VISITORS CENTER PROJECT CONTRACT AWARD
RECOMMENDATION:
It is recommended that the City Council award a construction contract for the Visitor
Center Remodel Project; City Project#03-06.
SUMMARY:
This action will allow for a project start prior to September 1, 2003.
BACKGROUND:
The Visitors Center Remodel project is out to bid with the six(6) pre-qualified firms:
Commercial Diversified B. E. McMurray
James Simon Company 4 Con Engineering
Doug Wall Construction D. W. Johnston Construction
the bids are due at 2:00 p.m. on August 12, 2003 and the results will be brought to
City Council for award of contract on August 13, 2003.
ALLEN F. SMOOr, A. A. E.
Executive Director - Airports