HomeMy WebLinkAbout7/16/2008 - STAFF REPORTS - 2.J. �pPLM Sp?
iy
ti c+
U N
CITY COUNCIL STAFF REPORT
DATE: July 16, 2008 CONSENT CALENDAR
SUBJECT: CHANGE ORDER NO. 2 TO AGREEMENT NO. 5616 WITH G & M
CONSTRUCTION FOR AN ADDITIONAL AMOUNT OF $47,440, FOR A
TOTAL CONTRACT PRICE OF $1,683,290.
FROM: David H. Ready
City Manager
BY: Department of Aviation
SUMMARY
This action approves a change order initiated by the Airport to accommodate mandatory
security and functional modifications to the US Customs facility.
RECOMMENDATION.-
Receive and file the report of aviation emergency procurement pursuant to Palm
Springs Municipal Code Sect 7.04.040(3).
STAFF ANALYSIS:
The City Council has approved a CFC (Customer Facility Charge) to fund the expansion
of the car rental lot. This expansion is an important project designed to improve the
customer services of the car rental concessions, which in-turn are a key contributor to
the success of the tourism industry. Due to the limited available space on the north side
of the main terminal, this project unfortunately could not be accomplished without
consuming some of the aircraft parking space used by US Customs services. This
action addresses the costs associated with actions taken to preserve the integrity of US
Custom's security measures, allow the operation to remain functional, and allow the car
rental expansion project to proceed and not incur delay issues.
Title 7 of the Palm Springs Municipal Code, section 7.04.040 (3) allows the director of
aviation to make emergency procurement of construction items, regardless of the
amount, to address immediate safety or security items. During the course of this
Item 2.J .
City Council Staff Report
July 16, 2008 - Page 2
G &M Agreement No. 5616—Change Order No. 2
project, such actions were taken to address circumstances which compromised the
security requirements of the US Customs, and if not corrected, would result in Customs
shutting down. Under the direction of the Airport staff and a contracted architect, the
contractor was directed to resolve the conditions and undertake the necessary
modifications under time and materials totaling $40,940. An additional $6,500 of costs
was incurred using this same contractor to expeditiously address an unsafe condition
within the terminal complex project.
FISCAL IMPACT:
The funds to support this Change Order No. 2 of $47,440; and are available in Airport
Customer Facility Charge (CFC) account 405-6003-56093 ($40,940) and account 415-
6500-56101 ($6,500), Terminal Complex Rehabilitation.
4na4-�'-
Thomas Nolan, Executive Director- Airport
5
David H. Ready, City ger
Attachments:
1. A5616, Change Order No. 2
0 0 0 0 C
Cl7fY OF PALM SPRINGS
AIRPORT RENTAL CAR READY/RETURN LOT EXPANSION
CONSTRUCTION CHANGE ORDER
To: 6&M Construction Date: July 9,2008
211 West Mesquite Avenue Project No. CP 2007-03
Palm Springs,CA 92264 Project Name: Airport Ready/Retum Lot Exp.
Change Order No.02
Contract Purchase No.0000778
Attn: George Marantz,President Account No.405-600356093 $40,940.00
and 416-6500-56101 $6.500.00
Description of Chance: This change order confirms the additional scope of work to the contract and the associated costs.
(See attached proposal for additional scope of work description and unit cost breakout):
AUTHORIZATION FOR CHANGE:
Sum tt1 I of Cosaime
Original Contract Price $ 1,587,000.00
Total of all Previous Change Orders $ 48,UU01
Total of this Change Order $ 47,440.06
Total Contract Price $ 1,683,290.00
This Change Of OIraereaseS)(deweases) (unchanged)the contract time by 0 w ing days.
Ahwetno g Order Aviation bepartm tal:Reviewed fay Date
bepu Director of Aviation
Approved by: bate:
Date. Executiv-dblrector of Aviation
City Approval:
Date:
City Clerk
Date:
City Manager
Distribution.,
ri inat Conformed Copies
City Clerk (1)
Contractor (1)
WON
Subsidiary of lfappy Traveler
211 West Mesquite Avenue
Fc&ID 495-24 1 70 3 2 Palm Springs, California 92264 MQ#A-272619
(760) 322-6918
Fax(760)778-6708
General Engineering - Grading Pipeline • Hazardous Waste Asbestos Demolition
June 16, 2008
Craig Toms
Assistant Director of Aviation
Palm Springs lntemationalAirport
3400 E. Tahquitz Canyon Way
Palm Springs, CA 92262
Regarding: Arrival Area Remodel for U.S. Customs @ the Palm Springs
International Airport
Invoice#: 061608
The follgwing is a delineation of the costs to remodel and rehabilitate the Signature
Air facility, at the southeast area of the building, for the use of the U.S. Customs
Border Protection Department of Homeland Security.
