HomeMy WebLinkAbout3/3/2004 - STAFF REPORTS (4) DATE: March 3, 2004
TO: City Council
FROM: Director of Public Works/City Engineer
2003/2004 ANNUAL SLURRY SEAL
RECOMMENDATION:
It is recommended that the City Council consider the following two actions:
1. Award contract to American Asphalt South, Inc., in the amount of$271,056.85 for
Bid Schedule A and Bid Schedule B, for the 2003/2004 Annual Slurry Seal, City
Project 03-15; and
2. Approve Contract Change Order No. 1 fora decrease of$119,928.46,fora reduced
total contract amount of $151,128.39, for the 2003/2004 Annual Slurry Seal, City
Project 03-15.
SUMMARY:
Award of this contract will provide for installation of a slurry seal on City streets within
Section 14, and Vista Chino from Gene Autry Trail to the east city limit; approval of Contract
Change Order No. 1 will allow the project to proceed with currently budgeted funds.
BACKGROUND:
The Public Works Department oversees the maintenance of the City's street system. Each
year, the Department assembles a capital project to continue its Slurry Seal Program on
various City streets. Last year, the Department identified those streets within Sections 14
and 19, as well as Vista Chino, east of Gene Autry Trail, as those streets requiring a slurry
seal consistent with the Department's schedule of maintenance. Unfortunately, the City
was unable to award the entire contact for the scheduled streets, and due to lack of
sufficient funds, completed a slurry seal program only of those streets located within
Section 19.
This year, we intended to "catch up" on last year's slurry seal program, which includes the
streets within Section 14, as well as Vista Chino from Gene Autry Trail to the east City
limits. Unfortunately, this year's capital improvement budget of$200,000 only allowed for
the Department to move forward with slurry sealing these streets which were scheduled last
year, and not for any slurry sealing of additional streets which are due to be scheduled this
year. Previously, Council was advised that this fact represents a challenge that the
Department continues to face each year, as the budget for street maintenance and
improvement projects is limited to gas tax and Measure A revenue which is restricted and
decreasing in relation to rising costs to perform street maintenance and improvement
projects.
The specifications forthis project were prepared by City staff, and on January 21, 2004,the
City Council approved and adopted the specifications for this project, and authorized
advertisement for construction bids. The project consists of two Bid Schedules: Bid
Schedule A represents slurry seal of Vista Chino, from Gene Autry Trail to the east city
limits; and Bid Schedule B represents slurry seal of City streets within Section 14.
2003/2004 Annual Slurry Seal
March 3, 2004
Page 2
On January 27 and February 2, 2004, the project was advertised for bids, and at 2:00 P.M.
on February 10, 2004,the Department of Procurement and Contracting received bids from
the following contractors:
Contractor Bid Sch A Bid Sch B Total
American Asphalt South, Inc.; Fontana, CA $43,952.18 $227,104.67 $271,056.85
Bond Blacktop, Inc.; Union City, CA $44,281.13 $229,670.17 $273,951 30
California Pavement Maintenance Co., Inc.; $48,076.65 $251.065.46 $299,142.11
Sacramento, CA
Pavement Coatings Co.; Cypress, CA $52,884.32 $271,987.44 $324,871.76
The engineer's estimate was $40,486 for Bid Schedule A, and $166,913 for Bid Schedule
B, for a total of$207,398. The estimate was based on bid amounts from last year's slurry
seal project, however, bid prices per square foot for this year's slurry seal project increased
roughly 25%.
The issue of lacking sufficient funds to budget for annual street maintenance is proved by
the fact that costs for this year's annual slurry seal increased over last year's costs, and it
is not possible to award the entire contract with the $200,000 budget for this project. In
order to move forward and proceed with as much maintenance as possible this year, staff
is recommending that the rubberized slurry seal of the three major streets within Section
14 be deleted from the contract. These streets (Alejo Road, from Indian Canyon Drive to
Sunrise Way; Sunrise Way, from Ramon Road to Alejo Road; and Avenida Caballeros,
from Ramon Road to Alejo Road),will have to be programmed as part of next year's annual
slurry seal. This fact continues to show that this Department is falling further behind in
required annual maintenance of City streets due to a shortage of gas tax and Measure A
funds available for routine street maintenance.
As stated previously, this Department has not yet suggested supplementing its annual
budget with general fund revenue, realizing the numerous other programs and projects that
require funding solely from the general fund. However, the fact that each year we continue
to lack sufficiently budgeted funds to slurry seal an appropriate amount of City streets is
evidence of the fact that an increase in funding for street maintenance is necessary.
