HomeMy WebLinkAbout2/18/2004 - STAFF REPORTS (13) DATE: February 18, 2004
TO: City Council
FROM: Convention Center Construction Project Administrator
ARCHITECTURAL CONTRACT AMENDMENT
RECOMMENDATION:
It is recommended thatthe City Council approve Amendment#2 to Agreement No.4615
with Fentress Bradburn Architects, Ltd., for scope changes authorized at completion of
Design Development level plans and specifications for the Convention Center
Expansion Project.
SUMMARY:
This action would amend the Agreement with the Convention Center Architect to
compensate them for Scope Changes authorized at completion of Design Development
level documents.
BACKGROUND:
From the beginning of this project the Architects were asked to fast track the design of
the Convention Center Expansion to meet a window of opportunity for demolition
(December 3`d). They were asked to complete a 14 month design process in 10 '/2
months. The mid-point of the design process is known as the Design Development
level. We reached this point in late June. At that time the design team was struggling
to hold the original design expansion square footage; to hold the aesthetic look of a
stone exterior; and to maintain the budget.
The only way to try and accomplish all of that and still maintain our demolition date of
December 2003,was to modify scope, add in alternates and increase the number of bid
schedules to allow for a greater stagger of the bidding. The project was set on a course
whereby the City would be taking early bids while design of later components continued.
There was risk that while this course of action would keep us on schedule, it could result
in higher bids due to early bidders trying to hedge their bids to cover unknowns of future
design changes.
The attached Agreement Amendment No. 2 details all of the items of scope that were
directed to be changed. The most difficult for the Architects was to split the southeast
registration area into an alternate which meant a complete redesign of the structural
steel system so that the building could stand with or without the southeast registration
area included. Another major change was for the Architects to produce five (5)
separate sets of bid schedules, instead of the three (3) contracted for, so as to
accommodate the City's desire to stagger the bid process to try and maintain schedule.
February 18, 2004
Page 2
Also, the architects were asked to develop an interior lighting design which was to
include computer modeling and rendering of the lobby spaces and to develop an
intersection redesign for Amado/Alvardo.
These changes in scope, to accommodate the City's desire to hold schedule, have a
cost breakdown as follows:
Bid Package Increase $20,340
SE Registration Alternate $66,050
Lighting Consultant $14,300
Civil Amado/Alvarado $ 8,300
Subtotal $108,990
Plus Reimbursables $10,899
Total $119,889
Attached is a Minute Order for City Council consideration. This requested action is out
of sequence as to what would normally occur if time was not an issue. Normally we
could ask the Architect to submit a cost proposal for this extra work and approve it prior
to work commencing. In this case the only way to maintain schedule was to order the
changes and catch up with the Amendment later.
The Architectural firm carried out this work in good faith and placed the priority of the
City schedule ahead of their need to seek a contract Amendment. The data submitted
for this request was received by staff on December 10, 2003 and negotiations were
completed in late January. Funding for this change will come from the Convention
Center Bond issue and these costs were included in the overall project cost estimate
presented to City Council on January 28, 2004.
Allen F. Smoot
Convention Center Construction Project Administrator
APPROVED:
City ManagerC'
Attachments:
1. Minute Order
2. Amendment No. 2
3. Backup Letter
AMENDMENT NO. 2
AGREEMENT NO. 4615 - CONVENTION CENTER DESIGN SERVICES
THIS SECOND AMENDMENT to Agreement No. 4615 for contract services, (herein
"Agreement")made and entered into on the day of 2004,by and between
the CITY OF PALM SPRINGS(herein"City")and FENTRESS BRADBURN ARCHITECT,LTD.,
(herein "Architect') is hereby amended effective , 2004, as follows:
Section 1. Exhibit"A" Scope of Services is hereby amended by adding the following Change
to Scope (direction given at completion of Design Development):
"At completion of Design Development,the City and Architect mutually agree that
the program has been modified as follows:
1) The Bid Package requirement is modified from 3 to 5;
2) The SE Registration Area is modified to be a standalone bid alternate;
3) Special design consulting for Lighting Design is added;
4) Civil design to rework the Amado/Alvarado intersection is added."
