HomeMy WebLinkAbout11/5/2003 - STAFF REPORTS (4) DATE: November 5,_ 2003
TO: City Council
FROM: Executive Director- Airports
SOUTHERLY AIRPORT TERMINAL ACCESS ROADWAY SECURITY
RECONFIGURATION - 300' RULE IMPLEMENTATION - CHANGE ORDER #1
RECOMMENDATION:
It is recommended that the City Council approve Change Order#1 (subject to FAA
approval), to agreement #4674 with Yeager Skanska, Inc for additional equipment
related to the Southerly Airport Terminal Access Roadway Security Reconfiguration
(AIP 3-06-0181-35, City Project 2002-20), in the amount of$432,837.01.
SUMMARY:
City Project#2002-20 is the modification to the Mid-Valley Parkway,Airport Extension
and the creation of a centralized inspection facility. This change order includes
security cameras, barrier control systems and electrical service upgrades.
BACKGROUND:
In response to the events of September 11`h,and the subsequent security regulations
mandated by the federal government,a blast analysis of the main passenger terminal
at the Airport was completed. The blast analysis, which, due to the extreme
confidentiality of the information contained in the report, was shared with the City
Council in Closed Session, identified several mitigation measures which would
improve the level of blast protection for the Airport.
In response to two specific federal security requirements, the 300 ft rule and
inspection of vehicles entering the secured area of the Airport, staff worked with the
Transportation Security Administration (TSA)and developed a centralized inspection
facility. This inspection facility and associated modifications to the Airport's loop
roadway system will allow for inspections of vehicles as they desire to approach the
main passenger terminal, as well as those vehicles who have a need to access the
secured area of the Airport.
In order for the Airport to operate the roadway system and inspection facility
efficiently, closed circuit television (CCTV) cameras will be used to monitor the safety
and security. Due to some last minute regulatory changes, additional barrier controls
are required. Additionally, the recent security improvements have exceeded the
capacity of the main electrical transformers and a 50% capacity increase is required.
YA
Southerly Airport Terminal Access Roadway - Change Order#1
October 29, 2003
Page 2
Sufficient funds are available via Airport Improvement Program (AIP) grant 36 and
available in account no. 415-6600-56060.
A Minute Order is attached for City Council consideration.
MIKE N WILLIAMS, A.A.E. 'ALLEN F SM OT, A.A.E.
Deputy Director- Operations Executive Director - Airports
APPROVE d`�—'gym
City Manager'
Attachment: Minute Order
Change Order
REVIEWED 6Y DE-PI OF FINANCE
N:\WordPerfect\City_Council\Engineering_Construction\Southerly_Access Roadway Change Order 1 10-29-2003 wpd
CHANGE ORDER NO. 1
SOUTHERLY TERMINAL ACCESS ROADWAY SECURITY RECONFIGURATION
AIP No. 3-06-0181-35
CITY PROJECT NO. 2002-20
CONTRACT NO.
CONTRACT DATE:April 2, 2003
CONTRACTOR:YEAGER SKANSKA Inc.
The following changes are hereby made to the Contract Documents:
1. Add: Closed Circuit Television system at and around Vehicular Inspection Plaza;
2. Add: Security Barrier Safety and Operating Enhancements;
3. Add: Security Barrier Gates for VIP Lot#2;
4. Add:Transformer Upgrade.
Justification:
1. The CCTV system will be integral part of the Roadway Terminal Approach Security System and Plaza
Inspection Facility in order to both monitor and record security related events;
2. The enhancements will allow the system operator greater control and saferimplementation;
3. Gate(s)installation will satisfy the TSA requirement and allow lot use;
4. Recent security project improvements have caused the main Terminal Transformers to overload;the
transformer(s)capacity will be increased 50%.
CHANGE TO CONTRACT PRICE
Original Contract Price: $7,796,239.00
Current contract price,as adjusted by previous Change Orders: $ 7,796,239.00
The Contract Price due to this Change Order will be[increased][decre"ed]by $432,837.01
The new Contract Price due to this Change Order will be: $8,229,076.01
CHANGE TO CONTRACT TRAE3-06-0181-35
The Contract Time will be[increased][deereaeed] by 15* (see Exhibit No. 1)calendar days.
The date for completion of work under the Change Order will be October 31,2003* (see Exhibit No. 1)
Approvals Required:
To be effective, this order must be approved by the Owner if it changes the scope of the objective of the project, or
as may otherwise be required under the terms of the Supplementary General Conditions of the Contract.
Requested by date
Recommended by Rodger Sheraton,VSA AIRPORTS,Inc. date October 16,2003
Ordered by date
Accepted by date
Yeager Skanska,Inc.
