DATE: May 7, 2008 CONSENT CALENDAR
SUBJECT: APPROVAL OF PLANS, SPECIFICATIONS AND ESTIMATE (PS&E)
AND AUTHORIZATION TO BID THE DOWNTOWN TRASH
ENCLOSURE REDESIGN AND DOWNTOWN ALLEYWAY
ENHANCEMENTS, CITY PROJECT NOS. 02-08 AND 03-08.
FROM: David H. Ready, Executive Director
BY: Community & Economic Development Department
SUMMARY:
The Downtown Trash Enclosure Redesign and Alleyway Enhancements, City Project
Nos. 02-08 and 03-08, is a project being undertaken by the Agency to address concerns
with the cleanliness, functionality and appearance of the trash enclosure and
surrounding area. The construction documents (Plans, Specifications and Estimate) are
being completed and, in accordance with 7.03.040 of the Procurement and Contracting
Code the Council is required to approve and adopt plans, specifications and working
details, and authorize the bid request for all public projects in excess of $100,000.
Approval of this project will allow staff to proceed with these public projects, with an
estimated cost of approximately $310,000.
RECOMMENDATION:
1. Approve the plans specifications and working details for the downtown trash
enclosure redesign and alleyway enhancements, City Projects 02 08 and 03-08,
and authorize staff to advertise and solicit bids.
STAFF ANALYSIS:
The Downtown Trash Enclosure Redesign and Alleyway Enhancements, City Project
Nos. 02-08 and 03-08, is a project being undertaken by the Agency to address concerns
with the cleanliness, functionality and appearance of the trash enclosure and
surrounding area. As part of the improvement to the area, the Agency has undertaken
the redesign of the enclosure as well as improving thelar ee/�Ile�lnay
Community Redevelopment Agency Staff Report
May 7, 2008-Page 3
Downtown Trash Enclosure and Alleyway Improvements
-
FISCAL IMPACT:
The total project cost is expected to be $310,000 and funding is available through
Community Redevelopment Agency funds, in account 81 1-81 91-651 99.
"�'W,6vv� !i
HN S. RA OND DI NASHAY
irector f C unity & Economic Development Redevelopment Coordinator
4i�AS J. r S N DAVID H. READY
Assistant City Manager— Development Services Executive Director
Attachments:
1. Resolution No.
2. Plans, Specifications & Estimates
Qo�� �Gti
Community Redevelopment Agency Staff Report
May 7,2008-Page 2
Downtown Trash Enclosure and Alleyway Improvements
between Pomme Frite and The Chop House, as it is a major entry to the downtown_
The enclosure is located on City-owned property but a portion of the beautification area
will be undertaken on private property.
On November 7, 2007, the Community Redevelopment Agency approved an agreement
with DMC Design Group, Inc. a professional engineering and surveying consultant, for
survey and design services for the redesign of the downtown trash enclosure, and also
approved an agreement with David Volz Design (DVD), a landscape architectural firm
for the design of enhancements to the downtown alleyway between the multi-level
parking structure and Palm Canyon Drive.
The consultants (DMC and DVD) prepared conceptual designs that were presented to
those downtown businesses that will be the ultimate users of the trash enclosure facility
or will most benefit from the alleyway beautification. These businesses played an active
part in the process helping to guide the final design of these improvements. In addition,
the project was presented to the Architectural Advisory Committee (AAC) on February
25, 2008 and again for restudy on March 10. On March 10, after the consultants
revised their plans and incorporated many of the recommendations of the AAC, AAC
gave their full approval and support to the redesigned trash enclosure and
recommended that the downtown alleyway beautification project be carried out at a later
date as part of a larger overall downtown master plan that may include wayfinder
signage and other features to enhance the downtown experience. At the present time,
there is no such comprehensive downtown master plan in place and Staff have not
been directed by Council to carry out such a plan. The project was reviewed by
Planning staff and the design of both the enclosure and the alleyway beautification
improvements were approved.
Section 7.03.040 of the Procurement and Contracting Code requires for public projects
in excess of $100,000 Council approve and adopt the plans, specifications and working
details, and authorize staff to advertise for construction bids. The Engineer's and
Landscape Architects Estimate for this project is approximately $310,000. Approval of
the recommended action will allow staff to proceed with bidding of this project, with a
tentative bid opening date of May 12, 2008 and an award date of May 28, 2008.
It is the intent that the construction of these improvements will be completed over the
summer, when business is slower and some of the most impacted businesses will be
closed or doing their own renovations.
Plans and Specifications are available for viewing at the offices of the Director of
Community and Economic Development Department, contact Diana Shay,
Redevelopment Coordinator at 323-8260.
060003
CITY OF PALM SPRINGS, CA
DMC Design Group,Inc.
