HomeMy WebLinkAbout3/5/2003 - STAFF REPORTS (15) MEMORANDUM
PALM SPRINGS INTERNATIONAL AIRPORT
From the desk of: Allen F. Smoot, A.A.E., Executive Director - Airports
DATE: March 5, 2003
TO: City Council
SUBJECT: CONVENTION CENTER EXPANSION—PHASE 11 UPDATE
On February 13, 2003, City Council reviewed a series of suggested expansion options and provided direction that
Option 5 was preferred with the elimination of the"L" shaped Exhibit Hall and an accompanied reduction in pre-
function space. City Council was also interested in a flexible design which might include up to 20,000 sq.ft. for a
ballroom/meeting room space. Project funds that the Council made available for the project were as follows:
Total Funding Available $37,868,954.
Less Phase I Cost (3,125,000.)
Total Available for Phase II $34,743,954.
Less Soft Costs (3,978,442.)
Less Pre-Opening Marketing Allowance (1,500,000.)*
Less 500 Space Parking Allowance (925,000.)
Less FF&E Allowance (400,000.)
Total Available for Construction $27,940,512,
*Subject to further review by City Council.
City Council also expressed that a $1 million construction contingency was inadequate as was $400,000 for site
landscaping. Staff then assigned a$2.2 million value to the construction contingency and increased the allowance
for landscape to$650,000. With these changes, the Option 5 project would exceed budqet by $2 to$2.5 million.
With the above parameters,the designers and the design team went back to work to refine the design to bring it into
budget and provide for greater flexibility. After reviewing several more options, the committee recommended
Option #10, (see attached drawing) with a concern over the feasibility and cost of restructuring the Oasis 5
mezzanine area yet remaining. The structural engineer has completed his review and has found the restructuring
is impractical and cost prohibitive. Option#11 is also attached. This option shows Oasis 5 remaining and actually
being expanded by a couple thousand square feet and a resultant 16,000 sq.ft.flex space for ballroom and meeting
rooms. The priority, as originally described by the Convention Center, was more meeting rooms and ballroom if
possible.
Following the two drawing attachments are,first,the original exhibit on howwe raise the$37.8 million"Total Funding
Available" and second, a new cost estimate sheet.
Amado Road
--�--—4Q2— ] �C \ I 'Column Free Flex Space
'ExhibR antl Flex Space Connectetl by 66'Amxall Connection
// I 'MustCerro and Relocane s,,4` s,ne MecM1 Meaabove Oasis5 I 'Munn Demo antlr desgn sesmc sWcwral systemwth lM1ree new
olumns
y I 'Layer Oasts at Amatlo
i
----- a j
Option #10
Pnl
a� 1n Exhibit 94,239 sf
�NbAH-
FWS,® Flex Space(ballroom) 20,035 sf
mass
I Replace Mech Mezz 1,500 sf
Add Admin + Mech 2,250 sf
Overall Reduct. 5,010 sf
A. ' t t 1 w ali F i w E7 11 j Feb, 26, 2003
Scale: NTS
` � 3E � r •,a � I
I c
Fentress
------ ------ Bradburn
- _- -�- - — - - Q
A R tu I T E ri T L T D.
Architecture • Inferiors . Planning
Andreas
Amado Road
^�_ V _V_" -�' Z-"y— \ ! •Keep axis ga,exwong slmclu2lsystem
Ke tin mach me,oaame above Oasts 5
///
3interwrmWmns between . fsS&Flex Space)
sule
1 'L Get approximately t Option
mare sf(but i$600K mlerwr columns)
! -Lessdxpensive that OpCwn%16($660$666K mnge)due mIsms
ncluded above\ I'Much less functional back of house
Less functional food]service
Less functional loading dock
Layer oasis at Amatlo
i
-¢ \1
! I
u,. a ! Option #11
(((lll��777)�
0 u 173 s3ms nca !
_ ! Exhibit 94,239 sf
a „,n axnmunao .— � 1 I
w.a3s r y
Oasis 5 X 7,061 sf
Flex Space(ballroom)16,894 sf
ll Add Mech + Admin 2,250 sf
t
_ ! Overall Reduct. 5,251 sf
Feb. 26, 2003
o
$ 1 ! Scale: NTS
Q Fentress
-- - -
��- Bradburn
A R C H I T E C T S L T D.
Architecture • Interiors - Planning
tl !
Andreas �
I
CONVENTION CENTER EXPANSION BOND ISSUE
Funding Scenarios For Phase II
TOT Plus Interest
(Plus Growth)
Revenue Available Annually $2,000,000.
Bond Proceeds 38,080,000.
Cost of Issue (1,251,782.)
Reserve Fund (2,36.5,000.)
Capitalized Interest (3,461,677.)
Net Bond Proceeds 31,001,541.
Phase 1I Civil Design Savings 100,000,
TOT Collections
FY 02-03 1,700,000.
FY 03-04 1,785,000.
