include,
but are not necessary limited to the Standard
Specifications and these technical provisions .
2 . Section 09200 - Lath and Plaster: Portland cement
scratch and brown coat for vertical tile surfaces .
1 . 3 QUALITY ASSURANCE:
A. Regulatory Requirements :
1 . In addition to complying with applicable codes and
regulations of governmental agencies having
jurisdiction, comply with the applicable
requirements of the referenced standards .
2 . Where the requirements of applicable codes,
regulations and standards conflict with this
Specification, comply with the more stringent
provisions .
3 . Conform to ANSI / TCA A137 . 1 for tile . Conform to
ANSI / TCA A108, 10 for installation of grout .
B. Source Quality Control :
1 . Certification: Furnish manufacturer ' s Master
Grade Certificates for tile proposed to be
installed. Certificates shall be on standard
forms of the Tile Council of America (TCA) and
shall certify type, grade and quality of tile.
DEMUTH CENTER RESTROOM FACILITIES CERAMIC TILE
CITY PROJECT NO. 98-20 SECTION 09311 -PAGE 1
5/24/02
C. Qualifications :
1 . Manufacturer: The manufacturer shall have a
minimum five years experience .
2 . Installer: The subcontractor shall specialize in
applying ceramic tile with a minimum of five years
experience .
1 . 4 SUBMITTALS :
A. Product Data : Submit complete manufacturer' s
descriptive literature, and specifications in
accordance with the provisions of Section 01301 .
B . Maintenance Stock: At time of completing the
installation, deliver stock of maintenance material to
the Owner. Furnish full size units matching the units
installed, packaged with protective covering for
storage, and identified with appropriate labels .
1 . Provide 3% additional tile and trim shapes of each
type, color, pattern and size used in the work for
owners use in replacement and maintenance .
Package securely to prevent damage and label
clearly. Provide minimum of one full sealed
carton.
1 . 5 DELIVERY, STORAGE AND HANDLING:
A. Protection: Use all means necessary to protect the
materials of this Section before, during and after
installation.
1 . Deliver manufactured materials in original sealed
containers with manufacturer ' s name, brand and
grade seals affixed or sealed within per ANSI/TCA
A137 . 1 .
2 . Keep materials dry until used.
3 . Store and protect products in dry, secure areas .
B. Replacements : In the event of damage, immediately make
repairs and replacements necessary to the approval of
the Architect and at no additional cost to the Owner.
PART 2 - PRODUCTS
2 . 1 TILE MATERIALS :
A. Ceramic tile: 4 1/4" x 4 1/4" glazed wall tile with
gloss finish. Color and price group equal to Daltile
DEMUTH CENTER RESTROOM FACILITIES CERAMIC TILE
CITY PROJECT NO. 98-20 SECTION 09311 -PAGE 2
5/24/02
Cobalt DM14 . Architect to confirm exact color
selection.
1 . Random Pattern: Percentages of different colors to
be confirmed by Architect .
2 . 2 MORTAR AND GROUT MATERIALS :
A. Portland Cement : ANSI / TCA A118 . 1 and A118 . 4 . ASTM
C150, Type II or Type II .
B. Hydrated Lime: ASTM C 207, Type S .
C. Sand: ASTM C144 and ASTM C40 .
D. Portland Cement Mortar: Portland cement thin-set
mortar equal to "MasterBlend" with "CustomFlex" ultra-
strength acrylic latex additive . ANSI A108 . 5 and ANSI
A118 . 4 .
E. Grout : Polyblend Non-sanded, as manufactured by Custom
Building Products or approved equal . Color to be #90
Ocean Blue . Joint width to be 1/8" maximum.
2 . 3 OTHER MATERIALS :
A. Other materials, not specifically described but
required for a complete and proper installation of the
work of this section, shall be new, first quality of
their respective kinds, and subject to approval of the
Architect .
PART 3 - EXECUTION
3 . 1 INSPECTION:
A. Inspection: Carefully inspect all surfaces to receive
tile . Do not apply materials until any necessary
corrections are made.
B. Examine wall substrates, setting beds and accessories
before tile installation begins to assure that
substrates are plumb and in a true plane within 1/8
inch in 8 feet .
3 . 2 PREPARATION :
A. Protect all surrounding work from damage or
disfiguration.
DEMUTH CENTER RESTROOM FACILITIES CERAMIC TILE
CITY PROJECT NO. 98-20 SECTION 09311 -PAGE 3
5/24/02
3 . 3 MIXING:
A. Mix Portland cement mortar in accordance with
manufacturer' s instructions .
