C,q<1FOBN�Pa CITY COUNCIL STAFF REPORT
DATE: September 3, 2008 CONSENT CALENDAR
SUBJECT: AMENDMENT OF CONTRACT SERVICES AGREEMENT WITH TERRA
NOVA PLANNING & RESEARCH FOR THE WATER SUPPLY STUDY
FOR THE SECTION 14 MASTER DEVELOPMENT PLAN
SUPPLEMENTAL ENVIRONMENTAL IMPACT REPORT.
FROM: David 1-I- Ready, City Manager
BY: Douglas C. Holland, City Attorney
RECOMMENDATION:
1 Make the finding that the First Amendment to the Contract Services Agreement
with Terra Nova Planning & Research is necessary and in the best interest of the
City in order to expand and update the Water Supply Study ("Study") for the
" Section 14 Master Development Plan Supplemental Environmental Impact
Report ("SEIR") in compliance with California Environmental Quality Act
("CEQA")-
2. Approve the First Amendment to the Contract Services Agreement with Terra
Nova Planning & Research.
3. Authorize the City Manager on behalf of the City to execute the First Amendment
to the Contract Services Agreement with Terra Nova Planning & Research.
STAFF ANALYSIS:
The City Attorney recommends that the City Council approve the First Amendment to
the Contract Services Agreement ("Agreement') with Terra Nova Planning & Research
("Terra Nova"). The City Council approved the original Agreement which was executed
as of January 18, 2007. The Agreement called for the preparation of a Supplemental
EIR and a Study of limited scope and documentation as part of a Settlement Agreement
regarding the adequacy of the original Section 14 Master Development Plan EIR- Since
the original Agreement with Terra Nova was executed, Terra Nova has been required to
conduct supplemental water supply modeling and analysis to address unforeseen
developments, including a recent decision by a federal court affecting State Water
Project water deliveries (See Exhibit A-1, "Scope of Work" to First Amendment to
Contract Services Agreement). The proposed First Amendment would compensate
59;519 I
ITEM NO.
City Council Staff Report
September 3, 2008-- Page 2
First Amendment of Contract for Services with Terra Nova Planning & Research
Terra Nova for this additional analysis and related meetings and consultation with the
City Attorney's office and other City staff. The City Council is required to consider the
First Amendment because the additional scope of work results in compensation in
excess of ten percent (10%) of the original compensation amount.
FISCAL IMPACT:
The additional compensation required to complete the updated water supply study in
the amount of, and not to exceed, Thirteen Thousand Five Hundred Dollars and 00/100
($13,500).
David H. Ready, City a
OA�&
Douglas C. Holland, City Attorney
Attachment:
1. Proposed First Amendment to Contract Services Agreement with Terra Nova Planning & Research
59n519 1
32
CITY OF PALM SPRINGS
FIRST AMENDMENT TO CONTRACT SERVICES AGREEMENT
CEQA Supplemental EIR for Section 14
Master Development Plan and Specific Plan
THIS FIRST AMENDMENT TO CONTRACT SERVICES AGREEMENT
("Amendment') is made by and between CITY OF PALM SPRINGS, a
Municipal Corporation ("City"), and TERRA NOVA PLANNING & RESEARCH
("Contractor") as of , 200_, and it amends that certain
Contract Services Agreement dated as of January 18, 2007, by and between City
and Contractor ("Agreement")- All terms defined in the Agreement shall have
the same meaning when used herein.
RECITALS
A. City contracted with Contractor for a Section 14 Master Development Plan
Supplemental Environmental Impact Report ("SEIR") in compliance with the
requirements of the California Environmental Quality Act ("CEQA").
B, The Scope of Services related to the SEIR called for a water supply study of
limited scope and documentation.
C. City has determined that the SEIR must incorporate a water supply study of
expanded scope, analysis and documentation requiring further work from the
Contractor in excess of that set forth in the Agreement's Scope of Services.
D. Buyer and Seller now mutually desire to amend the Agreement as set forth
below.
NOW, THEREFORE, in consideration of the mutual covenants set forth herein
and for other good and valuable consideration, the receipt and sufficiency of
which is hereby acknowledged, City and Contractor mutually agree to amend the
Agreement as follows:
AGREEMENT
1. Section 1.1 of the Agreement shall be amended to include reference to
Exhibit A-1 attached hereto and incorporated herein by this reference.