Further discussion at an appropriate time should occur to discuss the Department's future
abilities to fund a program to maintain the City's infrastructure limited to the use of gas tax
and Measure A revenue.
This bid award is an opportune time to bring to the Council's attention the fact that slurry
seal prices are steadily increasing, as well as overall street maintenance costs. This fact
causes the Department concern, as it is more and more difficult to keep up with a frequency
of street maintenance and slurry seal projects that is appropriate due to limitations on
budget and available funds. Historically, this Department has relied solely on gas tax and
local Measure A funds to cover all of its street maintenance costs. Unfortunately, other
projects, local matches for federal projects, and higher construction costs are severely
limiting the ability to spread those funds appropriately across the City for street
maintenance purposes. It is generally recommended that streets in good condition be
slurry sealed every 5-7 years to keep the streets in good condition, however, we have only
been able to budget with available gas tax and Measure A funds a slurry seal of city street
on an interval of approximately 9-10 years. This lends to further deterioration, and
ultimately, more expensive maintenance repairs, such as overlays and reconstruction.
2003/2004 Annual Slurry Seal
March 3, 2004
Page 2
With this in mind, it is not possible to award the entire contract amount. The Department
included as Bid Schedule A, a slurry seal of Vista Chino, at previous Council direction. This
street was excluded from the award of last year's slurry seal in order to fund last year's
slurry seal project. Staff recommends that Bid Schedule A, a rubberized slurry seal of Vista
Chino (which has been delayed two years), as well as Bid Schedule B, slurrying of City
streets within Section 14, be awarded at this time, with a concurrent approval of Contract
Change Order No. 1 to delete the three major streets within Section 14, postponing their
maintenance until next year's budgeted slurry seal project.
Staff has coordinated with staff from the Agua Caliente Band of Cahuilla Indians to
determine impacts to any events scheduled in or around the Tribal Casino or Spa Hotel.
The scheduling of the slurry seal project will not coincide or impact any known events, and
staff will continue to cooperate closely with Tribal staff to avoid any street closures in the
event future events are scheduled.
The basis of award was the total sum of Bid Schedules A and B. The low bidder is
American Asphalt South, Inc., from Fontana, California. The company is a California
corporation and its officers are: Allan Henderson, President; Lyle Stone, Secretary; Jeff
Petty, Vice-President; and Steve Aguirre, Treasurer. Upon approval of Contract Change
Order No. 1, sufficient funds will be available in account 134-4498-50100 (Slurry Seal
Program).
SUBMITTED: fv'
DAVID J. BARAKIAN
Director of Public Works, City Engineer
APPROVED
DAVID H. READY
City Manager
ATTACHMENTS:
1. Minute Order (2)
2. Contract Change Order No. 1
4EVIEWED BYDEPT. OF FINaAI'lrF
VA 3
CITY OF PALM SPRINGS
CONTRACT CHANGEORDER
To: American Asphalt South, Inc. Date: March 3, 2004
74855 Joni Drive, Suite 5 Project No.: 03-15
Palm Desert, CA 92260 Project: 2003/2004 Annual Slurry Seal
Change Order No.: One (1)
Attn: Jeff Petty, Vice President Contract Purchase No: Pending
Account Numbers: Pending
Agr.# Pending
M.O.# Pending Res. #
A. CHANGES IN WORK:
Decrease to Contract Quantities:
Bid Schedule B
Item Description
2 Construction of Rubberized Emulstion-Aggregate Slurry Seal, REAS (or FLEX SEAL), including
mobilization, traffic control, removal and replacement of reflectorized raised pavement markers
and pavement markings, and all appurtenant work on Alejo Road, from Indian Canyon Drive to
Sunrise Way; and on Sunrise Way from Ramon Road to Alejo Road; (and Avenida Caballeros
from Ramon Road to Alejo Road, included in the quantity but not listed in the bid item).
Increase to Contract Quantities:
None.
B. CHANGES IN COST:
Decrease to Contract Quantities:
Bid Schedule B
Item Description Quantity Unit Unit Price Amount
2 Construction of Rubberized Emulstion- 889,677 SF $0.1348 $119,928.46
Aggregate Slurry Seal, REAS (or FLEX
SEAL), including mobilization, traffic
control, removal and replacement of
reflectorized raised pavement markers
and pavement markings, and all
appurtenant work on Alejo Road, from
Indian Canyon Drive to Sunrise Way; and
on Sunrise Way from Ramon Road to
Alejo Road; (and Avenida Caballeros from
Ramon Road to Alejo Road, included in
the quantity but not listed in the bid
item).