B. During use, remix mortar occasionally. Additional
water or fresh materials shall not be added after
initial mixing. The mortar shall not be used after
initial set .
3 . 4 INSTALLATION:
A. Thoroughly soak all non-vitreous tile at least one-half
hour in clear water and drain off excess, leaving no
free water on back of tile . Any tile left out of water
for more than two hours shall be resoaked.
B. ANSI Standards : Comply with applicable requirements of
the following, except as otherwise indicated.
1 . ANSI A108 . 10 for Glazed Wall Tile, Ceramic Mosaic
Tile, Quarry Tile and Paver Tile installed with
Portland Cement Mortar.
C. Mortar application:
1 . Clean surface thoroughly. Dampen if very dry but
do not saturate .
2 . Apply mortar with flat side of trowel over an area
no greater than can be covered with tile while
mortar remains plastic.
3 . Cover surface uniformly with no bare spots with
sufficient mortar to ensure a minimum mortar
thickness of 3/32 inch between tile and backing
after tile has been beaten into place. Tile shall
not be applied to skinned-over mortar.
D. Application of Grout :
1 . Mixing: Refer to manufacturer ' s directions .
2 . Dry blend contents of an entire container or grout
prior to mixing with water.
3 . Use caution to prevent scratching or damaging of
tile surfaces .
4 . Dampen dry joints prior to grouting. Do not leave
puddles of water in joints before grouting.
5 . Force a maximum amount into the joints . Cushion
edge tile shall be finished evenly to the depth of
the cushion. Square-edge tile shall be finished
flush with the surface .
DEMUTH CENTER RESTROOM FACILITIES CERAMIC TILE
CITY PROJECT NO. 98-20 SECTION 09311 -PAGE 4
5/24/02
0
6. The finished joint shall be uniform in color,
smooth and without pinholes, voids or low spots .
E . Accurately form intersections and returns . Perform
cutting and drilling of tile without marrying visible
surfaces . Carefully grind cut edges of tile abutting
trim, finish or built-in items for straight aligned
joints .
F. Setting Ceramic Tile: Layout work according to
patterns detailed or approved. Lay out tile so that
fields or patterns center exactly on the areas and on
architectural features so that whenever possible no
tile that is less than half size occurs . Align joints
vertically and horizontally. No staggered joints will
be permitted. Firmly imbed and beat tile into mortar
with all finished surfaces brought to true and level
planes . Fill joints full with grout, wipe excess grout
from tile faces, and leave all joints finished at
uniform depth.
G. Grout shall be mixed and applied in accordance with the
referenced standards . Force a maximum of grout into
all joints . Before grout sets, strike or tool the
joints cushion-edge tile to depth of cushion, filling
gaps, and with square-edged tile, fill joints, flush
with their surface . Thoroughly brush out tile joints
before grouting.
3 . 5 SEALANTS :
A. Fill all expansion joints with colored elastomeric
sealant to match grout joints as recommended by the
Ceramic Tile Institute using back-up filler to prevent
sealant from bonding to substrate .
3 . 6 ADJUSTING AND CLEANING:
A. Finished Tile Work: Leave finished installation clean
and free of cracked, chipped, broken, unbonded, or
otherwise defective tile work.
B. Cleaning: Thoroughly clean tile of all stains and
grout residue . Acid or acid cleaners shall not be used
for the cleaning of glazed tile .
3 . 7 PROTECTION:
DEMUTH CENTER RESTROOM FACILITIES CERAMIC TILE
CITY PROJECT NO. 98-20 SECTION 09311 -PAGE 5
5/24/02
0
A. Apply to clean, completed tile walls a protective coat
of neutral cleaner solution, one part cleaner to one
part water.
B. Immediately prior to final acceptance of tile work,
rinse protective coat of neutral cleaner from all tile
surfaces .
END OF SECTION
DEMUTH CENTER RESTROOM FACILITIES CERAMIC TILE
CITY PROJECT NO. 98-20 SECTION 09311 -PAGE 6
5124/02
SECTION 09831
ANTI-GRAFFITI COATING
PART 1 - GENERAL
1 . 1 SUMMARY
A. Provide antigraffiti coatings on all exterior ceramic tile
walls shown on the Drawings, as specified herein, and as
needed for a complete and proper installation.
1 . 2 RELATED WORK:
A. Related Work Specified Elsewhere:
1 . Documents affecting work of this Section include, but
are not necessarily limited to the Standard
Specifications and these technical provisions .