2. Section 2.1 of the Agreement shall be amended to include reference to
Exhibit C-1 attached hereto and incorporated herein by this reference. Pursuant
to Section 1.8 of the Agreement, City Council approves and authorizes the
Additional Compensation payable to Contractor set forth on Exhibit C-1 in the
amount of, and not to exceed, Thirteen Thousand Five Hundred Dollars and
00/100 ($13,500) as compensation for the services set forth on Exhibit A-1.
Tcrra Nova Agreement-First Amendment Page 1 of 5
}Q2 h5I
Ica
3. Except as expressly amended herein, all terms and provisions of the
Agreement shall remain unamended and in full force and effect as originally
executed. In the event there is a conflict between the terms and provisions of this
Amendment and the terms and provisions of the Agreement, the terms and
provisions of this Amendment shall control.
4. This Amendment shall be binding upon and inure to the benefit of the City
and Contractor and their respective successors and assigns. This Amendment
may be executed in counterparts, each of which, when taken together, shall
constitute one fully executed original. Facsimile signatures shall be binding for
all purposes of this Amendment.
[EXECUTION PAGE FOLLOWS]
Terra Nova Agreement-First Amendment Page 2 of 5
597Vfis�
1 Zi
IN WITNESS WHEREOF, City and Contractor have executed this Amendment
as of the date first written above-
"CITY„
CITY OF PALM SPRINGS
a Municipal Corporation
By:
David H. Ready, City Manager
ATTEST:
By:
James Thompson, City Clerk
APPROVED FORM-
By:
Douglas C. Holland, City Attorney
"CONTRACTOR"
TERRA NOVA PLANNING 8. RESEARCH
a California Corporation
By:
John D. Criste, President
By:
Nicole Sauviat Criste, Vice President
Terra Nova Agreement-First Amendment Page 3 of 5
i42Sn9.1
EXHIBIT A-1
SCOPE OF WORK
ENVIRONMENTAL & PLANNING SERVICES
SECTION 14 MASTER DEVELOPMENT PLAN/SPECIFIC PLAN
SUPPLEMENTAL ENVIRONMENTAL IMPACT REPORT
AND
PROCESSING ASSISTANCE
Terra Nova Planning & Research, Inc. (hereafter Terra Nova) prepared and has
been under contract for the original scope of work to prepare a Supplemental EIR
for the Section 14 Master Development Plan/Specific Plan, which was approved
by the City and the Agua Caliente Band of Cahuilla Indians (Tribe) in 2002. A
Supplemental EIR was prepared in response to litigation challenging the earlier
environmental analysis, with water resources analysis being the focus of the
SEIR.
Supplemental Water Supply Study Modeling & Analysis
During the period that the project Water Supply Study (WSS) was under
development, the circumstances under which water supply was modeled and
analyzed changed significantly. The scope of the study was a result of recent
decisions by the courts regarding State Water Project (SWP) water deliveries
and the decision of the SWP managers to reduce delivers to SWP contractors,
including DWA. Terra Nova has since been coordinating with senior DWA staff
and indirectly with staff at the Department of Water Resources, and conducting
additional research on the effects of the SWP delivery reductions on DWA water
supplies. Amended WSS materials were provided and a variety of models were
reviewed with DWA and others; the final WSS reflects the substantial additional
consultation, research and analysis we conducted. The requested additional
funds include time spent to complete City, DWA, DWR and other consultations,
amend the WSS and facilitate its tacit approval as a consensus analysis.
Meetings, Consultations and Document Revisions
The process of developing the scope of the SEIR analysis, extensive and on-
going consultations and document revisions based on feed back from the City
Attorney and other City staff. In addition, the greatly expanded water resources
analysis included the consultation with and involvement and input of staff from
the City, DWA, Coachella Valley Water District (CVWD) and the state DWR.
Schedule
The schedule for this project, as it currently stands, is not affected by the subject
Change Order. The draft Response to Comments on the DEIR is currently being
reviewed by the City staff. Once finalized, they will be provided to the
commentators and 10-days thereafter the SEIR may be brought before the City
Council for certification.
Terra Nova Agreement-First Amendment Page 4 of 5
592665 1 g
EXHIBIT C-1
COMPENSATION
ENVIRONMENTAL & PLANNING SERVICES
SECTION 14 MASTER DEVELOPMENT PLAN/SPECIFIC PLAN
SUPPLEMENTAL ENVIRONMENTAL IMPACT REPORT
AND
PROCESSING ASSISTANCE
Compensation/Budget
The costs associated with the provision of the above referenced services shall
notexceed:
Field Surveys, Data Collection & Analysis $ 2,700.00
Expanded Water Supply Study $ 7,000.00
Additional Meeting, Consultation &Doc. Revision: $ 3,800.00
Total: $ 13,500,00