HomeMy WebLinkAbout2/4/2004 - STAFF REPORTS (2) DATE: February 4, 2004 TO: City Council FROM: Director of Public Works/City Engineer APPROVE CONSTRUCTION CHANGE ORDER NO. ONE (1) TO STEINY AND COMPANY, CITY PROJECT NO. 01-14. RECOMMENDATION: That the City Council approve Construction Change Order No. One (1) to Steiny and Company, for a decrease (credit) of $27,187.20 for the Sunrise Way Traffic Signal Interconnect Project. SUMMARY: Delete the proposed 19 in. Rack-Mounted Shelf and GDI Model 900 DS Radio Transceiver, eight (8) each and attachments. BACKGROUND: On Nov. 26, 2002, City Council of the City of Palm Springs awarded Steiny and Company the contract for the Sunrise Way Traffic Signal Interconnect project. Per the recommendation of the City Staff,the 19 inch Rack-Mounted Shelf and GDI Model 90ODS Radio Transceiver and attachments were deleted from the contract. The City is going to change the proposed radio transceiver units to Encom model 510OR Rack Mounted Radio Transceiver, including all attachments to match the system that was installed at Sunrise Way and Sunny Dunes Road, The Encom radio transceivers will be purchased by the City outside of this contract, eliminating markups by the Contractor. The eight Encom units will cost a total of $19,610, including tax and freight. There is a charge by the Contractor's supplier to re-stock the radio transceiver and attachments, because the City deleted these units from the contract after the Contractor purchased these units per Plans and Specifications. In addition to the above change, eighteen (18) additional working days will be added due to SCE delays. Funds to be credited in account numbers: 133-4298-50186 ($ 7,294.05) 261-4491-50186 ($19,893.15) ZX4— DAVID J. BARAKIAN Director of Public Works/City Engineer APPROVEB:� •C��� �v j%� City Manager ATTACHMENTS: 1. Minute Order 2. Construction Change Order No. One (1) REVIEWED BY DEPT. OF FINANCE -7� CITY OF PALM SPRINGS CONTRACT CHANGE ORDER To: Stein and Company Date: January 15,2004 12907 East Garvey Ave. Project No.: C.P.01-14 Baldwin Park, CA 91706 Project Name: Sunrise Way Traffic Signal Interconnect Change Order No.:One(1)) Attn: Dave Chadbome Contract Purchase No.: 316186 Account Number(s): 133-4298-50186 2614491-50186 Agr.#4594 M.O.#7197 Res.#_ A.CHANGES IN WORK: Increase to Contract Bid Item (New): Item Description A Re-stocking fee for 19 in. Rack-Mounted Shelf and GDI Model 90ODS Radio Transceiver and attachments Decrease to Contract Bid: Item Description B Credit for 19 in. Rack-Mounted Shelf and GDI Model 90ODS Radio Transceiver and attachments B.CHANGES IN CONTRACT COST: Increase to Contract Bid Item (New): Item Description A Re-stocking fee for 19 in. Rack-Mounted Shelf and Lump Sum $ 6,796.80 GDI Model 90ODS Radio Transceiver and attachments Decrease to Contract Bid: Item Description B Credit for 19 in. Rack-Mounted Shelf and GDI Model 8 each @$4,248.00 ($ 33,984.00) 90ODS Radio Transceiver and attachments TOTAL < CREDIT > CHANGE ORDER = ($ 27,187,20) NOTE: No additional markup will be added to any items in this Contract Change Order. All cost per each item are final. C.REASON FOR CHANGE: Bid Item A: A charge by the Contractor's supplier to re-stock the 19 in. Rack-Mounted Shelf and GDI Model 90ODS Radio Transceiver and attachments, 8 each, because the City deleted these units from the contract after the Contractor purchased these units per Plans and Specifications. Bid Item B: Per the recommendation of the City Staff, deleted the 19 in. Rack-Mounted Shelf and GDI Model 90ODS Radio Transceiver and attachments from the contract.The City is going to change the proposed radio transceiver units to Encom model 5100R Rack Mounted Radio Transceiver, including all attachments to match the system that was installed at Sunrise Way @ Sunny Dunes Road. The Encom radio transceivers will be purchased by the City outside of this contract, eliminating markups by the Contractor. I January 15, 2004 City Project 01-14 Sunrise Way Traffic Signal Interconnect Change Order No. One (1) Page 2 of 2 C.REASON FOR CHANGE(continued): Extension of time due to SCE delays= 18 working days D.SOURCE OF FUNDS: 1334298-50186 ($ 7,294.05) 261-4491-50186 ($ 19,893.15) Summary of Costs Contract Time Original Contract Amount: $ 160,663.00 Original Completion Date: Aug. 12,2003 This Change Order:- ($ 27,187.20) Days Added for this C.C.O.: 18 Previous Change Order(s): $ 0.00 Previous Days Added: 0 Revised Contract Amount: $ 133,475.80 Revised Completion Date: Sept. 19,2003 1 have received a copy of this Change Order and the City Approval: above AGREED PRICES are acceptable to the J con t Submitted By Date Street Mainte�Manager By �` Approved By i Date f Tige G��( «%l%i/I��IYL Director of Public Works I City Engineer Date OSL( d Approved by Date City Manager Distribution: Original Conformed Copies Conformed-File Copy Engineering (1) Engineering File (1) Finance (1) Engineering Field Inspector (1) Contractor (1) Engineering Field Supervisor (1) City Clerk (1) Purchasing Agent (1) a63 MINUTE ORDER NO. APPROVING CONSTRUCTION CHANGE ORDER NO. ONE (1) TO STEINY AND COMPANY, FOR A DECREASE (CREDIT) OF $27,187.20 FOR THE SUNRISE WAY TRAFFIC SIGNAL INTERCONNECT PROJECT, CITY PROJECT NO. 01-14 I HEREBY CERTIFY that this Minute Order, approving Construction Change Order No. One(1)to Steiny and Company,fora decrease(credit)of$27,187.20 forthe Sunrise Way Traffic Signal Interconnect Project, City Project No. 01-14,was adopted by the City Council of the City of Palm Springs,California, in a meeting thereof held on the 4"day of February, 2004. PATRICIA A. SANDERS City Clerk