HomeMy WebLinkAbout11/26/2002 - STAFF REPORTS (12) DATE: November 20, 2002 TO: City Council FROM: Public Works Director/City Engineer HOLD PUBLIC HEARING AND APPROVE PROPOSED CAMINO ALTURAS SEWER CONSTRUCTION REFUND AGREEMENT WITH BERNARD A. & MARY M. GUENTNER RECOMMENDATION: It is recommended that the City Council hold a Public Hearing and approve the attached resolution approving a Sewer Construction Refund Agreement between the City of Palm Springs and Bernard A. &Mary M. Guentner for the sewer main extension on Camino Alturas to Camino Monte and direct the City Clerk to record said agreement in the Office of the Recorder of Riverside County, California. SUMMARY: Under the terms of the Sewer Construction Refund Agreement, property owners that can now connect to the sewer main extension on Camino Alturas are required to reimburse the City prior to the issuance of a Sewer Construction Permit, in accordance with the assessment reimbursement fees set forth in the Agreement. The reimbursement is a proportionate share of the construction cost of the sewer. Upon receipt of the funds, the City reimburses the Guentners for the share amounts shown in the Sewer Construction Refund Agreement. The noticed Public Hearing gives the affected property owners a second opportunity to comment on the refund agreement in addition to the Public Meeting held with concerned property owners at City Hall on September 25, 2002. BACKGROUND: Bernard A. & Mary M. Guentner reside at 1921 Camino Monte and over a period of years had been experiencing sewer problems with their on-site septic system (their septic tank and cesspool had to be pumped on a frequent and increasing basis). Their neighbors had similar problems with their on- site septic systems as well (especially due to the poor percolation in the rocky hillside terrain in the area). The nearest sewer main was '/z block away on Camino Alturas; too far away for a lateral connection.After their attempts had failed to create a joint sewer district with neighbors to extend the sewer main to their end of the block at Camino Monte, the Guentners chose to extend the sewer main on Camino Alturas solely at their own expense. By letter dated October 28, 2001, the Guentners appealed to the City Engineer to create a Sewer Construction Refund Agreement. After receiving multiple competitive bids from licensed sewer contractors, the Guentners hired the low bidder, Tri-Star Construction & Excavation to construct an 8" public sewer main extension, manholes and appurtenances on Camino Alturas to Camino Monte for a total cost of$71,550. The remaining net cost, after deducting sewer lateral and on-site work at their own home came to $62,550, which is the net amount assessable to other property owners who connect to the Camino Alturas sewer main extension. The Camino Alturas sewer extension has been accepted by the City. 1 � 3� Under the terms of the Sewer Agreement, property owners fronting on the sewer that has been constructed are required to reimburse the City prior to the issuance of a Sewer Construction Permit, in accordance with the fees set forth in the Agreement. The reimbursement includes a proportionate share of the construction cost of the sewer. Upon receipt of the funds, the City reimburses the Guentners for the proportionate amounts shown in the Sewer Agreement, when or if neighboring property owners connect to the subject sewer main extension. There is no guarantee, however, by the City that other such sewer connections will be made in the future. The City Attorney has set a ten year time limit on the Sewer Refund Agreement from date of execution, with the ability to extend the agreement by mutual agreement of both parties. The Public Hearing