'I F 140 N.Maple St.,Slc_ DEPT. OF COMMUNITY AND ECONOMIC
P'ESIGtJ'GRL7UP-':' 104 Corona,CA 92880
DEVELOPMENT
DOWNTOWN TRASH ENCLOSURE
IMPROVEMENTS
90% ENGINEER'S ESTIMATE CALCULATIONS SHEET
Designer: Joshua D.Casper,P.1:. Date: 17-Apr-08
Checked: David M.Casper,P-E. Date: 17-Apr-08
Bid Item I Quunlity Unit Unit Cost I Item Cast
Bid Item No I -Clearing,Grubbing,mid Removal 1 LS $5,000 00 S5,000.00
Bid Item No 2-Construct Masonry Block Wall W/Pre-Fabricated Decorative Stec]Panels(Exterior) I LS $40,000 00 340,000 00
Bid Item No 3-Construct Mm onry Block Wall(Interior) 2000 LF S100 00 $2,000 00
Bid Itum No 4-Construct 6"PCC Concrete Over 6"Compacted Subgrade 300 00 $F $25 00 S7,500 00
Bid Item No 5-Construct 8"Reinforced PCC Concrete Over 6"Compacted Subgrade 600.00 SF $30 00 S13,000.00
Bid Irem No.6-Install Heavy Duty Floor Dmin mid Hinged Lockin.,,Traffic Rated Grate 2.00 EA $1,000,00 $2,000 00
Bid Item No.7-Install 3"Schedule 40 PVC Dram Pipe 5000 LF 12000 $1,000 00
Bid Item No.8-Install Terminal Cleanout 1 00 EA S50 00 $50.00
Bid Item No 9-Install Trash Compactor Steel Wheel Track 100 00 LF $25 00 12,500.00
Bid Item No 10-install Electric Tanklcss Water Hearer-Complete and Operational 1 00 LS $2,500.00 $2.500 00
Bid Item Nn 11 -Install 10'-0"Wide x I F-10"High Electric Roll Up Metal Door-Complete and Operational 2 00 RA $7,500 00 $15,000 00
Bid Item No.12-Install 5'-4"Wide x 7'-10"High Electric Ralf Up Metal Door-Complete and Operational 1,00 EA $4,000 00 $4,000 00
Bid Item No 13-Rc-Install Steel Swing Gate 1 00 FA S500 00 S500 00
Bid Item No 14-Water Improvements-Complete mid Operational 1 LS S2,500 00 $2,500 00
Bid Item No. 15-Elecuie/Lightmg Improvements-Complete and Operational 1 LS 110,000.00 $10,000 00
Suh-Total S112,550.00
10%Contingency $17,2,55.00
O
O Construction Toted S123,505.00
O
O
O
ju:JJ. �LILaLLI
La wdscapE fFrchit8c�.awd Varl2 pLawwers
PRELIMINARY ESTIMATE
Date: April 23, 2008
Project: Downtown Alleyway Beautification, City of Palm Springs
Estimated By: JB
BASE BID:
Item No. Item Description I Quantity Unit I Unit Price I Total
1 Mobilization (Not to exceed 5% of total 1 LS S 6,717.68 $ 6,717.68
bid)
2 Demolition- remove existing concrete 3,650 SF S 300 S 10,950.00
and interlocking pavers
3 Demolition- remove existing planter 2 EA $ 300.00 $ 600.00
curb (11 LF) and Ficus plants
4 Demolition-remove existing steel 2 EA $ 200.00 $ 400.00
bollards
5 Structural Calculations for Ornamental 1 LS $ 2,00000 $ 2,000.00
Wall
5 Fine Grading 3,520 SF $ 0.25 $ 880.00
6 5"Thick Concrete Paving, Integral 907 SF $ 1200. $ 10,884.00
Color
7 8"Thick Concrete Paving, Integral 988 SF $ 19.20 $ 18,969.60
Color
8 5"Thick, 27"wide Concrete Band, 94 SF $ 14.00 $ 1,316.00
Integral Color
9 6"Thick, 22"wide Concrete Band, 110 SF $ 14.00 $ 1,540.00
Integral Color
9 8"Thick, 27"wide Concrete Band, 88 SF S 14.00 $ 1,232.00
Integral Color
10 5'Thick, 12"wide Concrete Band, 12 SF `s 14,00 $ 168.00
Integral Color
11 5"Thick, 9"wide Concrete Band, 7 SF $ 14.00 $ 98.00
Integral Color
12 6 CM Thick, Interlocking Concrete 123 SF $ 16.00 $ 1,968.00
Paver on Concrete Base
13 8 CM Thick, Interlocking Concrete 1,249 SF $ 18.00 S 22,482,00
Paver on Concrete Base
14 10" Diameter Steel Pipe Bollards 7 EA $ 500.00 $ 3,500.00
15 TF6022 Lighted BGllard from Wausau 11 EA $ 1,8D0.00 $ 19,800,00
Tile, (12" x 50")
Light, Wall Mounted. Pendant Bell.
16 UCS model from Architectural Area 4 EA $ 1,400,00 $ 5,600,00
Lighting
17 Steel U Channel, 4"x 1.5" (C4 x 5.4), 52 LF $ 8.00 $ 416.00
Painted
Item No. Item Description Quantity Unit Unit Price Total
17 LED Light Strip. Up Light behind 1 EA $ 0.00 $ 0.00
Ornamental Wall.
18 Misc. electrical hardware, conduit, and 1 LS $ 7,600.00 $ 7,500.00
pull boxes
18 Ornamental Metal Wall 1 LS Is 38,000.00 S 38,000.00
SUB-TOTAL nu
15% Contingency
Total Estimated Construction Cost
000036