FY 04-05 1,838,550.
FY 05-06 1,893,707.
Net Debt Service,FY 05-06 (449,844.)
Total Funding Available 137,868,954. w�
CONVENTION CENTER PHASE II EXPANSION
Cost Estimate March 5,2003
Total Available for Construction $27,940,512.
Less Construction Contingency (2,200,000.)
$25,740,512.
Current Square Footage Based Estimate (26,253,090.)
(Option 10 or 11)
Current Overrun ($512,578.)
• Current estimate includes no dollars to restructure OASIS 5 mezzanine.
($500,000 to $700,000)
• Current estimate includes no dollars to refurbish existing meeting rooms or restrooms.
($500,000)
• Current estimate includes only $650,000 for landscaping compared to an estimate of up
to $1.8 million.
• Current estimate assumes we will have sufficient savings in the current per square foot
cost in pre-fimetion to offset exterior finishes and covered areas.
• Current estimate does not include a major rebuild of the HVAC system or dollars for the
deferred maintenance items.
PSCC MARKETING
PROGRAM SUMMARY
Pre-Opening Marketing
March 2003 - March 2005
Pre-opening Timeline
• 22 Months Out: Initiate creative development of marketing materials,
including advertising, brochures, meeting planner kits, etc. Secure future
advertising placements.
• 18 Months Out: Introduce new Convention Center to key clients using
collateral materials, site inspections, internet and trade shows. First release
of advertising program, and announcements at key trade meetings
(American Society of Association Executives [ASAE], International
Association of Exposition Managers [IAEM], etc.).
• 16 Months Out: Begin ramp-up of public relations campaign highlighting
project milestones (topping off, human interest, advance bookings of
interest, etc.).
• 12 Months Out: Peak activity in terms of advertising, PR and promotional
activity, working with potential clients.
• 1111�th4 x, Sep �raragements for grand oper� ng, ribbon cutting,
amillarttatio ours; -et c. ��zo all post=operling collateral materials.
Prepared by 3/5/2003 Page 1
Months Before Building Opening: 22 Months as of March 2003
FY 2002- FY 2003- FY 2004-05 Category
03 Total 04 Total Total Sub-totals Totals
Sales Collateral
Expansion Initial Piece(Incl.Floorplan)
Design&Copy Development(3,000 copies) 750 0 0 750
Printing 1,200 1,200
Postage 1,100 1,100
Trade Show Piece(Incl.Floorplan& Rendering)
Design&Copy Development _ 6,000 6,000
Printing(4,000 Pieces) 7,500 7,500
Meeting Planner Sales Kit w/stand alone elements
Design&Copy Development 10,000 6,000 16,000
Printing& Production(3,500 Kits) 0 35,000 35,000
Print Overrun on Stand Alone Elements 0 9,000 9,000
Final Tradeshow Brochure w/Completed Building Graphics
Design&Copy Development 0 1,500 1,500
Printing(5,000 copies) 0 7,500 7,500
Category Subtotals: 16,550 10,000 59,000 85,550
Advertising/Direct Mail
Industry Publications
Ad Design&Development 37,000 7,500 44,500
Meetings&Conventions 6 @ 8,753 ea. 4,753 30,259 17,506 52,518
Association Meetings 6 @ $5,891 ea. 23,564 11,782 35,346
Association Management(CEO's)6X @ $8,695 ea. 34,780 17,390 52,170
Tradeshow Week Exhibit Hall Directory 2 @ $6,966 ea. 6,965 6,965 13,930
Tradeshow Week NewsMagazine 2 @ $4,350 ea 2,350 65350 0 8,700
Forum(Chicago Market)6 @ $3,632 ea. 14,528 7,264 21,792
USAE 1 Show daily at ASAE @ $9,098 95098 9,098 0 18,196
Executive Update(DC Market)6 @ $5,185 ea. 205740 10,370 31,110
Medical Meetings 4 @ $5,157 ea. 10,314 10,314 20,628
Corporate Business Periodical (Western US)-2 @
$9,971 ea. 19,942 0 19,942
Direct Mail
Expansion Promo Kick-off
Design& Production 500 0 500
Printing(4,000 Pieces) 10,250 0 10,250
Postage 55500 0 5,500
Completion Mail Promo
Production(continue design theme from kick off promo) 4,000 4,000 8,000
Postage 6,000 6,000 12,000
Category Subtotal: 53,201 210,290 91,591 355,082
Prepared by 3/5/2003 Page 2
FY 2002- FY 2003- FY 2004.05 Category
03 Total 04 Total Total Sub-totals Totals
Public Relations
Develop&Host Media Events(Trade&Local) 15,000 15,000 30,000
(Also See Pre-Opening Events Described Below)
Pre-opening Events
PSDRCVA Golf Tournament Sponsorship 2,000 2,000 0 4,000
ASAE Annual 2,500 3,000 4,000 9,500
CSAE Annual 4,000 4,000 8,000
Chicago Sports Spectacular 2,500 2,500 5,000
Cal ASAE 2003 4,000 4,000 8,000
Groundbreaking-Nov.2003 5,000 0 5,000
Topping Off-Date TBD 10,000 0 10,000
Grand Opening-TBD 0 75,000 75,000
Familiarization Tour for Sacramento 10,000 12,000 22,000
Familiarization Tour for Chicago 10,000 15,000 25,000
Familiarization Tour for DC 6,000 25,000 31,000
HOPS Dinner(Oct.2003&2004) 5,500 5,500 11,000
Meeting Manager's Event 3,200 3,200
Category Subtotals: 7,700 77,000 162,000 246,700
Tradeshows/Sales Blitzes
Tradeshow Booth Display-Design and Purchase 20,000 0 20,000
ASAE 8/03&04 2,000 2,000 - 4,000
Cal SAE(Sacramento) 12/03&04 2,000 2,000 4,000
Destination Showcase (Feb.2004) 2,000 0 2,000
IAEM 2,500 2,500 5,000
CSAE Seasonal Spectacular(Chicago) 12/03&04 2,000 2,000 4,000
Category Subtotals: 0 30,500 8,500 39,000
Website Revision
Update Current Website to include Expansion
Elements/Progress 4,000 0 4,000
Complete Redesign of website to match new
brand/theme 10,000 25,000 35,000
(Elements to include New Logo/Image, Floorplans,
online ordering of services, diagrams,etc.)
