DATE: November 20, 2002
TO: City Council
FROM: Assistant Director via Executive Director of Airports
PALM SPRINGS INTERNATIONAL AIRPORT RESIDENTIAL SOUND INSULATION
PROGRAM CONSULTANT CONTRACT AMENDMENT NO. 3
RECOMMENDATION:
It is recommended that the City Council approve Amendment No. 3 to Standard Contract
Service Agreement No. A4023 for consulting and project management services for Palm
Springs International Airport(PSP)Residential Sound Insulation Program's(RSIP)Phase IV for
58 confirmed homes in an amount of $413,685.00 with C. Kell-Smith & Associates, Inc.;24
additional homes are eligible to be added during this phase at a unit cost of$7,132.50 per home
for a total of 82 homes for a not to exceed amount of$584,865.00;total contract amount not to
exceed $1,750,787.82 (original contract amount Phase 2 $409,725.82, Phase 3 $756,197.00
and Phase IV$584,865.00 = $1,750,78T82)
SUMMARY:
This phase of the Airports Residential Sound Insulation Program includes 82 potential homes.
Currently, there are 58 homeowner applications on file and efforts are underway to get the
remaining homeowners signed up for Phase IV. A unit price of$7,132.50 per home will be billed
for homes in excess of 58 with a not to exceed amount for this amendment of$584,865. ]fall
remaining homeowners participate,the program will have acoustically treated 243 single family
dwelling units. Participation is voluntary and all homes are located within the City of Palm
Springs qualified noise boundary.
BACKGROUND:
On November 4, 1998, City Council adopted minute order No. 6267 approving a standard
contract service agreement for RSIP Phase II consulting services for single family dwelling units
with C. Kell-Smith &Associates. Subsequently, minute orders 6411 and 6624 were approved
on May 19, 1999 and June 7, 2000 respectively,which granted the approval for consulting and
project management services for Phase III RSIP. To date the program has successfully
acoustically treated 161 single dwelling units.
Airport Improvement Program funds from the FAA in the form of noise grants will be used to
fund 90% of the project with a 10% match coming from the Airport. Sufficient funds are
available in 415-6600-56039 and 415-6600-56047 to complete the final phase of the Residential
Sound Insulation Program.
The Airport Commission unanimously approved staff's recommendation to approve Amendment
No. 3 to Standard Contract Agreement No. A4023 with C. Kell-Smith &Associates, Inc. at its
March 6, 2002 meeting.
�.•;i r:, "'.>,ii../'�� APPROVED:
�FARRY -'RIffl%W ALLEN F. SMC50T A.A.E.
AssisjdKf'Di—rodfor of Aviation Executive Director - Airports
APPROVED:_—:_ ^=� i. `✓ s .� �r
City Manager
Attachments: 1. Minute Order 2. Amendment No. 3 REVIEWED BY DEPI OF FINANCE
AMENDMENT NO. 3
AGREEMENT NO. A4023 FOR CONSULTING SERVICES FOR PALM SPRINGS
INTERNATIONAL AIRPORT NOISE COMPATIBILITY PROGRAM (NCP)RESIDENTIAL SOUND
INSULATION PROGRAM(RSIP) Phase IV.
THIS THIRD AMENDMENT TO THE AGREEMENT FOR CONTRACT SERVICES(No.A4023)(herein
AGREEMENT") is made and entered into this 20 day of November, 2002, by and between the CITY OF
PALM SPRINGS (herein "City" or "Owner"), a municipal corporation, and C. KELL-SMITI-I &
ASSOCIATES,INC.(herein "Contractor"),and amends that certain Agreement for contract services dated
November 4, 1998, as amended,between the same parties, as follows:
Section 1• Amend Exhibit "A" Scone of Services is to add at the end thereof, after item 18,the
following:
PHASE IV
An additional phase of 58 confirmed homes with the potential of an additional 24 homes for
a total of 82 homes is added to the scope of work. The same services shall be performed by
the contractor for this phase as for the prior phases, including program management,
acoustical engineering and architectural services, except as provided below:
1. Phase IV -Program Management Services -Reports: Forensic Analytical (FA) will
provide reports on all test conducted for lead-based paint, asbestos and carbon monoxide.
2. Phase IV -Acoustical Engineering Services -Attend one (1) scoping meeting at Palm
Springs International Airport with Airport Staff to define the needs of the project and to
discuss project coordination issues.
3. Phase IV - Architectural Services - Attend one (1) scoping meeting at Palm Springs
International Airport with Airport Staff to define the needs of the project and to discuss
project coordination issues.
4. Phase IV -Outreach Program-Because this is anticipated to be the final phase of the
residential sound insulation program at the Palm Springs International Airport, C.Kell-
Smith and Associates shall, thru an outreach and/or certified mailing program,make a
good faith effort to ensure participation by all 82 homeowners.
Section 2•Exhibit "C" Schedule of Compensation is hereby amended to add to the schedule an additional
58 confirmed homes with the potential of an additional 24 homes for a total of 82 homes is added to the
scope of work to read as follows:
PHASE IV - SUMMARY OF SCHEDULES OF COMPENSATION FOR 58 HOUSES
Contract
Description Amount Current %Complete Total Due
Additiona58 Hitting
Homes
C.Kell-Simth& $117,609
Associates,Inc.(*)
Charles M.Salter 05,424
Associates
Harrisonn C.Wick and 50,696
Associates(*)
39,956
Forensic Analytical HazMat
Grand Total $413,685
for 58 Houses
Fee Proposal per house: $7,132.50
(*) Time and Mats Included
(**)Time and Material Basis with "Not to Exceed Amount"
The previous schedule is a summary table. The detailed schedule and budgets are shown below.
Except as otherwise designated, all amounts shown below are lump sum totals. Payment will be made based upon the
percentage completion of the task,when approved by the Contract Officer. When designated above,payment may include
reimbursable expenses,or be on a time and materials basis but not exceeding the amount listed(on the schedules below,
reimbursables are separate design listed). With the approval ofthe Contract Officer,monies maybe shrfted between budget
categories as long as the Contract Sum is not changed.
Program Management Services: Exhibit "C" (continued)
Contract
Description Amount Current % Total
C.Kell-Smith& 58 Homes Billing Complete Due
Associates
$486
Prepare Schedule
Oversee Project 30,530
Scope Meet&Prep ,275
Homeowner Info Meeting ,275
Ropeity Owner Selection 5,345
Process
Homeowner Contact 5,125
Newslh'Qrtet'ly(6) 2,265
Schedule Architect ,595
Measurements
Schedule CM&Hazardous ,595
Materials
Distribute HazMat 630
Report to Airport&
Homeowners
298
Select Control Homes
192
Schedule Pre-Con Noise
Monitoring
Arch/Acoust Plans& 4,350
Specifications
Bid Process& 2,380
Contractor Selection
Homeowner ,275
Construct Meeting &
Preparation
Notice of Award 1,630
Obtain Submittals 900
3,300
Prep for Construction
Homeowner Appoint ,595
Scheduling
Sign of Contracts& Plan 8,835
Approval
Construction 14,610
Completion ofPloject 1,925
Attend Public Meetings & 4 400
Other Tasks
Estimated 11,798
Reimbursables
C.Kell-Smith& S 117,609
Associates Total
Per House Fee Proposal:$1,484 i
Acoustical Engineering Services: Exhibit "C" (continued)
Description Contract
Acoustical Engineering Amount Current %Complete Total Due
Sel'V1nes g 58 Homes Billing
Scope Meeting $2,442
Homeowner Meet#1 2,470
Homeowner Meet#2 5,814
L
uct Measwe 12,469
evelopment 10,703
ulahons18,563
ocuments 10,362
ates 11,908
Homeowner Meet#3 2,470
Pre-Bid Conference 2,222
Pie-Con Conference 2,222
Vendor Submittals 8,393
Materials Inspection 2222
Construction Observe 2,222
Post Construction 12,469
Measurement
Report 5,940
PSP Staff Meeting 2,222
Close Out Meeting 2,222
Charles M.Salter S 105,424
Associates
Total
Per House Fee Proposal:$1,818
Architectural Services: Exhibit "C" (continued)
Description Contract
Pi eject Architect Amount Current % Total
58 Homes Billing Complete
$4,400
Home Selection and Review
Selected Home Review 22,000
Construction Does 55,000
Consbuction Armin 64,346
Estimated Remrbuisables 4,950
Architect Total $150,696
Per House Fee Proposal up to 80 homes:$2,599
Per House Fee Proposal after 80 homes:$2,708
Hazardous Materials Specialists: Exhibit "C" (continued)
Contract
Description Amount Current % Complete Total
Forensic Analytical 58 Homes Billing Due
On Site Testing $11,796
Project Management 2,805
Sample Analysis-Lead ,375
5,808
Sample Analysis-Asbestos
660
Lead-Based Work Plan
Asbestos Work Plan 660
Final Report ,320
5,335
Estimated Reimbursables
$29,759
Total FlazMat
On Site Testing 55,390
Project Management ,155
Final Report ,320
Estimated Reimbursables 2,332
Total Carbon Monoxide $10,197
Fee Proposal per house: $688.89
Section 3• Exhibit "D" Schedule of Performance is hereby amended to add the following additional
schedule of performance for Phase IV for the additional 58 confirmed homes with the Potential of an
additional 24 homes for a total of 82 homes is added to the scope of work:
Section 4• Except as specifically worded herein all terms and conditions of the Agreement shall remain in
full force and effect and perfornance of services under the Agreement shall be governed by the provisions
of the Agreement.
IN WITNESS WHEREOF, the parties have executed and entered into this Agreement as of the I �
date first written above.
CITY OF PALM SPRINGS
ATTEST: a municipal corporation
By: By:
City Clerk City Manager
APPROVED AS TO FORM:
By:
City Attorney
CONTRACTOR: Check one:_Individual_Partnership_Corporation
Corporations require two notarized signatures: One from each of the following: A. Chairman of Board, President, or any Vice
President:AND B.Secretary,Assistant Secretary,Treasurer,Assistant Treasurer,or Chief Financial Officer).
By. Signature (notarized) By. Signature (notarized)
Name: Name:
Title: Title:
State of A State of q
County of ss County of ss
On___beforeme, On before me,
personally appeared personally appeared
personally known to me (or proved to me on the basis of personally known to me (or proved to me on the basis of
satisfactory evidence)to be the person(s)whose name(s)is/are satisfactory evidence)to be the person(s)whose name(s)is/are
subscribed to the within instrument and acknowledged to me subscribed to the within instrument and acknowledged to me
that he/she/they executed the same in his/her/their authorized that he/she/they executed the same in his/her/their authorized
capacity(ies), and that by his/her/their signature(s) on the capacity(ies), and that by his/her/their signature(s) on the
instrument the person(s),or the entity upon behalf of which the instrument the person(s),or the entity upon behalf of which the
person(s)acted,executed the instrument. person(s)acted,executed the instrument.
WITNESS my hand and official seal. WITNESS my hand and official seal.
Notary Signature: Notary Signature:
Notary Seal: Notary Seal:
! ! • l0
MINUTE ORDER NO,
APPROVING AMENDMENT NO. 3 TO STANDARD CONTRACT
SERVICE AGREEMENT NO. A4023 FOR CONSULTING AND
PROJECT MANAGEMENT SERVICES FOR PALM SPRINGS
INTERNATIONAL AIRPORT (PSP) RESIDENTIAL SOUND
INSULATION PROGRAM'S (RSIP) PHASE IV FOR 58
CONFIRMED HOMES IN AN AMOUNT OF $413,685 WITH C.
KELL-SMITH&ASSOCIATES,INC.;24 ADDITIONAL HOMES ARE
ELIGIBLE TO BE ADDED DURING THIS PHASE AT A UNIT COST
OF $7,132.50 PER HOME FOR A TOTAL OF 82 HOMES FOR A
NOT-TO-EXCEED AMOUNT OF $584,865; TOTAL CONTRACT
AMOUNT NOT-TO-EXCEED $1,750,787.82.
I HEREBY CERTIFY that this Minute Order approving Amendment No.3 to Standard Contract Service
Agreement No.A4023 for consulting and project management services for Palm Springs International
Airport(PSP) Residential Sound Insulation Program's (RSIP)Phase IV for 58 confirmed homes in an
amount of$413,685 with C.Kell-Smith&Associates, Inc.;24 additional homes are eligible to be added
during this phase at a unit cost of$7,132,50 per home for a total of 82 homes for a not-to-exceed
amount of$584,865; total contract amount not-to-exceed $1,750,787.82. was adopted by the City
Council of the City of Palm Springs, California, in a meeting thereof held on the 20th of November,