will be the second opportunity for affected property owners to comment on the proposed Camino Alturas Sewer Refund Agreement. The first opportunity for affected property owners to comment was at a Public Meeting held at City Hall on September 25, 2002 after meeting notices were mailed to the 6 affected property owners on September 12, 2002. Three owners representing 2 of the 6 affected properties attended the meeting with City staff, discussing project costs, proposed assessments and scheduling. There is no cost to the City for the privately constructed Camino Alturas sewer main extension. David J. Barakian Public Works Director/City Engineer City Man ag— — ATTACHMENTS: 1. Resolution approving Sewer Refund Agreement 2. Notice of Public Hearing 3. Sewer Refund Agreement (4 pgs.) 4. Exhibit "A"- Sewer Refund Agreement Plat Map 5. Exhibit "B"- Financial Statement of Construction Costs 6. Exhibit"C"- Sewer Refund Agreement Procedural Check List REVIEWED BY DEPT.OF FINANCE HAUSERS\BobM\Camino Alturas Sewer.Council Report 11-20-02.wpd 2 CITY OF PALM SPRINGS NOTICE OF PUBLIC HEARING NOTICE IS HEREBY GIVEN that on November 20, 2002, at the hour of 7:00 p.m. or as soon thereafter as possible, the City Council of the City of Palm Springs will hold a public hearing with respect to the consideration of a Sewer Construction Refund Agreement ("Agreement") between the City of Palm Springs,California and Bernard A.&Mary M.Guentner("Agreement")to reimburse Mr. &Mrs.Guentner for the cost of an off-site public sewer extension on Camino Alturas to Camino Monte which benefits other properties. The properties affected are: Assessor's No. Palm Springs Street Address Assessment 513-380-032 450 Camino Alturas $12,510 513-380-053 400 Camino Alturas $12,510 513-380-063 1921 Camino Monte $12,510 513-380-071 380 Camino Alturas $12,510 513-400-001 1935 Camino Monte $6,255 513-400-002 1951 Camino Monte $6,255 The public hearing will take place on or about 7:00 p.m., or as soon thereafter as possible, and will be held at the Council Chambers of the City Council of the City of Palm Springs, 3200 E. Tahquitz Canyon Way, Palm Springs, California 92262. Interested persons wishing to express their views on the consideration of the Agreement will be given the opportunity to do so at the public hearing or may, prior to the time of the public hearing, submitwritten comments to David J. Barakian, Public Works Director/City Engineer, Public Works/Engineering Department, City of Palm Springs, 3200 E. Tahquitz Canyon Way, Palm Springs, California 92262, telephone number (760) 323-8253. Pursuant to California Government Code Sections 66016 and 66018,this Notice shall be published twice at least ten days prior to the public hearing, and sent at least 14 days prior to the public hearing to any interested person who has filed a written request. Dated: OCTOBER 18, 2002 PATRICIA A. SANDERS CITY CLERK Publication Dates: November 4, 2002 November 11, 2002 10 �3 SEWER CONSTRUCTION REFUND AGREEMENT BETWEEN THE CITY OF PALM SPRINGS, CALIFORNIA AND BERNARD A. & MARY M. GUENTNER SEWER AGREEMENT NO. THIS SEWER AGREEMENT made and entered into this_day of , 2002, between the CITY OF PALM SPRINGS, CALIFORNIA, a municipal corporation, hereinafter called the CITY, and BERNARD A. & MARY M. GUENTNER , hereinafter called the DEVELOPER. WHEREAS, the CITY has established a policy for sewer refund agreements by City Council Resolution No. 13487 dated August 6, 1980 and Resolution No. 16031 dated October 15, 1986,which by reference are hereby made a part of this agreement; and WHEREAS, the DEVELOPER is, at the time of this agreement, the owners of the residence at 1921 Camino Monte at intersection of Camino Alturas(Assessor's Parcel