Loading...
HomeMy WebLinkAbout11/3/2004 - STAFF REPORTS (5) DATE: November 3, 2004 TO: City Council FROM: Director of Public Works/City Engineer APPROVE CONSTRUCTION CHANGE ORDER NO. TWO (2) TO CONTRERAS CONSTRUCTION COMPANY, CITY PROJECT NO. 02-27 RECOMMENDATION: It is recommended that the City Council approve Construction Change Order No. Two (2) to Contreras Construction Company, for an increase of $28,412.00 to City Project No. 02-27 (Convention Center Parking Lot). SUMMARY: At the request of Convention Center Renovation representatives funds allotted for this project will be utilized to construct street improvements on Avenida Caballeros and Amado Rd. In addition, this Change Order provides for the construction of additional curb walkway and sidewalk, and creates a new bid item required to compensate the Contractor for required spandrel work. BACKGROUND: On March 31, 2004, City Council awarded Contreras Construction Co., the contract for City Project No. 02-27, (Convention Center Parking Lot). This project is being constructed concurrently with the Convention Center renovations, and is being inspected and administered by the department of Public Works/Engineering. Construction on the project began on June 14th, and was originally scheduled to be completed on September 81". Work on the project was deferred beginning on August 2Id due to a lack of electrical service, and work is currently scheduled to resume on November 81h. Change Order No. One (1) provides the details for this deferment of work. A portion of this project was funded using Measure "A" funds, which are allotted for street improvement work within the City's Right of Way. At the request of Convention Center Renovation personnel, these funds will be utilized to complete street improvements along the perimeter of the Convention Center. This includes curb, paving and driveway approach work on both Avenida Caballeros and Amado Rd. This work includes items 12,15,16, 23 and a portion of Item A. In addition to street improvements, this change order corrects an oversight in the original bid schedule. While the construction of spandrels at the parking lot driveway approaches were required as a part of this project, the bid item was omitted. Item A allows for payment of this work. Items 8, 18, and 26 provides for a new walkway and disabled ramp at the existing Convention Center parking lot located at the NW corner of Avenida Caballeros and Amado Rd. Item 17 allows for payment for additional Type A curb due to the actual quantities required exceeding the original estimate CCO#2, Contreras Construction Co. November 3, 2004 Page 2 Ten (10) additional working days will be added to the project. Funding for Items 12, 15, 16, 23 and A is available in Account No. 134-4498-50227 (Local Measure A, Amado/Alvarado Street Improvements. Funding for Items 8, 17, 18, and 26 is available in Account No. 261-4283-5003 (Convention Center Phase 2, Building and Equipment) SUBBMITED BY: APPROVED BY: � �K � DAVID J. BARAKIAN DAVID H. READY Director of Public Works/City Engineer City Manager ATTACHMENTS: 1. Minute Order 2. Construction Change Order No. Two (2) CITY OF PALM SPRINGS CONTRACT CHANGE ORDER To: Contreras Construction Co. Date: October 12,2004 P.O.Box 1808 Project No.: 02.27 Indio, CA 92201 Project: Convention Center Parking Change Order No.: Two (2) Contract Purchase No.: 416500 Account Numbers: 4498.50227 4371.50227 4283.50003 Agreement No.: 4387 A.CHANGES 1N WORIQCOST: INCREASE TO CONTRACT QUANTITIES—ALTERNATE BID SCHEDI ILE A Bid Item No. 8. Remove PCC Walk 300 SF @ $0.75/SF $ 225.00 12. 3" AC Paving 1000 SF @ $1.10/SF $ 1,100.00 15. 6" Misc. Base 1000 SF @ $0.85/SF $ 850.00 16. A2-6 Curb/Gutter 395 LF @ $18.00/LF $ 7,110.00 17. Al-6 Curb 203 LF @ $15.00/LF $ 3,045.00 18. PCC Sidewalk 300 SF @ $3.10/SF $ 930,00 23. 6' PCC Cross Gutter 144 SF @ $8.00/SF $ 1,152.00 26. PCC Ramp I EA @ 950/EA $ 950.00 New Item A. Curb Return/Spandrel 1450 SF @ $9.00/SF $13,050.00 (Agreed Unit Price) TOTAL NET CHANGE ORDER INCREASE AMOUNT $28,412.00 C. REASONS FOR CHANGES: Items 12, 15, 16, 23 and a portion of Item A: At the request of the Convention Center construction staff, Measure `A' Funds will be used (where allowable), to construct street improvements along the Caballeros and Amado Rd. Frontages of the Convention Center. Item A: While always a part of the approved plan for the parking lot construction, a bid schedule item for these improvements was not included in the contract documents. This item is being added in order to provide compensation for the work. Item 17: Actual quantity required exceeded the original estimate. Contract Change Order#2 Contreras Construction City Project No. 02-27 Items 8, 18 and 26: At the NW corner of Caballeros and Amado a new disabled ramp was constructed. Due to ADA requirements, the back of this ramp could not match up to the existing walkway that leads to the adjacent parking lot. This walkway will be removed and replaced to match, and an additional disabled ramp will be constructed to provide access to the lot. Ten additional working days will be added to the contract for the completion of these improvements. * Note: No additional mark ups will be added to any item on this Change Order.All costs per each item are final. D. SOURCE OF FUNDS Account No. 261-4283-50003 Conv. Center Phase 2 (Building& Equipment) Items 8, 17, 18, and 26: ($5,150.00) Account No. 134-4498-50227 Local Measure A, Amado/Alvarado St. Improvemnts Items 12, 15, 16, 23, and A: ($23,262.00) Summary of Costs Contract Time Original Contract Amount: $ 730,35b.25 Original Completion Date: September 8,2004 This Change Order: $ 28,412.00 Days Added for this C.C.O.: -to- Previous Change Order(s): $ 2,225.00 Previous Days Added: to be determined Revised Contract Amount: $760,993.25 Revised Completion Date: to be determined 1 have received a copy of this Change City Approval: Order and the above AGREED PRICES are acceptable to the contractor. Submitted by Date Field Engineering Manager By Approved by s Date City-Engineer Date Approved by Date City-Manager Distribution: Original Conformed Copies Confrnmed-File Copv Engineering (1) Engineering File (1) Finance (1) Engineering Field Inspector (1) Contractor (1) Engineering Field Supervisor (1) City Clerk (1) Purchasing Agent (I) 2 MINUTE ORDER NO. APPROVING CONSTRUCTION CHANGE ORDER NO. TWO (2) TO CONTRERAS CONSTRUCTION CO., FOR AN INCREASE OF $28,412.00 FOR THE CONVENTION CENTER PARKING LOT PROJECT, CITY PROJECT NO. 02-27 I HEREBY CERTIFY that this Minute Order, approving Construction Change Order No. Two (2) to Contreras Construction Co., for an increase of$28,412.00 for the Convention Center Parking Lot Project, City Project No. 02-27, was adopted by the City Council of the City of Palm Springs, California, in a meeting thereof held on the 3`d day of November, 2004. KATHIE HART Chief Deputy City Clerk •