2 . Section 09311 - Ceramic Tile .
1 . 3 SUBMITTALS
A. Product data : Within 60 calendar days after the Contractor
has received the Owner ' s Notice to Proceed, submit :
1 . Materials list of items proposed to be provided under
this Section;
2 . Manufacturer ' s specifications and other data needed to
prove compliance with the specified requirements;
3 . Proof that the proposed subcontractor is currently
approved for this purpose by the manufacturer of the
approved materials;
4 . Manufacturer' s recommended installation procedures
which, when approved by the Architect, will become the
basis for accepting or rejecting actual installation
procedures used on the Work.
1 . 4 QUALITY ASSURANCE
A. Use adequate numbers of skilled workmen thoroughly trained
and experienced in the necessary crafts and completely
familiar with the specified requirements and methods needed
for proper performance of the work of this Section.
B. Use a subcontractor who is currently approved in writing by
the manufacturer of the approved materials .
PART 2 - PRODUCTS
2 . 1 ANTI-GRAFFITI COATINGS
DEMUTH CENTER RESTROOM FACILITIES ANTI-GRAFFITI COATING
CITY PROJECT NO. 98-20 SECTION 09831 -PAGE 1
5/24/02
A. The design is based on VANDL-GUARD as manufactured by
Rainguard Products Company. , 3471 Via Lido, Suite 213,
Newport Beach, CA 92663 .
B. Coating shall consist of a clear, translucent colorless
one-part water based, cross-linked co-polymer protective
film which is easily cleaned and prevents penetration of
staining medium into the substrate.
C. Materials shall be the products of one manufacturer and
shall be either the one upon which the design is based, or
the products of a manufacturer approved in advance by the
Architect .
PART 3 - EXECUTION
3 . 1 SURFACE CONDITIONS
A. Examine the areas and conditions under which work of this
Section will be performed. Correct conditions detrimental
to timely and proper completion of the Work. Do not
proceed until unsatisfactory conditions are corrected.
B. Surfaces must be clean, dry and free from grease and other
contaminants .
3 . 2 INSTALLATION
A. Install the work of this Section in strict accordance with
pertinent requirements of governmental agencies having
jurisdiction, and the manufacturer ' s recommended
installation procedures as approved by the Architect .
B. Apply product utilizing airless spray equipment in
accordance with manufacturers recommendations by an approved
applicator experienced in applying the specified system.
C. Apply three (3) coats of anti-graffiti coatings to all
exterior ceramic tile walls shown on the drawings .
D. Apply the product directly from the manufacturers
container. Do not thin.
END OF SECTION
DEMUTH CENTER RESTROOM FACILITIES ANTI-GRAFFITI COATING
CITY PROJECT NO. 98-20 SECTION 09831 -PAGE 2
5/24/02
i •
SECTION 09900
PAINTING
PART 1 - GENERAL
1 . 1 DESCRIPTION:
A. Provide Finish Painting where shown on the drawings, as
specified herein, and as needed for a complete and
proper installation.
1 . 2 RELATED WORK:
A. Related Work Specified Elsewhere :
1 . Documents affecting work of this Section include,
but are not necessary limited to the Standard
Specifications and these technical provisions .
1 . 3 WORK INCLUDED:
A. Surface preparation.
B. Prime coat application.
C. Intermediate coat application.
D. Finish coat application.
E. Upon completion of work under this contract, all
exterior surfaces within the contract limits and within
vision, will have a painters finish.
1 . 4 WORK NOT INCLUDED:
A. Surfaces Not To Be Painted:
1 . Prefinished wall, ceiling and floor coverings .
2 . Items with factory-applied final finish.
3 . Ceramic tile.
1 . 5 SUBMITTALS :
A. Samples under provisions of Section 01301 .
1 . Submit three samples 8-1/2 inches by 11 inches in
size illustrating range of colors and textures
available for each surface finishing product
scheduled for selection.
2 . Prepare wood samples on type and quality of wood
specified.
DEMUTH CENTER RESTROOM FACILITIES PAINTING
CITY PROJECT NO. 98-20 SECTION 09900 -PAGE 1
5/24/02
1 . 6 QUALITY ASSURANCE:
A. Product Manufacturer: Company specializing in
manufacturing quality paint and finish products with
ten years experience.
B. Applicator: Company specializing in commercial
painting and finishing with five years experience.