No.513-380-063),delineated on the plat"Camino Alturas Sewer Construction Refund Agreement"attached hereto, marked Exhibit"A", and hereby made a part; and WHEREAS, the sanitary sewers that are the subject of the AGREEMENT(Off-Site Sewers on Camino Alturas)have been dedicated to public use by the DEVELOPER, and have been accepted by the CITY; and WHEREAS, the CITY has determined that benefit from the construction of the Off-Site Sewers on Camino Alturas will accrue to properties connecting to the Off-Site Sewer("PARCELS"); and WHEREAS,the DEVELOPER has submitted a financial statement of construction costs totaling$71,550 (less $5,000 sewer lateral and $4,000 septic system abandonment at 1921 Camino Monte)= 62 550 net cost for said sewer main extension from TRI-STAR CONSTRUCTION & EXCAVATION dated February 14, 2002, copies of which are attached hereto and marked"Exhibit B", and made a part of this agreement; and WHEREAS, the DEVELOPER, in accordance with the before mentioned Council Resolution has requested that the CITY and the DEVELOPER enter into a Sewer Refund Agreement to reimburse the DEVELOPER for the cost of off-site sewer which benefits other properties; and WHEREAS, the CITY has determined that benefit from the construction of off-site sewer will accrue to properties connecting to the off-site sewer; and WHEREAS, the CITY had determined that said benefit will be in direct proportion to Parcel Nos. 513-380-032, 513-380-053, 513-380-063, 513-380-071, 513-400-001 and 513-400-002 as shown on Exhibit "A"; and WHEREAS, it is in the best interests of the DEVELOPER and the CITY to establish the AGREEMENT to provide for an equitable apportionment of construction costs for the Off-Site Sewers to properties benefitting from the construction of the Off-Site Sewer. 1 NOW,THEREFORE,THIS AGREEMENT WITNESSETH that for good and valuable consideration,the receipt and sufficiency of which is hereby acknowledged, and in consideration of the mutual covenants indicated between the CITY and the DEVELOPER, it is hereby agreed that: SECTION 1. Assessments. Developers, owners, or lessees of lots shown on Exhibit"A"abutting Off- Site Sewers shall pay to the CITY the amount shown herein,plus sewer connection charges in effect at such time prior to a permit being issued for connection to the Off-Site Sewers. Upon receipt of such payment CITY shall pay the DEVELOPER the amount shownherein. The Assessment for Parcels is hereby established at a Calculated Benefit for Six (6) Properties (Based on total net sewer main construction cost of$62,550) as follows: ASSESSOR'S NO. ASSESSMENT PALM SPRINGS STREET ADDRESS 1. 513-380-032 $12,510 450 Camino Alturas 2. 513-380-053 $12,510 400 Camino Alturas 3. 513-380-063 $12,510* 1921 Camino Monte (Note#1)* 4. 513-380-071 $12,510 380 Camino Alturas 5. 513-400-001 $ 6,255 1935 Camino Monte (Note#2)** 6. 513-400-002 6,25 1951 Camino Monte (Note#2)** TOTAL $62,550 The above assessments represent a proportionate redistribution of the costs of the construction of the Off-Site Sewers based on each Parcel's (proportionate benefit) in relation to sewer main extension costs. *Note #1: Bernard A. & Mary M. Guentner, the DEVELOPER, are the sole property owners who constructed the subject sewer main extension(contracted to Tri-Star Construction&Excavation)at their sole expense. *($12,510 amount indicated is for proportionate spread purposes only-No additional payment required) **Note#2: Properties at 1935 and 1951 Camino Montewere assessed ('/2 share each) because they will be required to extend the sewer main to serve their properties prior to connection, since the subject sewer main extension does not directly front their properties.Their total connection cost will therefore be more than the '/z share cost above after their additional cost for further sewer main extension is added to their costs. A separate sewer reimbursement agreement would be initiated by the first of these 2 property owners to extend the main, unless they mutually agree to share the extension costs up front. 