TOTAL DECREASE TO CONTRACT QUANTITIES: ($119,928.46)
114 V
Increase to Contract Quantities:
None.
TOTAL INCREASE TO CONTRACT QUANTITIES: $0.00
TOTAL NET CHANGE ORDER AMOUNT: ($119,928.46)
NOTE: No additional markup will be added to any items in this Contract Change Order. All costs per
each item are final.
C. REASONS FOR CHANGES:
Decreased Items:
The 2003/2004 Fiscal Budget appropriated $200,000 for the annual slurry seal project. The lowest,
responsive, responsible bid price for the programmed slurry seal project is $271,056.85, $71,056.85
above the budgeted funds for this project. Maintenance of the three arterial streets (Alejo Road, Sunrise
Way, and Avenida Caballeros) within Section 14 will have to be postponed until the next fiscal year
when it can be budgeted as part of the next annual slurry seal project.
D. SOURCE OF FUNDS:
Funds are available in the following account:
Account No.: 134-4498-50100 (Slurry Seal Program)
Summary of Costs Contract Time
Original Contract Amount: $271,056.85 Original Completion Date: To be determined
This Change Order: ($119,928.46) Days Added for this C.C.O.: - 0 -
Previous Change Order(s): $0.00 Previous Days Added: - 0 -
Revised Contract Amount: $151,128.39 Revised Completion Date: To be determined
I have received a copy of this Change Order and City Approval:
the above totals are acceptable to the
contractor.
Submitted by Date
Street Maintenance Manager
By
Approved by Date
Director of Public Works/City Engineer
Title
Approved by Date
Date City Manager
Distribution:
Original Conformed Copies Conformed-File Copy
Engineering (1) Engineering File (1) S
Finance (1) Public Works Inspector (1)
Contractor (1) Engineering Field Supervisor (1)
City Clerk (1) Purchasing Agent (1)
Proof of Publication
In Newspaper
STATE OF CALIFORNIA
County of Riverside
Jacquelin K. Welch Says:
1. 1 am a citizen of the United States, a CITY OF PALM SPRINGS
resident of the City of Desert HotNOTICE INVITING BIDS
Springs, County of Riverside, State of For constructing 2003/2004 Annual Slurry Seal
City Project 03-15
California, and over the age of 18 years. N-, NOTICE IS HEREBY GIVEN that sealed bids for the
2. I am the Research & Production 2003/2004 Annual Slurry Seal will be received at the office of
Assistant of The Public Record, a the Director of Procurement and Contracting of the Pity of Palm
Springs,California;until 2:00 PM. on February 17,2004, at
newspaper of general circulation printed which lime they will be opened and read aloud.
and published in the City of Palm N-2 DESCRIPTION OF THE WORK:The Work comprises
the application of rubberized emulsion-aggragale slurry seal
Springs, County of Riverside, State of (REAS)or FLEX SEAL;and construction of Type ll Slurry Seal
on various City streets In Sections 7 and 14(as listed in the
California. Said The Public Record ($ a Appendix);traffic striping;and all appurtenant work.
newspaper of general circulation as that N-3 AWARD OF CONTRACT:reserves right after opening bids to
term is defined in Government Code reject any or all bids,to waive any Informality(non-responsive-
seetion 6000, its status as such having ness) In a bid, or to make award to the lowest responsive,
responsible bidder on the basis of the total sum of Bid
been established by judicial decree of the Schedules A and B and reject all other bids,as it may best
Superior Court of the State of California in serve the interest of [he City Bidders shall bid on all Bid
Schedules
and for the County of Riverside In (b) As a condition of award,the successful bidder will
be required to submit payment and performance bonds and
Proceeding No. Indio 49271 , dated insurance
March 31 1987 entered in Judgment N-4 BID SECURITY:each bid shall be accompanied by a
i can(,ad or cashier's check or Bid Sell the amount of 10 per-
Book No. 129, page 355, on March 31 , cent of the total bid price of the total sum of Bid Schedules A
and B payable to the City of Palm Springs.