1 . 7 REGULATORY REQUIREMENTS :
A. Conform to Environmental Protection Agency (EPA) ,
California Air Resources Board (GARB) and South Coast
Air Quality Management District (SCAQMD) regulations .
B. Comply with applicable codes and regulations of
governmental agencies having jurisdiction including
those having jurisdiction over airborne emissions and
industrial waste disposal . Where those requirements
conflict with this specification, comply with the more
stringent provisions .
1 . 8 DELIVERY, STORAGE AND HANDLING:
A. Deliver products to site in sealed original containers .
B. Provide adequate storage facilities . Store paint
materials at minimum ambient temperature of 45 degrees
F and maximum of 90 degrees F, in well ventilated area
unless required otherwise by manufacturer ' s
instructions .
C. Take precautionary measures to prevent fire hazards and
spontaneous combustion.
1 . 9 PROJECT SITE CONDITIONS :
A. Provide continuous ventilation and heating facilities
to maintain surface and ambient temperatures above 45
degrees F for 24 hours before, during and 48 hours
after application of finishes, unless required
otherwise by manufacturer ' s instructions .
B. Do not apply exterior coatings during rain, or when
relative humidity is above 50 percent, unless required
otherwise by manufacturer' s instructions .
DEMUTH CENTER RESTROOM FACILITIES PAINTING
CITY PROJECT NO 98-20 SECTION 09900-PAGE 2
5/24102
C. Minimum Application Temperature for Latex Paints : 45
degrees F for interiors unless required otherwise by
manufacturer' s instructions .
D. Minimum Application Temperature for Varnish and
Transparent Finishes : 65 degrees F for interior unless
required otherwise by manufacturer' s instructions .
E . Provide lighting levels sufficient to conduct painting
operations .
F. Beginning of installation means acceptance of existing
surfaces .
1 . 10 MAINTENANCE:
A. Extra material to be not less than one full gallon of
each color, type of paint, in new unopened containers .
Label each container for identification.
PART 2 - PRODUCTS
2 . 1 ACCEPTABLE MANUFACTURERS :
A. Design is based on the products manufactured by Dunn-
Edwards Corporation, Los Angeles, CA (213) 771-3330 .
B. Substitutions : Under provisions of Section 01630,
submit chemical formulations of material submitted for
substitution.
2 . 2 MATERIALS :
A. Products used are to be from one manufacturer and shall
be either the ones upon which the design is based or
the products of a manufacturer approved in advance .
B. Paints : provide ready-mixed, except field catalyzed
coatings . Pigments shall be fully ground maintaining
soft paste consistency, capable of being readily and
uniformly dispersed to a complete homogeneous mixture.
C. Paint Accessory Materials : Other materials not
specified but required to achieve required finishes
shall be of high quality and approved by the
manufacturer.
D. Paints shall have good flowing and brushing properties
and be capable of drying or curing free of streaks and
sags .
DEMUTH CENTER RESTROOM FACILITIES PAINTING
CITY PROJECT NO 98-20 SECTION 09900 -PAGE 3
5124102
• 0
PART 3 - EXECUTION
3 . 1 EXAMINATION:
A. Prior to commencing the work of this section, carefully
inspect previously installed work and verify that such
work is complete to the point where this installation
may properly commence .
B. Verify that work of this section may be installed in
accordance with applicable codes, regulations and
standards, the Contract Documents and the approved
submittals .
3 . 2 PREPARATION:
A. Protection: Protect previously installed work and
materials which may be affected by work of this
section.
B. Surface Preparation:
1 . Perform preparation and cleaning procedures in
accordance with coating manufacturer' s
instructions for each substrate condition.
2 . Concrete surfaces shall be cleaned free of all
dirt, efflorescence and other foreign matter.
Glazed surfaces on concrete shall be roughened to
uniform texture.
3 . Seal wood required to be job-painted. Prime
edges, ends, face underside and backsides of
counters, cases, cabinets and other specified
surfaces . Use spare varnish for backpriming where
transparent finish is required.
7 . Shellac and seal marks which may bleed through
surface finishes .
3 . 3 MATERIAL PREPARATION:
A. Mix, prepare and store painting and finishing materials
in accordance with manufacturer ' s directions .
3 . 4 APPLICATION:
A. Apply painting and finishing materials in accordance
with the manufacturer ' s submittals, as approved. Use
applicators and techniques best suited for the material
and surfaces to which applied.