2 / nn L � /i� SECTION 2. Payment. It shall be the duty of the DEVELOPER to keep CITY informed in writing as to the location at which payment shall be made. CITY should make payment within 90 days after receiving the payment from the assessee. If DEVELOPER does not have a written address for payment on file with the CITY, or if the address has expired, CITY shall retain assessment. No interest shall assume on late payment. SECTION 3. Successors. The right of DEVELOPER to receive payment as stated herein shall not be transferrable to successors and assigns but shall remain personal with DEVELOPER. SECTION 4. No Representations or Liability. CITY makes no representation as to (a) when, if ever, it will receive the above costs assessed on the Parcels, (b) its legal liability to enforce the collection of the fees assessed, (c) changes in the law affecting the CITY's ability to charge fees and assessments. Due to these factors, the CITY shall have no liability whatsoever to any of the developers, owners or lessees for the collecting of the assessments stated in Section 1 above,orforthe payment of such sums to DEVELOPER. SECTION& Term. This agreement shall terminate ten(10)years from the date of the Agreement first above written, unless extended by mutual agreement of the parties. SECTION 6. Amendment The parties hereto mutually agree that this Agreement maybe amended at any time by the mutual consent of the DEVELOPER and CITY and by recordation of an instrument in writing. SECTION 7. Integration It is understood that there are no oral agreements between the parties hereto affecting this Agreement and this Agreement supersedes and cancels any and all previous negotiations, arrangements, agreements and understandings, if any, between the parties, and none shall be used to interpret this Agreement.Any resolutions or actions of the Council inconsistent with the foregoing are hereby rescinded to the extent of their inconsistency. This Agreement incorporates all the understandings of the parties. SECTION 8. Recordation The City Clerk shall record this AGREEMENT in the Recorder's Office of the County of Riverside, California. 3 l � �b IN WITNESS WHEREOF, the CITY and the DEVELOPER has hereunto caused these presents to be executed the day and year first above mentioned. ATTEST: DEVELOPER: By BERNARD A. GUENTNER MARY M. GUENTNER ATTEST: CITY OF PALM SPRINGS, CALIFORNIA By City Clerk City Manager Reviewed and Approved By: City Attorney Attachments: 1. Exhibit "A" Sewer Refund Agreement Plat (Camino Alturas & Camino Monte) in Palm Springs, CA. 2. Exhibit "B" Financial Statement of Construction Costs (Tri Star Construction & Excavation) 3. Exhibit "C" Sewer Refund Agreement Procedural "Check List' H1USERS\BobM\Camino Alturas.Sewer Reimb.Agree.Bernard Guentner.10-16-02.wpd 4 1 :3 4 Po{4 ti p0. Mo 2.783f 3.7/9 2* Par. 0 v" Par 5 zk•• _ ;� 0.54Ac �yX " rS r' +� `� 27 26 „ a \ 3. b44a ' 1S 'Par,� RM gg � '- GharghowY 3 '� 59Act ,,,. 302 i 380 Camino Alturas I Per./x.! .} 3 as N 1 StOoe Pll�iae a + ; APN#'13-380-071 ' +-"4 K I ��50� 133a0A 5 p6! 4 A '•ir .!