CITYWIDE ARHM OVERLAY PROJECT
RECOMMENDATION:
It is recommended that City Council approve Contract Change Order No. 1 with Granite
Construction Company, for an increase of $47,605.00, for a total contract amount of
$223,781.17, for the Citywide ARHM Overlay Project, City Project 02-01.
SUMMARY:
Contract Change Order No. 1 will allow for the addition of Andee Drive, between Sonora
Road and East Palm Canyon Drive, to the Citywide ARHM overlay project.
BACKGROUND:
City Project No. 02-01 was awarded by the City Council at its August 7, 2002, meeting. The
project will install asphalt rubber hot mix (ARHM) overlays on Stevens Road, from Indian
Canyon Drive to its easterly end; Crossley Road, from Mesquite Avenue to 34`hAvenue;
Calle Abronia, from Ramon Road to Camino Parocela; and Calle Palo Fiero, from Sunny
Dunes Road to North Riverside Drive. Originally, the project was limited to these four
streets; however, the actual construction bid received from Granite Construction was far
below the Engineer's estimate, giving the City an opportunity to add another street to this
street maintenance project. Staff has identified Andee Drive, between Sonora Road and
East Palm Canyon Drive, as a street requiring repair and preventive maintenance through
the use of an ARHM overlay, and has negotiated a contract price with Granite Construction
consistent with its bid prices for its addition to the project.
Sufficient funds are available in account no. 134-4498-50100 (Slurry Seal Program).
SUBMITTED:
DAVID J. BARAKIAN
Director of Public Works/City Engineer
APPROVED:
J�
DAVID H. READY_ REVIEWED BY DEPT.OF FINANCE
City Manager
ATTACHMENTS:
1. Minute Order
CITY OF PALM SPRINGS
CONTRACT CHANGE ORDER
To: Granite Construction Company Date: September 20, 2002
585 W. Beach Street Project No.: C.P. 02-01
Watsonville, CA 95076 Project Name: Citywide ARHM Overlay
Project
Change Order No.: One (1)
Attn: Bob Garcia, Project Engineer Contract Purchase No.: 316126
Account Number(s): 134 - 4498 - 50100
Agr.#4544 M.O. #7136 Res. #
A. CHANGES IN WORK:
Increase to Contract Bid Items(New)- Bid Schedule 1, Andee Drive from Sonora Rd to East Palm Canyon
Dr
Item Description
1 Mobilization
2 Cold Plane Existing AC Pavement
3 Construct 1.5 in. ARHM Overlay
4 Adjust Sewer Manhole to Grade
5 Traffic Striping and Markings
B. CHANGES IN CONTRACT COST:
Increase to Contract Bid Items (New) - Bid Schedule 1, Andee Drive from Sonora Rd to East Palm Canyon
Dr
Item Description
1 Mobilization Lump Sum $ 4,500.00
2 Cold Plane Existing AC Pavement 17,500 SF @ $0.45 $ 7,875.00
3 Construct 1.5 in. ARHM Overlay 49,000 SF @ $0.65 $ 31,850.00
4 Adjust Sewer Manhole to Grade 5 Each @ $500.00 $ 2,500.00
5 Traffic Striping and Markings Lump Sum $ 880.00
Total $ 47,605.00
TOTAL CHANGE ORDER = $47,605.00
NOTE: No additional markup will be added to any items in this Contract Change Order.All cost per
each item are final.
C. REASON FOR CHANGE:
Perthe recommendation of the Public Works Director/City Engineer,cold plane existing asphalt pavement,
construct 1.5 in. ARHM overlay, adjust sewer manholes and instal traffic striping and markings on Andee
Road from Sonora Road to East Palm Canyon Drive. The City received exceptional unit prices from the
contractor and proposes to utilize this opportunity to include this street due to its current bad condition.
D. SOURCE OF FUNDS:
Slurry Seal Program - Local Measure A 134 - 4498 - 50100 = $ 47,605.00
Summary of Costs Contract Time
Original Contract Amount: $ 176,176.17 Original Completion Date:
This Change Order: $ 47,605.00 Days Added for this C.C.O.: 10
Previous Change Order(s): $ 0.00 Previous Days Added: 0
Revised Contract Amount: $ 223,781.17 Revised Completion Date:
14,2
Sept. 20, 2002
City Project 02-01 Citywide ARHM Overlay Project
Change Order No. One (1)
Page 2 of 2
1 have received a copy of this Change Order and the City Approval:
above AGREED PRICES are acceptable to the
contractor. Submitted By Date
Field Engineering Supervisor
By
Approved By Date
Title Director of Public Works/City Engineer
Date Approved by Date
City Manager
Distribution:
Original Conformed Copies Conformed-File Copy
Engineering (1) Engineering File (1)
Finance (1) Engineering Field Inspector (1)
Contractor (1) Engineering Field Supervisor (1)
City Clerk (1) Purchasing Agent (1)
?�4 3
MINUTE ORDER NO.
APPROVING CONTRACT CHANGE ORDER NO. 1 WITH
GRANITE CONSTRUCTION COMPANY, FOR AN
INCREASE OF $47,605.00, FOR A TOTAL CONTRACT
AMOUNT OF $223,781.17, FOR THE CITYWIDE ARHM
OVERLAY PROJECT, CITY PROJECT 02-01
I HEREBY CERTIFY that this Minute Order, approving Contract Change Order No. 1 with Granite
Construction Company, for an increase of$47,605.00, for a total contract amount of$223,781.17,
for the Citywide ARHM Overlay Project, City Project 02-01, was adopted by the City Council of the
City of Palm Springs, California, in a meeting thereof held on the 2ntl day of October, 2002.
PATRICIA A. SANDERS
City Clerk