DEMUTH CENTER RESTROOM FACILITIES PAINTING
CITY PROJECT NO. 98-20 SECTION 09900-PAGE 4
5/24102
0 •
B. The number of coats specified is the minimum that shall
be applied. Apply additional coats when undercoats,
stains or other conditions show through final paint
coat, until paint film is of uniform finish, color and
appearance . Second coat shall be tinted a different
shade from the first and third coats .
C . Sand lightly and dust clean between succeeding coat .
D. Apply each material at not less than the manufacturer ' s
recommended spreading rate to provide a total dry film
thickness of not less than 5 . 0 mils for the entire
coating system of prime and finish coats for 3-coat
work.
E . Provide a total dry film thickness of not less than 3 . 5
mils for the entire coating system of prime and finish
coat for 2-coat work.
3 . 5 ADJUSTING AND CLEANING:
A. Remove, finish or repaint work not in compliance with
specified requirements .
B. Keep premises free from unnecessary accumulation of
tools, equipment, surplus materials and debris .
C. Promptly remove paint where spilled, splashed, smeared
and splattered.
D. Upon completion of work, leave premises neat and clean
to satisfaction of Owner.
3 . 6 FINISH SCHEDULE:
A. EXTERIOR WOOD - PAINT FINISH - GLOSS
1st Coat - Primer W708
2nd Coat - Intermediate W960
3rd Coat - Finish W960
B EXTERIOR WOOD - STAIN FINISH - OPAQUE
1st Coat - Primer/Finish W703
2nd Coat - Finish W703
C. EXTERIOR WOOD - STAIN FINISH - SEMI-TRANSPARENT
1st Coat - Finish WPT3
END OF SECTION
DEMUTH CENTER RESTROOM FACILITIES PAINTING
CITY PROJECT NO 98-20 SECTION 09900 -PAGE 5
5/24/02
,
S���6 ', PO B0X`420807 SANRA'FNCISCO CA041420807
COMPEiVSATiON
N SU RSIN CE - - - .
-FU.iV D: CERTIFICATE OF WORKERS`COMPENSATION INSURANCE
INSURANCE
1Y� :'2001 1it
461 49 hI "Q<5400P.4
POLICY NUM RER. -
' CERTIFICATE EXPIRES
- - -
( .0 Y Rig flPfUl �[?R;rl\It�
DPA L'uGliuS •L1CZD13'E—F1MANtE DEPT
P 9 SOX 2743
PAUT SPRINGS ,CA 92263
L.
....,_ _ ompensatim insurance policy in,a form approved by the California -
TI7is is to that we have issued a valld,Workers'C _
_ Insurarice Gommisslorier tb the em to eF named below"'far the policy period indicated --
P Y J(
This policy is not subject to cancellation by the Fund except upon)fen days'advance written notice to the employer.
30
We will also give you'TEN days'advance notice should this policy be cancelled prior to its normal expiration.
This certificate of insurance is not an insurance policy and does not amend, extend or alter the coverage afforded by the
policies listed herein. Notwithstanding any requirement. term, or condition of any contract or other document with
respect to which this certificate of insurance may be. issued or may pertain, the insurance afforded by the policies
described herein is subject to all the terms. exclusions and conditions of such policies.
z7t%f��_ G7�sZf2.0_� . t�����T(TC1G/►-.fil.
AUTHORIZED REPRESENTATIVE - - PRESIDENT
PI:uYiF' 'S LIADAYLIT'( LIMIT tI`df.I JD,[ iG DEYENS7, CQSTS 1,?. rC('0,t)00 PL" OCCL' ; ENU1
P9,?)P.SEHL:NF 00015 ,.`.fTl_aD ADDITI:O4`NL INSURED ?J1PLC7Y r
10,,01l01 S5 ,1TTACrIE2 70 ekt1D' FORNS '1 PART OF '11115 POL I—Y.