%r U�.7 • .7 Sol 0.5 Act 4TF ►.K, t~ PM�Ni 29 �Ln lO. P e\ = > a 24 O �s o i �soya��p�gop6 _ �o0 O ea g• ^� rror. ♦ c 0 9'bh �,h 7/ \ 0.84t Ac. 0 rt pt�AL 'mac SIP e9 K %lt Gamto o m �`� 5. o W W 70 nr � v Aug 12 02 07: 48a Tri Star Cons. 7603217798 p. z r * Contracting, Excavation, Grading "We dig the Coachella Valley„ Friday,August 09,2002 City of Palm Springs Engineering P.O.Box 2743 Palm Springs, CA 92263 Attn: Marna Re: Bernard Guenther Contract,Camino Alturas @ 1921 Camino Del Monte Dear Mama: The contract to Mr. Guenther is in the amount of$71,550.00. The contract consists of the following: 0 1) On-site work for septic system abandonment and connection to the city sewer system is in the amount of$4,000.00. 2) Off-site work for sewer main extension&lateral is in the amount of A67,550.00 The subcontract costs for the off-site worlkare as follows: Fire department $5,629.76 Engineering $ 1,850.00 Man holes $2,204.01 Asphalt paving $ 7,293.00 1 Permits $2,979.30 I Shoring 615.44 Subtotal $20,571.51 Move-inlout 1,500.00 $22,071.51 422,071.51 Direct equipment,labor&material $45,478A9 The direct charges are broken down as follows: I •- r Sewer main extension $40,478A9 ' Sewer lateral $ 5,000.00 Sincerely, Lan J. Owens, President -Bus(760)321-0898 P.O.Box5 ,Cathedral va Gcaa thed City, ornia 92235 Fax(760).321-7798 i2 r EXHIBIT "B" 1 :3140 SEWER CONSTRUCTION REFUND AGREEMENT Procedures 1. Copy of at least two bids from contractors to do construction 2. Copy of City construction permits 3. Copy of itemized invoice for work done 4. Copy of proof of payment(cancelled checks or cancelled invoices) 5. Prepare agreement with Exhibits (See samples) Route to City Engineer for review Route to City Attorney for review 6. Schedule meeting with developer and affected property owners to review costs and distributions to affected properties 7. Prepare Notice of Public Hearing letter to be sent to all affected properties (see samples) City Clerk will mail these 8. Prepare Notice of Public Hearing (see samples) publish two times starting at least 15 days prior to date of Public Hearing(City Council meeting) 9. Prepare staff report and Resolution Attach Agreement Route to City Engineer for final review and signature on staff report 10. Give items listed in#9 in duplicate to the City Clerk two weeks prior to date of Council meeting 11. City Clerk sends agreement to Riverside County Recorder's Office for recordation. EXHIBIT "C" / '31 /o CITY OF PALM SPRINGS NOTICE OF PUBLIC HEARING NOTICE IS HEREBY GIVEN that on November 20, 2002, at the hour of 7:00 p.m. or as soon thereafter as possible, the City Council of the City of Palm Springs will hold a public hearing with respect to the consideration of a Sewer Construction Refund Agreement ("Agreement") between the City of Palm Springs,California and Bernard A.&Mary M.Guentner("Agreement")to reimburse Mr. &Mrs. Guentner for the cost of an off-site public sewer extension on Camino Alturas to Camino Monte which benefits other properties. The properties affected are: Assessor's No. Palm Springs Street Address Assessment 513-380-032 450 Camino Alturas $12,510 513-380-053 400 Camino Alturas $12,510 513-380-063 1921 Camino Monte $12,610 513-380-071 380 Camino Alturas $12,510 513-400-001 1935 Camino Monte $6,255 513-400-002 1951 Camino Monte $6,255 The public hearing will take place on or about 7:00 p.m.,or as soon thereafter as possible, and will be held at the Council Chambers of the City Council of the City of Palm Springs, 3200 E. Tahquitz Canyon Way, Palm Springs, California 92262. Interested persons wishing to express their views on the consideration of the Agreement will be given the opportunity to do so at the public hearing or may, prior to the time of the public hearing,submitwritten comments to David J. Barakian, Public Works Director/City Engineer, Public Works/Engineering Department, City of Palm Springs, 3200 E. Tahquitz Canyon Way, Palm Springs, California 92262, telephone number (760) 323-8253. Pursuant to California Government Code Sections 66016 and 66018,this Notice shall be published twice at least ten days prior to the public hearing, and sent at least 14 days prior to the public hearing to any interested person who has filed a written request. Dated: OCTOBER 18, 2002 PATRICIA A. SANDERS CITY CLERK Publication Dates: Novemberl ,2002 November 8, 2002 L y Proof of Publication + In Newspaper STATE OF CALIFORNIA County of Riverside Laura Reyes says: 1. 