Section 2. Exhibit"C"Schedule of Compensation is hereby amended by adding fees for Design
Development Completion Scope Changes as follows:
"Design Development Completion Scope Changes additional fees (Lump Sum):
1) Bid Package Increase $20,340
2) SE Registration Alternate $66,050
3) Special Consulting (Lighting) $14,300
4) Civil - Arnado/Alvarado $ 8,300
5) Reirnbursables $10,899
Total $ 119,889
Note:The additional fees of$119,889 shall be added to the Design Development fee
of$565,000 established in Amendment#1 to this Agreement thus bringing the total
Design Development fee to $684,889; the total Lump Sum fee is hereby increased
from $2,972,083 to $3,091,982.
Section 3. "Exhibit"D" Schedule of Performance is hereby amended by adding six (6) weeks
additional time to each of the milestone dates."
Except as specifically worded herein,all terns and conditions of the Agreement shall remain in full
force and effect and performance of services under the Agreement shall be governed by the
provisions of the Agreement.
-I-
IN WITNESS WHEREOF,the parties hereto have caused these presents to be executed on the
day of 12004.
"City"
ATTEST: CITY OF PALM SPRINGS, CALIFORNIA
By:
City Clerk City Manager
REVIEWED AND APPROVED:
City AttUiw
"Architect"
FENTRESS BRADBURN ARCHITECT, LTD.
Name:
Title:
Name:
Title:
Palm Spring Convention Center Revised 01/27/04
Fee worksheet for Design Development revisions 200222.005
Item Description FBA hours Rate $/hr Fee
FBA Fee
1 Producing 5 bid packages in lieu of 3
Meetings and travel time
Mike W and John K 20 $210 $4,200
Support 20 $75 $1,500
Plotting and collating 32 95 $3,040
Coordination and out of sequence inefficiencies 40 95 $3,800
Index sheet 8 75 $600
Crosby Group $5,400
WE Engineers $1,800
Mainiero Smith $0
Michael Buccino $0
Fee Subtotal : $20,340
Expenses 10% $2,034
Fee Total ,-, $22,374
FBA Fee
2 Design southeast registration lobby as an alternate
Floor Plan drawing 90 $90 $8,100
Reflected Clg plan 30 $90 $2,700
Section Drawing 60 $90 $5,400
V _ Detail drawing 175 $90 $15,750
Consultant coordination 50 $90 $4,500
Crosby Group $8,500
M-E Engineers $5,600
Mainiero Smith $6,000
Michael Buccino $9,500
Fee Subtotal $66;050
--10 -
Expenses 10% $6,605
Fee:Total - : $72,655
FBA Fee
3 Special Design Services Lighting 70 $90 $6,300
Coordinate revisions with consultants 38 $100 $3,800
3 M-E Engineers $8,000
Fee Subtotal $18,100
Expenses10% $1,810
Fee Total $19,910
Mainiero Smith
4 Design at Amado and Alver ado intersection $4,500
Fee Subtotal - - $4,500
Expenses10% $450
Fee Total - $4,950
FEE GRAND TOTAL $119,889
MINUTE ORDER NO.
APPROVING AMENDMENT NO. 2 TO AGREEMENT NO.
4615 WITH FENTRESS BRADBURN ARCHITECT, LTD .,
TO INCORPORATE SCOPE CHANGES FOR THE
CONVENTION CENTER EXPANSION PROJECT FOLLOWING
DESIGN DEVELOPMENT COMPLETION.
I HEREBY CERTIFY that this Minute Order,approving Amendment No.2 to
Agreement No. 4615 with Fentress Bradbunl, Architect, Ltd., to incorporate
scope changes for the Convention Center Expansion Project following Design
Development completion was approved by the City Council of the City of
Palm Springs,California,in a meeting thereof held on the 18`h day of February,
2004.
PATRICIA A. SANDERS
City Clerk
1