1987. N-5 BIDS TO REMAIN OPEN:The Bidder shall guarantee
3. The Public Record is a newspaper of the Total Bid Price for a period of 60 calendar days tram the
data of bid opening.
general circulation ascertained and N-6 CONTRACTOR'S LICENSE CLASSIFICATION: The
established in the Cityof Palm Springs in Contractor shall possess a valid Class"A"OR"012"OR"C-
32"Contractor license at the time of submitting bids
the County of Riverside, State Of N-7 CALIFORNIA WAGE PATE REQUIREMENTS: The
California, Case No. RIC 358286, Filed Contractorshall pay the general prevailing rate of per diem
wages as determined by the Director of the Department of
June 8, ZOOi. Industrial Relations of the State of California for the locality
where the work Is to be performed.A copy of said wage rates
4. The notice, of which the annexed is a is on file of the office of the City Engineer, The Contractor and
true printed copy, was published in the any subcontractors shall pay not less than said specified rates
and shall post a copy of said wage rates at the project site.
newspaper on the following publication N-8 RETAINAGE FROM PAYMENTS:The Contractor may
_ decLIo receive too percent-oPpaymems-due under the
dates to wit: Contract Documents from time to time,without retention of any—
portion of the payment by the City,by depositing securities of
equivalent value with the City in accordance with the provisions `A o
January 27, 2004 of Section 22300 of the Public Contract Code.
N-9 OBTAINING OR INSPECTING CONTRACT
February 3, 2004 DOCUMENTS:
I certify under penalty of perjury that the cuments may be inspected without
charge(at the office ofa) Contract othe City Engineer,3200 East Tahmuftz
above is true and correct. Canyon Way,Palm Springs,CA 92262
Dated at Palm Springs, California, (b)Complete sets of said Contract Documents may be
purchased at$25 00 per set and are obtainable from the office
this 3HD day of February 2004. of the City Engineer,3200 East Tahquilz Canyon Way, Palm
Springs,CA 92262. No refund will be made of any charges for
vvGHL..�� sets of Contract Documents.
(c)An additional fee of$20 00 will be charged for sets of
documents sent by mail
N-10 ADDRESS AND MARKING OF BIDS:The envelope
47 enclosing the Bid shall be sealed and addressed to the City of
Palm Springs,and shall be delivered or mailed to the Director
of Procurement and Contracting of 3200 East Tahquilz Canyon
Way,Palm Springs,CA 92262 The envelope shall be plainly
Jacquelin K. Welch marked in the upper left hand corner with the name and
Research & Production roduction Assistant address of the Bidder and shall bear the words"Bid For.:'fol-
lowed by the[life of the Project and the date and hour of open-
,'r, ing Bids.The certified or cashier's check or Bid Bond shall be
enclosed In the same envelope with the Bid.
BY ORDER OF THE CITY OF PALM SPRINGS
Date January 22,2004 David Succeed,PE
7 Director of Public Works/City Engineer
January 27,February 3,2004
MINUTE ORDER NO.
AWARDING CONTRACT TO AMERICAN ASPHALT
SOUTH, INC., IN THE AMOUNT OF $271,056.85 FOR BID
SCHEDULE A AND BID SCHEDULE B, FOR THE
2003/2004 ANNUAL SLURRY SEAL,CITY PROJECT 03-15
I HEREBY CERTIFY that this Minute Order, awarding contract to American Asphalt South, Inc.,
in the amount of$271,056.85 for Bid Schedule A and Bid Schedule B, for the 2003/2004 Annual
Slurry Seal, City Project 03-15, was adopted by the City Council of the City of Palm Springs,
California, in a meeting thereof held on the 3ftl day of March, 2004.
PATRICIA A. SANDERS
City Clerk
q 5
MINUTE ORDER NO.
APPROVING CONTRACT CHANGE ORDER NO. 1 FORA
DECREASE OF $119,928.46, FOR A REDUCED TOTAL
CONTRACT AMOUNT OF $151,128.39, FOR THE
2003/2004 ANNUAL SLURRY SEAL,CITY PROJECT 03-15
I HEREBY CERTIFY that this Minute Order, approving Contract Change Order No. 1 for a
decrease of$119,928.46, for a reduced total contract amount of$151,128.39, for the 2003/2004
Annual Slurry Seal, City Project 03-15, was adopted by the City Council of the City of Palm
Springs, California, in a meeting thereof held on the 3`d day of March, 2004.
PATRICIA A. SANDERS
City Clerk