1 am a citizen of the United States, a resident of the City of Indio, County of Riverside, State of California, and over the age of 18 years. 2. 1 am the Office & Production Manager CITY OF PALM SPRINGS NOTICE OF PUBLIC HEARING of The Public Record, a newspaper of NOTICE IS HEREBY GIVEN that on November 20,2002,at 9 general printed and the hour olT00p,m.drop soon thereafter as possible,the City p Council of the City of Palm Springs will hold a public headog the City of Palm Springs, County of with respect to the conald,,dtion Of a Sewer Construction__ Riverside State of California. Said The Refund Agreement("Agrdeme"t") between the City of Palm Springs. California and Bernard A 8 Mary M Bremner Public Record is a newspaper of general eAgr.amere in reimbbrse Mr.&Mrs Gardiner far the cost Of circulation as that term Is defined n an op-site public sewer extension on Camino Alluras to Camino Monte which benefits dtherpraperlies The properties affected Government Code section 6000, its are Assessor's N ' Palm S r St I_Adtl g� As v t status as such having been established 513-380-032 450 Camino Alturas $12,510 513-380-053 400 Camino Alturas $12,510 by judicial decree of the Superior Court of 513-380-063 1921 Camino Monte $12.610 the State of California in and for the 513-380 380 Camino Allures $12,510 513-400-001 1935 Camino Monte $6.255 County of Riverside in Proceeding No. 513-400-002 1951 Camino Monte $6,255 Indio 49271 dated March 31 1987 The public hearing will take place on or about e 7.00 p or,or as soon[hereafter as possible,and w111 be held at entered in Judgment Book No. 129, the Council Chambers of the City Council of the City of Palm Springs, 3200 E. Tahqui[z Canyon Way, Palm Springs, page 355, on March 31, 1987, California 92262. Interested persons wishing to express their 3. The Public Record is a newspaper of views on the consideration of the Agreement will be given the opportunity to de so or the public hearing or may,prior to the general circulation ascertained and time of the public hearing,submit written comments,°David established in the Cityof Palm Springs inBarakian, Public Works Director/CRy Engineer, Public Works/Engineering Department,City of Palm Springs,3200 E. the County of Riverside, State of Tahquttz Canyon Way, Palm Springs, California 92262, lele California Case No. RIC 358286 Filed phone ndmbePursu Pursuant to 53 , r Pursuan! to California Government Code June 8, 2001. Sections 66015 and 66018,this Notice shalfee published twice at least ten days prior to the public hearing,and sent at least 14 4. The notice, of which the annexed Is a days prior to the public hearing to any interested person who true printed copy, was published in the has filed a written request Dated OCTOBER 18.2002 newspaper on the following publication PATRICIA A.SANDERS CITY CLERK dates t0 wit: Odtober zs,November 6,20g2 October 29, 2002 November 5, 2002 1 certify under penalty of perjury that the above is true and correct. Dated at Palm Springs, California, this 5th day of November 2002. eyes & Produc ana er PALM City of Palm Springs Department of Public Works and Engineering 3200 E.Tabgmrz Canyon Way • Palm Springs, California 92262 Tel: (760) 323-8253 Fax: (760) 322-8360 • Web:www.a.palm-spnngs.ca.us .aim"u November 21, 2002 Bernard A. & Mary Guentner 1921 Camino