CVA Web Promotion Program 4,000 4,000 8,000
Category Subtotals: 8,000 14,000 25,000 47,000
Convention Sales Person-DC
Hire DC Sales Person/Office Share w/CVA Staff 8,334 100,008 75,006 183,348
(Salary, benefits,office,etc, beginning in 6103 thru
3105)
Category Subtotals: 8,334 100,008 75,006 183,348
Contingency/Pop-up Opportunities
Marketing/Client Opportunities/Incentives Etc. 5,000 26,500 41,000 72,500
Category Subtotals: 5,000 26,500 41,000 72,500
Grand Total: 1,029,180
Totals by Fiscal Year: 98,785 468,548 858,194
rv'rCARTHY 91a 9cc1 2902 02J12J09 09142pm P. S01
MEMO February 12, 2003
TO; Palm Springs Mayor, City Council and City Manager
RE; Increasing annual Convention Center loss to $7 million
FROM; Frank Tysen on behalf of Palm Springs Hotel Owners
• Convention Center expansion originally a good idea
When the big hotels initiated a move to increase the bed tax for the possible
expansion of the convention center we did not oppose it even though we felt that to increase
the bed tax for the small hotels fron n 10%to I 1 30,0 was not fair and appropriate. To appease
any opposition the big hotels tnanagers assured us that a feasibility study was to be done and
that they would not pursue the convention center expansion if This studv would show that it
was not a good idea.
• Expansion does not pencil out
We have analyzed this study and feel that the convention center expansion proposal
is not a positive proposal for our crty. To spend some $30 million dollars for this expansion
to increase the bcd tax by a mere $500.000 00 does not make sense. Debt service alone
would increase to $ 5,51 0,000 a year while operating loss would add another annual expense
of$1,500,000,
• Ci.ty's Solvency'Threatened
Such expansion would indood be dangerous to our city's financial health and could
ultimately lead to insolvency , It s-ems irresponsible at this point to saddle the taxpayers with
an annual deficit of some S7,000,0J0 for the convention center. 'Phis is money that would
otherwise be in our general funds which we cannot afford to spend on such a foolhardy
proposal,
• Expansion leaves no tnoney fi7r urgent priorities
Our community is currently faced with some horrendous problems that will require
major future outlays. Foremost, crime has become a very serious problem it) Ixalm Springs
being one ofthe bighest in the Coa hclla Valley. Obviously we need to spend more money
for police not incur a greater bUchnot deficit to seta few more conventioneers when we
alreadv ca.lft handle crime control :°or t.be people who now visit plus our residents. We
desperately need the money to stin;ulate infusion of"quality retail in our downtown which we
have been losing at an alarming rate. Finally due to economic conditions and fear of war
many of our hotels are now staffcring substantial oucupancy drops requiring creative solutions
which again will be difficult when There is no money left to do Anything.
• barge corporate hotel interests versus owner operated hotels
We are aware that a handftil of corporate hotel managers have been lobbying hard for
the convention center expansion ""heir corporations will marginally benefit from some
convention business increase but ti-esc corporations hardly concern themselves with saddling
our taxpayers with an unjustifiable debt' Bcsidcs ''he typical corporate hotel manager d,res
not stay long in our city. On the contrary we are hotel ovmers wllo have hrvcsted our life
savings in these hotels. We live he e and are herc for the long haul. We are all worried and
we urge you not to put all our eggs in tsne basket. Perhaps a scaled, down version is in order.
We need to explore less costly Me-native to increase tourism.