Project Percentage Amount
Completed
1 Demo & Removal of interior 100% $ 8,000.00
2. Relocate Phone &Water
Fountain 100% $ 1,000.00
3. Counter top &work station 100% $ 12,500.00
4. Frame & drywall bulkheads 100% $ 2,750.00
5. Construction of new wall
including drywall 100% $ 8,50f0.00
6. Install drop ceiling <$4,750.00>
Drywall ceiling only 100% $ 1,500.00
7. 'Realign sprinkler system <$1,250.00>
Adjust sprinkler system only 100% $ 500.00
8. New electrical & data wiring 100% $` 1,500.00
9. Exits lights &fixtures 100% $ 600.00
10. New carpet 100% $ 1,800.00
11. Remove existing automatic
door 100°% $ 1,200.00
12. Paint remodeled area 100% $ 3,250.00
13. Install door hardware By 06/23/08 $ 1,750.00
14. Encapsulate ACM NC
Total 94.0
D000
Arrival Area Remodel for U.S. Customs
@ the Palm Springs International Airport
Additional Items Required by Local and San Diego U.S. Customs and/or
Unanticipated Additions to the Contract
1. Extruded steel mesh for ceiling...............................................
Material-24 sheets @ $601sheet............................................$ 1,440A0
Labor to out&hang metal Ceiling...........................................$ 2,500.00
Insulate entire ceiling.............................................................$ 1,100.00
2. Weld all joints on steel panels including screw heads...........$ 850.00
3. Supply&weld bracket on support beam ...............................$ 750.00
4. Jack-hammer& remove concrete support walls encasing
steel I-beams (not anticipated on plans)................................$ 1,650.00
5.. Frame, drywall, &texture panel in middle of room.................$ 1,250.00
6. Install footings& support post, concrete, &bracket............,.$ 2,250.09
7. Drywall &encase beam & paint............. $ 500A0
8. Install 5 junction boxes under the counter, saw out&
removetwice..........................................................................$ 1,260.00
9. Remove floor tiles, scrape floor&floor stone floor prior to
laying carpet..................... .............$ 850.00
........................................
10. Miscellaneous paint touch up-ceiling panels & repair
light fixtures in existing U.S. Customs............................... $ 400.0'0
11. Communication Wiring...........................................................$ 1,800.00
12. Installation of communication wiring.........................a............$ 750.00
13. Labor to install wiring for automatic door& control units.........$ 1,000.00
14. Connect & install phones to main console panel, wiring
door control, computers, lights &AC in counter.....................$ 250.00
15. Baggage exam counter& computer desk (over &above hid
)$ 2,ODD.DQ
16. Stainless steel for baggage exam counter(over& above bid)$ 3,800.00
V. Transport baggage counter top to &from stainless steel
manufacture.................... ....................$ 80.09
18. Electric locks on exit door.,............ ...-............................ 1,265.00
19. Automatic separation door........................... . $ 7,668,00
20. Water extraction due to broken water fountain .. ...................$ 2,185.00
(Originally$4,186, $2,000 discount given)
Arrival Area Remodel for U.S. Customs
(7 the Palm Springs International Airport
21. G & M Construction personnel assistance with water vacs
3 men-3 hrs each @ $40.00/hr..............................................$ 3E0.00
22. New water fountain..................--..............._.........................$ 660.00
23. Labor to install&warrant new water fountain........................$ 75.00
24. Tinted windows with protective coating..................................$ 1,052.00
25. Two motion sensors & one keypad for auto doors.................$ 1.443.00
TOM ...............................................................................................$ 39,078.00
15% Office, Overhead & Management.............................................$--5 862-00
Total for Additional Unanticipated Projects....................................$ 44,940.00
Change Order#1 Deduct - 4,000,00
Total for Additional Change Order#2 $40,940.00
I
OHM
SubMdiwy of Happy Traveler
211 West Mesquite Avenue
rea.1a 095-2 u7032 Palm Springs, California 92264 Lie.#A-272619
(760) 322-6918
Fax(760)778-6708
General Engineering Grading • Pipeline • Hazardous Waste Asbestos Demolition
INVOICE TO THE CITY OF PALM SPRINGS
Payment Request# 1 Project: Main Terminal Sidewalk
Period Beginning: 05/12/08 Period Ending: 05/15/Da
Company: G & M Construction
Address: 211 W. Mesquite Avenue
Palm Springs, CA 92264
Phpne/Fax: 760.322-6918 Fax: 760-77"708
Taxpayer ID#: 96-2417.032 Date: 66121/08
STATEMENT OF CONTRACT AMOUNT
1. Original Contract Amount: 6 500,00
2. Net Authorized Change Orders:
(as per attached breakdown) oo-
3. Adjusted Contracted Amount (1 & 2): $ 6,600.09
4. Value of work completed this period $ 6 500.00
(as per attached breakdown)
S. Value of Authorized Change Orders: $ -0-
(as per attached breakdown)
6. Value of Work Completed Previously $ 0�
7. Total (4, 5, & 6): $ 6,500.00
8. Less Retention: (10%) -0_
9. . Total less retention- $ 6500.00
10: Less Funds Received (deduct): $
11. AMOUNT-OF THIS REQUEST: $ 6,500.00
6060C 7
® Subsidiary of Happy Traveler
211 West MesquiteAvenne
Fed W 095-2417032 Palm Spriztgs, California 92264 Lia SA-272619
(760) 322-6918
Fax(760)778-6708
General Engineering • Grading • Pipeline • Hazardous Waste Asbestos Demolition
May 21, 2008
Craig Toms
Assistant Director of Aviation
Palm Springs International Airport
3400 E. Tahquitz Canyon Way
Palm Springs, CA 92262
Regarding: Main Terminal Sidewalk
Invoice#: 052108-B
Main Termini I Additional sidewalk
1. Cut, remove, and dispose of grass........................................$ 2,500.00
2. Regrade area.........................................................................$ 700.00
3. 600 sq. ft. of concrete @ $5.501sq. ft.....................................$ 3,300-00
Total ................................. .....................5 f.5.0�0,OD
r
0 a 0 C