Monte Palm Springs, CA 92264 Re: Proposed Sewer Refund Agreement SEWER EXTENSION ON CAMINO ALTURAS TO CAMINO MONTE PUBLIC HEARING NOTICE Dear Mr. & Mrs. Guentner (1921 Camino Monte, Palm Springs, CA, APN#513-380-063): As you were previously notified by phone, the Public Hearing for the above referenced subject has been rescheduled. The meeting is now scheduled for Tuesday, November 26, 2002 at 7:00 pm. The meeting will be held at City Council Chambers in Palm Springs City Hall, located at 3200 East Tahquitz Canyon Way, Palm Springs, CA 92262 Sincerely4L David J. Barakian Director of Public Works/City Engineer cc: David H. Ready, City Manager David Aleshire, City Attorney Trisha Sanders, City Clerk Post Office Box 2743 • Palm Springs, California 92263-2743 PALM ,0"./ SAS 4x y s F kw1�a City of Palm Springs „ P g Department of Public Works and Engineering oQA,t: 3200 E.Tabquia Canyon Way • Palm Springs, California 92262 Tel. (760)323-8253 • Fax: (760) 322-8360 • Web www.ci.palm-springs.ca.us November 21, 2002 Georgia Williams and Gary B. Stobert P.O. Box 9434 Palm Springs, CA 92263 Re: Proposed Sewer Refund Agreement SEWER EXTENSION ON CAMINO ALTURAS TO CAMINO MONTE PUBLIC HEARING NOTICE Dear Ms. Williams & Mr. Stobert (400 West Camino Alturas, Palm Springs, APN#513-380-053): As you were previously notified by phone, the Public Hearing for the above referenced subject has been rescheduled. The meeting is now scheduled for Tuesday, November 26, 2002 at 7:00 pm. The meeting will be held at City Council Chambers in Palm Springs City Hall, located at 3200 East Tahquitz Canyon Way, Palm Springs, CA 92262. Sincerely Av'� David J. Barakian Director of Public Works/City Engineer cc: David H. Ready, City Manager David Aleshire, City Attorney Trisha Sanders, City Clerk Post Office Box 2743 0 Palm Springs, California 92263-2743 P M S Z City of Palm Springs ' r�"I Ni _; Department of Public Works and Engineering 3200 F.Tah uirz Canyon Way Palm Springs, California 92262 O .«.,,...'' �. 9 Y Y ' FO RPS� Tel: (760) 323-8253 • Fax: (760) 322-8360 • Web- www.ci.palm-spriugs.ca.us November 21, 2002 Ayad M. and Gihan Gharghoury 380 West Camino Alturas Palm Springs, CA 92264 Re: Proposed Sewer Refund Agreement SEWER EXTENSION ON CAMINO ALTURAS TO CAMINO MONTE PUBLIC HEARING NOTICE Dear Mr. & Mrs. Gharghoury (380 Camino Altuas, Palm Springs, APN#513-380-071): As you were previously notified by phone, the Public Hearing for the above referenced subject has been rescheduled. The meeting is now scheduled for Tuesday, November 26, 2002 at 7:00 pm. The meeting will be held at City Council Chambers in Palm Springs City Hall, located at 3200 East Tahquitz Canyon Way, Palm Springs, CA 92262. Sincerely, 0- (, David J. Barakian Director of Public Works/City Engineer cc. David H. Ready, City Manager David Aleshire, City Attorney Trisha Sanders, City Clerk Post Office Box 2743 0 Palm Springs, California 92263-2743 i� PALM O zz1us0� City of Palm Springs Department of Public Works and Engineering 3200 E.Tahquitz Canyon Way • Palm Springs, California 92262 a(i FO , \P '. Tel (760) 323-8253 ' Fax: (760) 322-8360 • Web www.ci.patm-springs.ca.us November 21, 2002 Ms. Edna Mae Beach 1935 South Camino Monte Palm Springs, CA 92264 Re: Proposed Sewer Refund Agreement SEWER EXTENSION ON CAMINO ALTURAS TO CAMINO MONTE PUBLIC HEARING NOTICE Dear Ms. Beach (1935 Camino Monte, Palm Springs, APN#513-400-001): As you were previously notified by phone, the Public Hearing for the above referenced subject has been rescheduled. The meeting is now scheduled for Tuesday, November 26, 2002 at 7:00 pm. The meeting will be held at City Council Chambers in Palm Springs City Hall, located at 3200 East Tahquitz Canyon Way, Palm