HomeMy WebLinkAbout12/15/2004 - STAFF REPORTS (7) DATE: December 15, 2004 TO: City Council FROM: Convention Center Project Administrator CONVENTION CENTER PROJECT CHANGE ORDER AUTHORITY RECOMMENDATION: It is recommended that the City Council ratify all Convention Center Project Change Orders approved by the Project Administrator through December 15, 2004 and authorize an additional $500,000 in Change Order approval authority for the Project Administrator. SUMMARY: This action would ratify all Change Orders issued to date and provide for additional authority to the Project Administrator to allow for the continued smooth flow of the project. BACKGROUND: On October 15, 2003 the City Council approved Resolution No. 20766 establishing administrative parameters for the Convention Center Project. Included in those parameters was the authority for the Project Administrator to approve Change Orders up to $500,000, with regular reports to City Council, and the ability for the City Council to extend the authority. Attached is the "Contract Status Report' for the Convention Center Project dated 19 Nov. 2004, showing total Change Orders to date at$157,106. Two of the Trades, No. 30 Asphalt and No. 31 Misc. Concrete were negotiated Change Orders with the Site Grading Trade Contractors (No. 3A) as the prices agreed to were below the original budgets for the Trades. These two trades equal$142,472 and when added to the Change Orders referenced above, the total Change Orders to date comes to$299,578. (Note:The total Change Orders though December 15, 2004 will be updated at the Council meeting). The attached Resolution would ratify all Change Orders approved by the Project Administrator through December 15, 2004 and would authorize an additional $500,000 in authorrity. Allen F. Smoot Convention Center Project Administrator Approved �k '< City Manager Attachments: 1. Resolution 2. Contract Status Report CONTRACT STATUS REPORT PALM SPRINGS CONVENTION CENTER EXPANSION PROJECT DATED: 19 No. 04 Note: Contract Amount includes any change orders approved at time of award. Trade# Description Contract Amt. Change Orders Adjusted Contract 1 Demolition 369,233 0 369,233 2 Dry Utilities 114,406 0 114,406 3 Site Demolition 325,000 0 325,000 3A Site Grading 400,000 38,575 438,575 3B Shoring 22,154 -2-1,970 184 4 Drilled Caissons 153,000 44,488 197,488 6 Site Concrete 352,276 -10,010 342,266 7 Landscape & Irrig. 381,800 0 381,800 8 Conc. & Reinforcing 1,867,000 67,939 1,924,939 9 Stone/Masonry 1,863,306 459 1,863,765 10 Structural Steel 8,540,000 30,335 8,570,335 12 Drywall/Stucco/Studs 5,970,740 2424 5,973,164 13 Roofing 573,170 0 573,170 1d Flash/Sheet Met. 348,095 36,982 385,077 15 Doors,frames,Hardwarr 179,200 2,673 181,873 16 Glass & Glazing 585,700 0 585,700 17 Acoustical Ceilings 1,530,777 0 1,530,777 18 Tile 94,500 0 94,500 19 Carpet 251,350 0 251,350 20 Painting 350,000 0 350,000 21 Plumbing 700,000 2,524 702,524 22 HVAC 2,626,743 0 2,626,743 23 Fire Sprinklers 269,000 0 269,000 24 Electrical 1,511,000 -51,885 1,459,115 25 Wet Utilities 623,880 4,719 628,599 26 Mill Work 117,330 0 117,330 27 Waterproofing 34,620 0 34,620 29 Special Doors 24,500 0 24,500 30 Asphalt Ch to 3A 78,200 0 78,200 - 31 Misc. Concr 3A 64,272 0 64,272 32 Toilet Compartments 20,605 0 20,605 33 Misc. Specialties 62,550 0 62,550 34 Signage 200,000 0 200,000 35 Operable Walls 499,630 0 499,630 38 Direct Purchase Equip. 1,598,120 9,853 1,607,973 40 N. Parking Lot 553,178 0 553,178 41 Carpet Tile 221,052 0 221,052 42 Utility Relocation 84,953 0 84,953 43 General Requirements 641,025 0 641,025 44 FF&E 400,000 0 400,000 TOTALS 34,592,365 167106 34,749,471 r a BUDGET STATUS REPORT PALM SPRINGS CONVENTION CENTER EXPANSION PROJECT 19 Nov.04 BUDGET ITEM AMOUNT Funds Available From Bond Issue 44,580,542 Funds Available From E Blueprinter 10,300 TOTAL AVAILABLE FUNDS 44,590,842 Soft Cost Items Architectural Design 3,184,972 Environmental Documents 58,000 Topo Survey 18,000 Pre-construction CM services 174,502 CM Services 1,870,825 CM Fee Increase 336,014 City Representative 349,080 Plan Check 21,601 Testing & Inspection 180,000 Blueprinting 200,000 City Administration Cost 160,000 Builders Risk Insurance 50,031 Pre-opening Marketing 350,000 Subtotal Soft Costs 6,953,025 Construction Costs FF&E Set Aside 400,000 Security Set Aside 50,000 Utility Relocations 83,973 General Requirements 641,025 North Parking Lot 553,178 Direct Purchase Equipment 1,598,120 Original Trade Contractor Costs 31,315,089 Change Orders 157,106 Subtotal Construction Costs 34,798,491 TOTAL COSTS 41,751,516 CONTINGENCY REMAINING 2,839,326 J,41 3 RESOLUTION NO. 21164 OF THE CITY COUNCIL OF THE CITY OF PALM SPRINGS, CALIFORNIA, RATIFYING ALL CONSTRUCTION CHANGE ORDERS FOR THE CONVENTION CENTER PROJECT, CITY PROJECT NO. 02-27, APPROVED BY THE PROJECT ADMINISTRATOR THROUGH DECEMBER 15,2004AND AUTHORIZING AN ADDITIONAL $500,000 IN CHANGE ORDER AUTHORITY TO THE PROJECT ADMINISTRATOR. WHEREAS Resolution No. 20766 was approved by City Council on October 15, 2003 to establish, among other parameters, the ability of the Project Administrator to approve Change Orders up to $500,000 and then return for further authorization; and WHEREAS with the project approximately 50% complete additional authority is now needed to ensure the continue smooth construction process and the City Council desires to allocate this additional authority; NOW THEREFORE BE IT RESOLVED by the City Council of the City of Palm Springs, as follows: Section 1: That the City Council does hereby ratify all Construction Change Orders issued by the Project Administrator through December 15, 2004. Section 2. That the City Council does hereby authorize an additional $500,000 of Change Order Authority for the Project Administrator under the same parameters as established in Resolution No. 20766. ADOPTED this 15" day of December, 2004. AYES: Member McCulloch, Mills, Pougnet and Mayor Oden NOES: None ABSENT: Member Foat ATTEST: CITY OF PALM SPRINGS, CALIFORNIA By: City Clerk City Manager REVIEWED & APPROVED AS TO FORM