Approved by the FAA date
PALM SPRINGS INTERNATIONAL AIRPORT AIP 3-06-0181-36
EXHIBIT No. 1
CHANGE ORDER NO. 1
1 CCTV SYSTEM
POLE MOUNTED PULL-BOXES 8,732.85
OPTIC FIBER AND TERMINATIONS 30,093.00
CAMERAS, MONITORS, SWITCHES, MISC. 157,500.00
SUB-TOTAL 196,32,5.85
2 SECURITY BARRIER SYSTEM ENHANCEMENTS
CONTROLS-CONTROL PANEL, PLC OVDS UPGRADES 17,078.25
BARRIERS - BARRIER LIGHTS AND SWITCHES 6,384.00
CABLES -OPTIC FIBER, COAXIAL, CONTROL 21,000.00
SUB-TOTAL 44,462.25
3 SECURITY GATES FOR VIP LOT#2
ELECTRICAL FOR GATES POWER/DATA CONDUIT 5,531.40
INSTALL GATES AND OPERATORS 11,396.70
SUB-TOTAL 16,928.10
4 TRANSFORMER UPGRADE
TRANSFORMERS -2,500 KVA 73,500.00
REMOVE/DISPOSE OF EXISTING TRANSFORMERS 9,723.00
INSTALL AND HOOK-UP NEW TRANSFORMERS 91,897.81
SUB-TOTAL 175,120.81
TOTAL. CHANGE ORDER No. 1 432,837.01
Contract Time Increases:
Item 2 "Security Barrier System Enhancements"and item 3 "Security Gates for VIP Lot#2"
as a part of the original contract are increased in total by 15 Calendar Days.
Item 1 "CCTV System"and item 4'Transformer Upgrade", in terms of contract time separate
from the original contract, will commence November 17, 2003 and be completed in 33 Calendar
Days, December 19, 2003.
Conditions of the Change Order:
These changes will be implimented in accordance with the Contract Documents and revisions.
qA v
� Yeager Yeager Skanska Inc.
1995 A9ua Mansa Road
Riverside,CA 92509
�e �eP.
Phan. 9OM84-5360
SKANSKA We 909.664.1644
Web
pate Reference
October 15,2003 Southerly Terminal Access
Rodger Sheraton
VSA Airports
CIO Airport Administration
3400 E. Tahquitz Way, OFC
Palm Springs, CA 92262
Additions to Electrical/Security Systems
Gentlemen,
The following is a breakdown of the requested additions to the electrical and security
systems on the above referenced project.
CCTV SYSTEM
POLE MOUNTED PULL-BOXES $ 8,732.85
OPTIC FIBER AND TERMINATIONS $ 30,093.00
CAMERAS, MONITORS, M1SC. $ 157,500.00
SUBTOTAL $ 196,325.85
SECURITY BARRIER SYSTEM ENHANCEMENTS
CONTROLS—CONTROL PANEL,PLC OVDS UPGRADES $ 17,078.25
BARRIERS—BARRIER LIGHTS AND SWITCHES $ 6,384.00
CABLES—OPTIC FIBER, COAXIAL, CONTROL $ 21,000.00
SUBTOTAL $ 44,462.25
SECURITY GATES FOR VIP LOT#2
ELECTRICAL FOR GATES—POWER, DATA, CONDUIT $ 5,531.40
GATES AND OPERATORS $ 11,396.70
SUBTOTAL $ 16,928.10
TRANSFORMER UPGRADE
TRANSFORMERS —2,500 KVA $ 73,500.00
REMOVE AND DISPOSE OF EXISTING TRANSFORMERS $ 9,723.00
INSTALL AND HOOK UP NEW $ 91,897.81
SUBTOTAL $ 175,120.81
GRAND TOTAL $ 432,837.01
Y� 5-r
2
October 15, 2003
The above prices include all labor, equipment, and materials for the complete
installation of the items listed. This work will not be done within the timeframe of
the original project.
If you have any questions regarding this request,please contact me.
Sincerely,
Ron Skinner
Superintendent
MINUTE ORDER NO.
APPROVING CHANGE ORDER#1 (SUBJECT TO FAA APPROVAL), TO
AGREEMENT#4674 WITH YEAGER SKANSKA, INC FOR ADDITIONAL
EQUIPMENT RELATED TO THE SOUTHERLY AIRPORT TERMINAL
ACCESS ROADWAYSECURITY RECONFIGURATION(AIP 3-06-0181-35,
CITY PROJECT 2002-20), IN THE AMOUNT OF $432,837.01.
I HEREBY CERTIFY that this Minute Order approving Change Order #1
(subject to FAA approval), to agreement #4674 with Yeager Skanska, Inc
for additional equipment related to the Southerly Airport Terminal Access
Roadway Security Reconfiguration (AIP 3-06-0181-35, City Project 2002-
20), in the amount of$432,837.01, was adopted by the City Council of the
City of Palm Springs, California, in a meeting thereof held on the 29`h day of
October, 2003.