Springs, CA 92262. Sincerely, David J. Barakian Director of Public Works/City Engineer cc: David H. Ready, City Manager David Aleshire, City Attorney Trisha Sanders, City Clerk Post Office Boy; 2743 0 Palm Springs, California 92263-2743 pALAq `� G;r�llu�i4,p City of Palm Springs �i I -4r it v, I, Ig / Department of Public Works and Engineering � FOhPil� 3200 E.Tahquitz Canyon Way • PaLm Springs, California 92262 91 0- ' Tel (760) 323-8253 • Fax. (760)322-8360 • Web: www.ci.palm-spcings.ca.us November 21, 2002 Harold E. or David L. McKinney 1951 South Camino Monte Palm Springs, CA 92264 Re: Proposed Sewer Refund Agreement SEWER EXTENSION ON CAMINO ALTURAS TO CAMINO MONTE PUBLIC HEARING NOTICE Dear Mr. McKinney (1951 South Camino Monte, Palm Springs, APN#513-400-002): As you were previously notified by phone, the Public Hearing for the above referenced subject has been rescheduled. The meeting is now scheduled for Tuesday, November 26, 2002 at 7:00 pm. The meeting will be held at City Council Chambers in Palm Springs City Hall, located at 3200 East Tahquitz Canyon Way, Palm Springs, CA 92262. Sincerely, David J. Barakian Director of Public Works/City Engineer CC' David H. Ready, City Manager David Aleshire, City Attorney Trisha Sanders, City Clerk Post Office Box 2743 0 Palm Springs, California 92263-2743 OF PALM City a , of Palm Springs Department of Public Works and Engineering �RaORAtO� \^�,,.,''P ,-' 3200 E.Ta6quitz Canyon Way • Palm Springs,California 92262 9<i Fp?,p1\ TeL (760) 323-8253 • Fax (760) 322-8360 • Web. wwwci.palm-springs.ca us November 21, 2002 Georgia Williams & Gary B. Stobert P.O. Box 9434 Palm Springs, CA 92263 Re: Proposed Sewer Refund Agreement SEWER EXTENSION ON CAMINO ALTURAS TO CAMINO MONTE PUBLIC HEARING NOTICE Dear Ms. Williams & Mr. Stobert (450 West Camino Alturas, Palm Springs, APN#513-380-032): As you were previously notified by phone, the Public Hearing for the above referenced subject has been rescheduled. The meeting is now scheduled for Tuesday, November 26, 2002 at 7:00 pm. The meeting will be held at City Council Chambers in Palm Springs City Hall, located at 3200 East Tahquitz Canyon Way, Palm Springs, CA 92262. Sincerely, David J. Barakian Director of Public Works/City Engineer cc: David H. Ready, City Manager David Aleshire, City Attorney Trisha Sanders, City Clerk Post Office Box 2743 • Palm Springs, California 92263-2743 RESOLUTION NO. OF THE CITY COUNCIL OF THE CITY OF PALM SPRINGS, CALIFORNIA, AUTHORIZING AND APPROVING THE CAMINO ALTURAS SEWER CONSTRUCTION REFUND AGREEMENT WITH BERNARD A. &MARY M. GUENTNER WHEREAS, by Resolution No. 13773 of the City Council, dated April 15, 1981, a policy was established for the formation of Sewer Construction Refund Agreements; and WHEREAS Bernard A. & Mary M. Guentner have caused to be constructed an off-site sanitary public sewer extension with manholes and other appurtenances on Camino Alturas to Camino Monte, which has been connected to the existing City sewer system; and WHEREAS Agreement No. provides for collection by the City the proportionate reimbursement costs assessed to neighboring properties connecting to this off-site public sewer extension on Camino Alturas to Camino Monte; and WHEREAS the funds collected from the neighboring property owners for connecting to the Camino Alturas public sewer extension shall be reimbursed to Bernard A. & Mary M. Guentner under the terms of the Sewer Construction Refund Agreement. NOW THEREFORE BE IT RESOLVED that the City Council of the City of Palm Springs does hereby authorize and approve Agreement No. ADOPTED this_day of , 2002. AYES: NOES: ABSENT: ATTEST: CITY OF PALM SPRINGS, CALIFORNIA By: City Clerk City Manager REVIEWED AND APPROVED: