HomeMy WebLinkAbout12/17/2003 - STAFF REPORTS (22) DATE: December 17, 2003
TO: City Council
FROM: Executive Director -Airports
TURNER CONSTRUCTION AGREEMENT NO. 4577 - 2ND AMENDMENT -
CONVENTION CENTER
RECOMMENDATION:
It is recommended that City Council approve Amendment No. 2 to Agreement No.
4577 with Turner Construction Company for construction management services on
the Convention Center project.
SUMMARY:
This action would approve an update to the Construction Manager's contract to
reflect the expected four (4) month project delay.
BACKGROUND:
Turner Construction Company was selected prior to the first phase Convention
Center project to provide construction management services, both pre-construction
and during construction, for the Convention Center Phase II project. The original
contract called for preconstruction work to begin January 2003 with construction
beginning in September 2003. This contract was approved before the architect for
the project was selected. By the time that selection was completed it was obvious
that project construction would have to be delayed until December 2003. Rather
than ask for additional fees to keep their staff mobilized during this extended
preconstruction period,Turner sent a letter asking that their existing preconstruction
fee of $175,000 be spread over ten (10) months which would take them to the
projected December 2003 construction start date. The proposed contract
Amendment No. 2 reflects the ten (10) month revised preconstruction period and
adds an additional four(4) months at$17,500 per month, but does not increase the
overall contract as the monthly "construction period staff'expenses are decreased
by a like amount.
The second change to the contract is to increase the "fee" portion of the contract
(2.9% of the actual construction cost)from$580,000 to$740,304.84. This increase
reflects the City Council's action of last September 3, 2003 wherein the overall
construction budget was increased from $20 million to $25,527,753. The contract
calls for a fee adjustment based on construction cost adjustments.
The third change to the agreement is to provide for $17,900 of reimbursable
expenses over the four(4) month delay period from December 2003 through March
2004. This is the only requested increase in fees related to the delay; Turner has
agreed to absorb some $118,560 of additional staff expenses necessary to restart
and redo work related to the delay. Nothing in the current contract would require
Turner to redo work at not cost, however they realize they are part of the team and
must assume some of the responsibility for the delay.
The last change is a clarification. Currently, in the Convention Center Construction
budget we are carrying $901,205 for "General Conditions" ( i.e., testing, safety,
printing, extra supervision, etc.). The clarification is that up to $195,000 of the ��
Turner Construction Agreement No. 4577 - 2n'Amendment - Convention Center
December 17, 2003
Page 2
General Conditions' dollars may be utilized to reimburse Turner Construction for
Safety Engineer visits and additional superintendents if said additional
superintendents will expedite the project's completion.
A minute order approving Amendment No. 2 and Amendment No. 2 are attached
for City Council consideration.
y-Vv APPROVED.
ALLEN F. SMOOT, A. A. E. . - City Manager
Executive Director - Airports
Attach ment(s):1. Minute Order
2. Amendment No. 2
REVIEWED BY DEPT. OF FINANCE
AMENDMENT NO. 2
AGREEMENT NO. 4577 - CONSTRUCTION MANAGEMENT SERVICES
THIS SECOND AMENDMENT to Agreement No. 4577 for contract services, (herein
"Agreement")made and entered into on the day of ,2003,by and between
the CITY OF PALM SPRINGS, (herein "City") and TURNER CONSTRUCTION COMPANY,
(herein "Construction Manager") is hereby amended effective as
follows:
Section 1. Section 3.4 Term is hereby amended to reflect a new ending date of September 30,
2005.
Section 2. Exhibit "C" Schedule of Compensation, Phase 1I, is hereby amended to read as
follows:
"Phase II Expansion Compensation:
Terms of Compensation. The services provided raider this Agreement shall be
performed for a lurnp sum fee of Two Million One Hundred Fifty-Nine Thousand
Three Hundred Four Dollars and Eighty-Four Cents, as outlined in the General
Conditions Breakdown and the Billing Schedule of the Construction Manager's
Proposal, attached hereto. The monthly fee breakdown is as follows:
General Conditions Fee
A. Pre-Construction Expenses Staff
February 2003 $0 $17,500.00 $0
March 2003 $0 $17,500.00 $0
April 2003 $0 $17,500.00 $0
May 2003 $0 $17,500.00 $0
Jrme 2003 $0 $17,500.00 $0
July 2003 $0 $17,500.00 $0
August 2003 $0 $17,500.00 $0
September 2003 $0 $17,500.00 $0
October 2003 $0 $17,500.00 $0
November 2003 $0 $17,500.00 $0
December 2003 $4,475.00 $17,500.00 $33,650.22
January 2004 $4,475.00 $17,500.00 $33,650.22
February2004 $4,475.00 $17,500.00 $33,650.22
March2004 $4,475.00 $17,500.00 $33,650.22
-1-
B. Construction& Closeout
April 2004 $9,863.75 $54,391.66 $33,650.22
May 2004 $9,863.75 $54,391.66 $33,650.22
June 2004 $9,863.75 $54,391.66 $33,650.22
July 2004 $9,863.75 $54,391.66 $33,650.22
August 2004 $9,863.75 $54,391.66 $33,650.22
September 2004 $9,863.75 $54,391.66 $33,650.22
October 2004 $9,863.75 $54,391.66 $33,650.22
November 2004 $9,863.75 $54,391.66 $33,650.22
December 2004 $9,863.75 $54,391.66 $33,650.22
January 2005 $9,863.75 $54,391.66 $33,650.22
February 2005 $9,863.75 $54,391.66 $33,650.22
March 2005 $9,863.75 $54,391.66 $33,650.22
April 2005 $9,863.75 $54,391.66 $33,650.22
May 2005 $9,863.75 $54,391.66 $33,650.22
June 2005 $9,863.75 $54,391.66 $33,650.22
July 2005 $9,863.75 $54,191.66 $33,650.22
August 2005 $9,863.75 $54,391.66 $33,650.22
September 2005 $9,863.75 $54,391.68 $33,650.22
$215,175.00 $1,203,825.00 $740,304.84
GRAND TOTAL $2,159,304.84
Compensation for the above sums shall be billed to the City on a monthly basis as outlined above
on a hunp sum basis. The Construction Manager's General Conditions are for a Lump Sum Amount
of($1,419,000.00)dollars as outlined in Turner's General Conditions proposal dated September 18,
2002. The Construction Manager's General Conditions will be billed as a lump stun amount as
outlined in the above schedule. The fee for the Construction Manager's Services is 2.9%of the total
cost of construction except for Turner's General Conditions. The Fee has been calculated at 2.9%
of($25,527,753.00) dollars and will be billed as a lump sum amount of($33,650.22) dollars per
month. During the last month's billing the fee(but not the general conditions charge which remains
fixed)will be adjusted to reflect the actual cost of the project and the fee will either be increased or
decreased based on the actual cost of the project. As provided in Exhibit "D", the Schedule of
Performance,Construction Manager shall further provide a Status Report to the City on October 30,
2004, setting forth the Construction Manager's best estimate of the date of completion for all
Convention Center Expansion (the "Status Report"). In the event that the Status Report indicates
that construction cannot be reasonably completed by July 30, 2005, then the monthly payment
schedule above (for both General Conditions and the Management Fee) shall be adjusted for the
remaining term of the Agreement to the date that constriction will be completed. The City's Project
Administrator, upon his prior written approval may reimburse, at cost, Constriction Manager for
costs of safety engineer's visits to the site and for extra Project Superintendent time if said extra time
will help expedite the project. Total reimbursements shall not exceed $195,000.00 and said funds
shall come from the City's pre-established General Conditions Budget of$901,205.00. Costs will
be reimbursed based on attachment No. 1 hereto.
-2-
a��4 y
12/05/2003 FRI 11:06 FAX Z004/006
1z/0'si2003 10:49 FAX 760 318 3815 PSP INT'L AICFT 0009
Section 3. Duie E e, caution_ The persoia(s) executing this Anoendment on bofalf of the patties
hezato warrant that (i) such party is duly organized and existing, (ii)they are duly
authorized to execute and deliver this Amendment on behalf of said party,(i ii)by so
executing this Amendment, such party is formally bound to the provisions of this
Amendment, and (iv) the eatezing into this Amendment does not violate any
provision of any other agreement to which said party is bound.
Section 4. Ful l Force and Effect. The parties further agree that,except as specifloally provided
in fMs amendment, the terms of the agreement shall remain unchanged and in full
force and affect
IN WITNESS VvTTPREOF,the parties Hereto have ma"d these presents to be exquatedon the
day of ,2003.
"City"
ATTEST: CITY OF PALM SPRINGS, CALIFORNIA
Ey,
City Clcwk City Manager
REVIEWED AND APPROVED:
City A.ttomey
"Construction Manager°'
TURNER CONSTRUCTION COMPANY
Name:
Title:
Namo:
Ti'Cle:
-3-
;2
12/03/2003 WED 10:50 [TR/RX No 0783] [a008
ATTACHMENT #1
(To Amendment No. 2 to Agreement No. 4577)
Turner Construction Hourly Rates:
Position Hourly Rate
Superintendent $75.00
Safety Engineer $75.00
c;7,az14 to
MINUTE ORDER NO.
APPROVING AMENDMENT NO. 2 TO
AGREEMENT NO. 4577 WITH TURNER
CONSTRUCTION COMPANY RELATED TO
A FOUR (4) MONTH DELAY IN THE START
OF CONSTRUCTION OF THE
CONVENTION CENTER EXPANSION
PROJECT.
- - - - - - - - - - - - - - - - - - - -
I HEREBY CERTIFY that this Minute Order approving Amendment No. 2 to
Agreement No.4577 with Turner Construction Company related to a four(4)
month delay in the stat of construction of the Convention Center Expansion
project,was adopted by City Council of the City of Palm Springs, California
in a meeting thereof held on the 17th day of December, 2003.
PATRICIA A. SANDERS
City Clerk