NAPE OF A!)D'it T!ONAL ".I�tF�_IF?_ LITf OF 5PPENGiS
'=MDC i, ut,:, - r j rrn fir, i.n, �c - �Ii1iC�3J R� T'`_ff =_7 _n ..r SL,F. w_„Iu .I il1,;
knfDs '93. ry F�''ir.t. i . f(1 Jt: t•EIi�.,!� F�lf~,? l3 �}II;. I''_?_L.,'+' ,
EMPLOYER
7
HAFFY Tl";AVEL F_ F2Ei�F`.i.s$ If htgP_. V P!I'C,f.. PPRIts, lii!I'
DEA 5 f'x M M1 ;57;?Uf"4 Sfri�d - - -
117
P1 U.M+'eASm�iM0i in'rt M1�nrli'�.14
.u��r" Ihrn� ��r6ah lmnnAnm�l��e� ih ul yu ri,i °I` ,d1n
a0401"Om CERTIFICA OF LIABILITY INSURAN E °05/1`6o�D°Y'
PRODUCER THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION
ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
HRH Ins Sery of So California HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
License Number 0684603 ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
77-564 Country Club Dr. #401 COMPANIES AFFORDING COVERAGE
Palm Desert CA 92211
COMPANY
A American States Insurance
INSURED COMPANY
G & M Construction B Lexington Ins Co/AES
211 W. Mesquite COMPANY '
Palm Springs CA 92264 C
COMPANY
D
COVERAGES
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD
INDICATED, NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS,
EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
CO TYPE OF INSURANCE POLICY NUMBER POLICY EFFECTIVE POLICY EXPIRATION LIMITS
LTR DATE (MMIDDIYY) DATE (MMIDDIYY)
B GENERAL LIABILITY 1140950 02/13/02 02/13/03 GENERAL AGGREGATE $ 2,000,000
X COMMERCIAL GENERAL LIABILITY PRODUCTS COMPIOP AGG $ 1,000,000
CLAIMS MADE ❑X OCCUR PERSONAL&ADV INJURY S 1,000,000
OWNER'S&CONTRACTOR'S PROT EACH OCCURRENCE 5 1 ,000,000
FIRE DAMAGE (Any one fire) S 50,000
MED EXP(Any one person) 5 EX C I u,ded
A AUTOMOBILE LIABILITY 010E916141-1 03/06/02 03/06/03
ANY AUTO COMBINED SINGLE LIMIT $ 1 ,000,000
ALL OWNED AUTOS
BODILY INJURY $
X SCHEDULED AUTOS (Per person)
X HIRED AUTOS BODILY INJURY
X NON OWNED AUTOS (Per accident) $
PROPERTY DAMAGE $
GARAGE LIABILITY AUTO ONLY-EA ACCIDENT 5
ANY AUTO OTHER THAN AUTO ONLY
EACH ACCIDENT $
AGGREGATE S
EXCESS LIABILITY EACH OCCURRENCE $
UMBRELLA FORM AGGREGATE $
OTHER THAN UMBRELLA FORM $
WORKERS COMPENSATION AND WC STATU OTH-
EMPLOYERS'LIABILITY TORY LIMITS ER
EL EACH ACCIDENT $
THE PROPRIETORS INCL EL DISEASE-POLICY LIMIT $
PARTNERS/EXECUTIVE
OFFICERS ARE EXCL EL DISEASE EA EMPLOYEE $
OTHER
D SC IPTION F PE ATONSILOCATION IVEHICIES/SPECIAL IT,E S
R emut ar estroom acil rt Les - TI e Work
City Protect No, 98-20
Cl ty Df Palm Springs is named as an additional insured as per the
attached CG2010 11/85.
CERTIFICATE HOLDER CANCELLATION
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE
City of Palm Springgs` EXPIRATION DATE THEREOF THE ISSUING COMPANY WILL ENDEAVOR TO MAIL
Dept. Procurement&Contracting 30 DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT
3200 Tahquitz Canyon Way BUT FAILURE TO MAIL SUCH NOTICE SHALL IMPOSE NO OBLIGATION OR LIABILITY
Palm Springs CA 92262
OF ANY KIND UPON THE COMPANY, ITS AGENTS OR REPRESENTATIVES
AUTHO D REPRESENT TIVE
Mart
ACORD 25-S (1/95) LICENSE #0684503 RD CORPORATION 1988
05/16/02
INSURED: G &M Construction
211 W. Mesquite
Palm Springs, CA 92264-
Re: General Liab - Lexington hisurance Co. - Policy# 1140950
Effective 02/13/02 To 02/13/03
This endorsement changes the policy. Please read it carefully.
ADDITIONAL INSURED - OWNERS, LESSEES OR CONTRACTORS
(FORM B)
This endorsement modifies insurance provided under the following:
COMMERCIAL GENERAL LIABILITY COVERAGE PART
WHO IS AN WSi_1RED (Section II) is amended to include as an insured the person or
organization shown in the Schedule, but only with respect to liability arising out of your
work for that insured by or for you.
SCHEDULE
NAME OF PERSON OR ORGANIZATION:
City of Palm Springs
RE: Demuth Park Restroom Facilities - Tile Work
City Project No. 98-20
11/85
LICENSE #0684503