HomeMy WebLinkAbout2/19/2003 - STAFF REPORTS (9) DATE: February 19, 2003 TO: City Council FROM: City Engineer APPROVE CONSTRUCTION CHANGE ORDER NO. FIVE(5)TO DBX, INCORPORATED, CITY PROJECT 00-05. RECOMMENDATION: That the City Council approve Construction Change Order No. Five (5) to DBX, Incorporated, for an increase of $9,506.89 for the Tahquitz Canyon Way Signal Interconnect, City Project Number 00-05. SUMMARY: This change order to the Tahquitz Canyon Way Signal Interconnect project totals $9,506.89, however the aggregate amount of all change orders will now exceed $25,000.00. Therefore, in accordance with the terms of the Procurement Ordinance, Council approval is required. BACKGROUND: On June 19, 2002, City Council of the City of Palm Springs awarded DBX Incorporated the contractforthe Tahquitz Canyon Way Signal Interconnect project. It was determined in the field by both the City and contractor that the existing conductors for the traffic signal at Tahquitz Canyon Way and Avenida Caballeros are in bad condition. Per the recommendation of the Director of Public Works/City Engineer, the contractor shall remove the existing conductors and replace them with new conductors per plans and specifications. (Increased cost = $8,800.00) On Change Order No. 2, the contractor was to provide and install a Type III AF Service Pedestal and Cabinet at the intersection of Sunset Way and Tahquitz Canyon Way to complete the full modification of the traffic signal system. SCE determined that the existing electrical connection from their facility to the existing service pedestal,which provides electrical service to the landscape median and the traffic signal, is sub-standard. In order to upgrade the electrical service to SCE standards, for the proposed use, SCE requires the work within their vault to be performed only by their approved contractor. This work will be performed by Weissker, Inc., paid by DBX and this change order will reimburse DBX for this required cost. (Increased cost = $ 706.89) Additional working days are proposed to be added to the contract in accordance with the terms of the change order. 4?A City Project 00-05 Tahquitz Canyon Way Signal Interconnect Project City Council Report Page 2 of 2 Sufficient funds are available in account number 133-4298-50173 (Tahquitz Canyon Signal Interconnect). SUBMITTED: �e , DAVID J. BARAKIAN City Engineer APPROVED: DAVID H. READY City Manager ATTACHMENTS: 1. Minute Order 2. Change Order No. One (5) REVIEWED BY DEPTH. OF FINANCE �y� Z CITY OF PALM SPRINGS CONTRACT CHANGE ORDER To: DBX, Incorporated Date: January 30,2003 42066 Avenida Alvarado, Suite C Project No.: C.P.00-05 Temecula,CA 92590 Project Name: Tahquitz Canyon Way Signal Interconnect Change Order No.: Five(5) Attn: Jim Perry, President Contract Purchase No.: 212078 Account Number(s): 261-4491-50173, 134-4498-50173, 261-3201-52043 133-4298-50173 Agr.# 4522 M.O.# 7099 Res.# A. CHANGES IN WORK: Increase to Contract Bid Item (New)-Schedule A: Item Description D Remove and Replace existing conductors at Tahquitz Canyon Way and Avenida Caballeros Increase to Contract Bid Item(New)-Schedule E: Item Description B Install stub-out from existing SCE vault to proposed service pedestal B. CHANGES IN CONTRACT COST: Increase to Contract Bid Item(New)-Schedule A: Item Description D Remove and Replace existing conductors at Lump Sum $ 8,800.00 Tahquitz Canyon Way and Avenida Caballeros Increase to Contract Bid Item (New)-Schedule E: Item Description B SCE's contractor to install stub-out from existing Lump Sum $ 706.89 SCE vault TOTAL CHANGE ORDER = $ 9,506.89 NOTE: No additional markup will be added to any items in this Contract Change Order. All cost per each item are final. C.REASON FOR CHANGE: It was determined in the field by both the City and contractor that the existing conductors for the traffic signal at Tahquitz Canyon Way and Avenida Caballeros are in bad condition. Per the recommendation of the Director of Public Works/City Engineer,the contractor shall remove the existing conductors and replace them with new conductors per plans and specifications. (Increased cost=$8,800.00) On Change Order No. 2, the contractor was to provide and install a Type III AF Service Pedestal and Cabinet at the intersection of Sunset Way and Tahquitz Canyon Way to complete the full modification of the traffic signal system. SCE determined that the existing electrical connection from their facility to the existing service pedestal, which provides electrical service to the landscape median and the traffic signal, is sub-standard. In order to upgrade the electrical service to SCE standards, for the proposed use, SCE requires the work within their vault to be performed only by their approved contractor.This work wilt be performed by Weissker, Inc.,paid by DBX and this change order will reimburse DBX for this required cost. (Increased cost=$ 706.89) q143 January 30, 2003 City Project 00-05 Tahquitz Canyon Way Signal Interconnect Change Order No. Five (5) Page 2 of 2 (Continued) C. REASON FOR CHANGE: Additional working days to be added per the following: Schedule A, Bid Item No.7,Tahquitz Canyon Way and Calle Encilia 5 days added for delays while staff investigated locations of controller cabinet and service pedestal with respect to existing right-of-way. Schedule A, Bid Item D,Tahquitz Canyon Way and Avenida Caballeros 1 day added to remove and replace conductors Schedule E, Bid Item No. B, consideration of time adjustment will be deferred until completion of the work. Determination of commensurate time extension will be in accordance with the provisions of Sec. 8-1.07 of the Standard Specifications, due to SCE's work schedule to coordinate work to de-energize existing service pedestal and re-energize new service pedestal. D.SOURCE OF FUNDS: Tahquitz Canyon Signal Interconnect Account No. 133-4298-50173 $ 9,506.89 Summary of Costs Contract Time Original Contract Amount: $755,303.00 Original Completion Date: Dec.12,2002 This Change Order: $ 9,506.89 Days Added for this C.C.O.: 6 Previous Change Order(s): $ 22,212.57 Previous Days Added: 7 Revised Contract Amount: $787,022.46 Revised Completion Date: Jan.3,2003 I have received a copy of this Change Order and the City Approval: above AGREED PRICES are acceptable to the contractor. Submitted By Date By Field Engineering Supervisor Approved Byr Date Title Director of Public Works/City Engineer Date Approved by Date City Manager Distribution: Original Conformed Copies Conformed-File Copy Engineering (1) Engineering File (1) Finance (1) Engineering Field Inspector (1) Contractor (1) Engineering Field Supervisor (1) City Clerk (1) Purchasing Agent (1) oqftq MINUTE ORDER NO. APPROVING CONSTRUCTION CHANGE ORDER NO. FIVE (5) TO DBX, INCORPORATED, FOR AN INCREASE OF $9,506.89 FOR THE TAHQUITZ CANYON WAY SIGNAL INTERCONNECT, CITY PROJECT NUMBER 00-05. I HEREBY CERTIFY that this Minute Order, approving Construction Change Order No. Five (5) to DBX, Incorporated, for an increase of $9,506.89 for the Tahquitz Canyon Way Signal Interconnect, City Project Number 00-05, was adopted by the City Council of the City of Palm Springs, California, in a meeting thereof held on the 19" day of February 2003. Patricia A. Sanders City Clerk a