HomeMy WebLinkAbout11/26/2002 - STAFF REPORTS (5) DATE: November 20, 2002
TO: City Council
FROM: Director of Public Works/City Engineer
SUNRISE WAY TRAFFIC SIGNAL INTERCONNECT
RECOMMENDATION:
It is recommended that the City Council award contract to Steiny and Company, Inc., in the
amount of$160,663.00 for the Sunrise Way Traffic Signal Interconnect, City Project 01-14.
SUMMARY:
Award of this contract will install traffic signal improvements along Sunrise Way, from East
Palm Canyon Drive to Tachevah Road, including interconnect and signal timing
coordination.
BACKGROUND:
The City of Palm Springs applied for and received a $120,000 Surface Transportation
Improvement Program (STIP) grant to construct traffic signal interconnect improvements
along Sunrise Way. Sunrise Way is the last remaining major arterial corridor to have its
traffic signals interconnected, with signal interconnect projects having been or nearly
completed along North, South and East Palm Canyon Drives, Indian Canyon Drive, Ramon
Road, and Tahquitz Canyon Way.
The Sunrise Way trafficsignal interconnect improvements have been designed by the City's
consultant,Albert Grover&Associates. On October 2, 2002,the City Council approved and
adopted the plans and specifications for this project, and authorized advertisement for
construction bids. The project consists of one Bid Schedule, and includes installation of
traffic signal interconnect equipment and modifications or replacement of existing traffic
signal controllers at the following locations:
Sunrise Way at Tachevah Road
Sunrise Way at Alejo Road
Sunrise Way at Amado Road
Sunrise Way at Tahquitz Canyon Way
Sunrise Way at Baristo Road
Sunrise Way at Ramon Road
Sunrise Way at Mesquite Avenue
Sunrise Way at East Palm Canyon Drive
The proposed interconnect system will allow for more efficient movement of traffic along this
major arterial corridor, as the traffic signal controllers at each intersection along the corridor
are timed and coordinated to provide a better opportunity for continuous movement of traffic
in one direction or the other.
Sunrise Way Traffic Signal Interconnect
November 20, 2002
Page 2
On October 8 and 15, 2002, the project was advertised for bids, and at 2:00 P.M. on
October 29, 2002, the Department of Procurement and Contracting received bids from the
following contractors:
Contractor Total Bid
1. Steiny and Company, Inc.; Corona, CA $160,663.00
2. Pete & Sons Construction, Inc.; Riverside, CA $165,000.00
3. DBX, Inc.; Temecula, CA $171,170.00
4. Lynch Communications, Inc.; Riverside, CA $184,000.00
The consultant's estimate was$136,000. The low bidder is Steiny and Company, Inc.,from
Corona, California. The company is a corporation and its officers are: J. O. Steiny,
Chairman; Susan Steiny, President; Richard Tesoriero, Vice-President; and Gayle
Kappelman,Secretary. Sufficient funds are available in accounts 1 33-4298-50 1 86(Sunrise
Way Interconnect) and 261-4491-50 1 86 (Sunrise Way Interconnect).
SUBMITTED:
/f
DAVID J. BARAKIAN
Director of Public Works/City Engineer
APPROVED:
DAVID H. READY
City Manager
ATTACHMENTS:
1. Minute Order
REVIEWED BY DEPT.OF FINANCE
n f I
CITY OF PALM SPRINGS
NOTICE INVITING BIDS
For constructing SUNRISE WAY TRAFFIC SIGNAL INTERCONNECT
City Project No. 01-14
N-1 NOTICE IS HEREBY GIVEN that sealed bids for the Sunrise Way
Traffic Signal Interconnect will be received at the office of the
Procurement Manager of the City of Palm Springs, California, until
2 : OOP.M. on October 29, 2002, at which time they will be opened and
read aloud.
N-2 DESCRIPTION OF THE WORK: The Work comprises the construction of a
traffic signal interconnect system, modifying traffic signals and all
appurtenant work on Sunrise Way from Tachevah Drive to East Palm Canyon
Drive in Palm Springs.
N-3 AWARD OF CONTRACT:
(a) The City reserves the right after opening bids to reject any
or all bids, to waive any informality (non-responsiveness) in a bid,
or to make award to the lowest responsive, responsible bidder and
reject all other bids, as it may best serve the interest of the City.
(b) As a condition of award, the successful bidder will be
required to submit payment and performance bonds and insurance.
N-4 BID SECURITY: each bid shall be accompanied by a certified or
cashier' s check or Bid Bond in the amount of 10 percent of the total
bid price, payable to the City of Palm Springs .
N-5 BIDS TO REMAIN OPEN: The Bidder shall guarantee the Total Bid
Price for a period of 60 calendar days from the date of bid opening.
N-6. CONTRACTOR' S LICENSE CLASSIFICATION: The Contractor shall
possess a valid Class A or C-10 Contractor license at the time of
submitting bids.
N-7 CALIFORNIA WAGE RATE REQUIREMENTS: The Contractor shall pay the
general prevailing rate of per diem wages as determined by the
Director of the Department of Industrial Relations of the State of
California for the locality where the work is to be performed. A copy
of said wage rates is on file at the office of the City Engineer.
The Contractor and any subcontractors shall pay not less than said
specified rates and shall post a copy of said wage rates at the
project site.
N-8 RETAINAGE FROM PAYMENTS: The Contractor may elect to receive 100
percent of payments due under the Contract Documents from time to
time, without retention of any portion of the payment by the City, by
SUNRISE WAY TRAFFIC SIGNAL INTERCONNECT
CITY PROJECT NO.01-14 NOTICE INVITING BIDS
9/26/02 Q PAGE 1
depositing securities of equivalent value with the City in accordance
with the provisions of Section 22300 of the Public Contract Code .
N-9 OBTAINING OR INSPECTING CONTRACT DOCUMENTS:
(a) Contract Documents may be inspected without charge at the
office of the City Engineer, 3200 East Tahquitz Canyon Way, Palm
Springs, CA 92262 .
(b) Complete sets of said Contract Documents may be purchased at
$35 . 00 per set and are obtainable from the office of the City
Engineer, 3200 East Tahquitz Canyon Way, Palm Springs, CA 92262 . No
refund will be made of any charges for sets of Contract Documents .
(c) An additional fee of $20 . 00 will be charged for sets of
documents sent by mail .
N-10 ADDRESS AND MARKING OF BIDS: The envelope enclosing the Bid
shall be sealed and addressed to the City of Palm Springs, and shall
be delivered or mailed to the Director of Procurement and Contracting
at 3200 East Tahquitz Canyon Way, Palm Springs, CA 92262 . The
envelope shall be plainly marked in the upper left hand corner with
the name and address of the Bidder and shall bear the words "Bid
For. . . " followed by the title of the Project and the date and hour of
opening Bids . The certified or cashier' s check or Bid Bond shall be
enclosed in the same envelope with the Bid.
BY ORDER OF THE CITY OF PALM SPRINGS
Date
By
David J. Barakian, PE
Director of Public Works/City Engineer
SUNRISE WAY TRAFFIC SIGNAL INTERCONNECT
CITY PROJECT NO.01-14 NOTICE INVITING BIDS
9/26/02 PAGE 2
MINUTE ORDER NO.
AWARDING CONTRACT TO STEINY AND COMPANY,
INC., IN THE AMOUNT OF $160,663.00 FOR THE
SUNRISE WAY TRAFFIC SIGNAL INTERCONNECT, CITY
PROJECT 01-14
I HEREBY CERTIFY that this Minute Order, awarding contract to Steiny and Company, Inc., in the
amount of$160,663.00 for the Sunrise Way Traffic Signal Interconnect, City Project 01-14, was
adopted by the City Council of the City of Palm Springs, California, in a meeting thereof held on the
201h day of November, 2002.
PATRICIA A. SANDERS
City Clerk
yb