HomeMy WebLinkAbout1/7/2009 - STAFF REPORTS - 2.G. @ p A LM SAR
.y
U N
W
c W
� oadeo`'vv
City Council Staff Report
January 7, 2009 NEW BUSINESS
Subject: CHANGE ORDER NO. 2 TO AGREEMENT N0. 5700 WITH GRANITE.
CONSTRUCTION COMPANY, FOR THE 2007/2008 ANNUAL ARHM
OVERLAY, CITY PROJECT 07-17
From: David H. Ready, City Manager
Initiated by: Public Works and Engineering Department
SUMMARY
Approval of Change Order No. 2 to the Granite Construction Company contract
(Agreement No. 5700) revises the total contract amount for construction to
$1,497,039.51 for an increase of $52,495.51 for additional construction quantities
required to complete the work indicated in the original contract and Change Order No.
1, and additional streets added for overlay as part of the 2007/2008 Annual ARHM
Overlay, City Project 07-17.
RECOMMENDATION:
1) Approve Change Order No. 2 to Agreement No. 5700 with Granite Construction
Company, in an amount of $52,495.51 for a revised total contract amount of
$1,497,039.51 for the 2007/2008 Annual ARHM Overlay, City Project 07-17; and
2) Authorize the City Manager to execute all necessary documents.
STAFF ANALYSIS:
On July 16, 2008, the City Council awarded a construction contract to Granite
Construction Company for the 2007/2008 Annual ARHM Overlay, City Project 07-17.
This project includes an asphalt rubber hot mix (ARHM) overlay of the following City
streets.-
1. Indian Canyon Drive, from Tramview Road to San Rafael Drive (west half)
2. Farrell Drive, from Tahquitz Cyn Way to Baristo Road
_ 3. Farrell Drive, from Baristo Road to Ramon Road
4. Baristo Road, from Sunrise Way to Farrell Drive
Item No. 2 . G • .
City Council Staff Report
January 7, 2009 - Page 2
Granite Construction Company—Change Order No. 2 (CP 07-17)
5. Tachevah Drive, El Alameda, Tamarisk Road, and Amado Road (between Palm
Canyon Drive and Indian Canyon Drive)
6. Belardo Road (between Ramon Road and Arenas Road)
7. San Lorenzo Road (between Random Road and Sunrise Way)
8. Camino Real (between Mesquite Avenue and S. Riverside Drive)
9. Via Escuela (between N. Palm Canyon Drive and Zanjero Road)
A total of approximately 650,000 square feet of overlay was included in the project, as
originally bid. City Council subsequently approved Change Order No. 1 on July 30,
2008 which expanded the scope of the project by approximately 280,000 square feet
and included the addition of the following streets:
1) Paseo El Mirador (Sunrise Way to Paseo de Anza)
2) Santa Rosa Drive (Monte Vista Dr. to Patencio Rd.)
3) Arenas Road (Palm Canyon Dr. to Indian Canyon Dr.)
4) Lugo Road (400 feet north of Baristo Rd. to Arenas Rd.)
5) Panga Way (Patencio Rd. to west end)
(3) Patencio Road (Arenas Rd. to Baristo Rd.)
7) Santa Rosa Drive (Patencio Rd. to west end)
8) Tahquitz Canyon Way (Palm Canyon Dr. to Indian Canyon Dr.)
9) Mountain View Place (Via Monte Vista to Patencio Rd.)
10) Chino Drive (Patencio Rd. to Palm Canyon Dr.)
11) Cahuilla Road (Hermosa Place to Via Lola)
12) Canyon Place (Patencio Rd. to Mission Rd.)
13) Merito Place (Palm Canyon Dr. to Mission Rd.)
14) Zanjero Road (Cabrillo Rd. to Cortez Rd.)
15) Zanjero Road (Via Escuela to north end)
16) Alvarado Road (Palm Canyon Dr. to De Anza Rd.)
17) Via Norte (Via Escuela to Mariscal Rd.)
When construction began, the Annual Slurry Seal Project was completing work in
section 23 (Warm Sands Neighborhood). During that project two streets that had been
scheduled for a slurry seal application were identified as having a low pavement
condition index (PC[), and it was determined that the condition of the streets had
deteriorated to the point that slurry seal was no longer an appropriate maintenance
option. These streets were removed from the slurry project and added to the overlay
project at a cost of$26,459.00. The two streets were:
1) Riverside Place (Riverside Dr. to the North end)
2) Parocela Place (Warm Sands Dr. to Grenfall Rd.)
E4
City Council Staff Report
January 7, 2009- Page 3
Granite Construction Company—Change Order No. 2 (CP 07-17)
In addition to these streets, an agreement was made with the developer of Dinks Bar
and Grill to expand the paving limits on the South side of Via Escuela Road between
North Palm Canyon and Zanjero Rd. The Overlay Project and this development took
place concurrently and an agreement was made in which the developer deposited
$10,367.10 with the City to cover expenses associated with the additional paving which
was originally conditioned as a part of the Dinks project. The paving was completed as
a part of this project and these funds will be utilized to cover the expenses for this
additional work.
All other additional costs indicated on this Change Order are due to the actual
construction quantities required to complete the work approved in the original contract
and Change Order No. 1.
This is a final balancing change order, and no additional work will be performed on this
project. It should be noted that costs incurred by the City to adjust water valves to
grade are expected to be reimbursed by the Desert Water Agency in accordance with a
prior agreement. Reimbursement is expected to be $46,000.00.
FISCAL IMPACT:
Funding for this project is available in the following accounts and will be utilized as
indicated: 133-4298-50225 Local Measure A, ARHM Overlay ($42,128.41) and 001-
4201-43200 Contractual Services ($10,367.10).
SUBMITTED:
David J. Barakian Thomas J. Wilson
Director of Public Works/City Engineer Assistant City Manager
David H. Ready,
City Manager
Attachments:
1. Construction Change Order No. 2
03
CITY OF PALM SPRINGS
CONTRACT CHANGE ORDER
To: Granite Construction Co. Dale: November ta,2008
585 West Beach Street Project No.: 07-17
Watsonville,CA 95076 Project: 2oo7/2ooS ARHM Overlay
Change Order No.: TWO (2)
Contract Prircbase No.: 09-0338 : o
Account Numbers: 133-4298-50225
1,34-4498-50225
Agreement No.: 5700
CHANGES IN WORIC/COST
Increase/Decrease to Contract Quantities
Schedule A
Item No_ 3 Cold Mill AC -421 @ $0.30/SF ($126.30)
Item No. 4 1.5" ARI-IIvI Overlay -445 @ $1.14/SF ($507.30)
Item No. 5 Adjusi Water Valve -4 @ $500.00/EA ($2,000.00)
Item No. 7 Detector Loops I @ $300.00/EA $300.00
Subtotal (decrease amount) ($2,333.60)
Schedule B
Item No. 3 Cold Mill AC -1332 @ $0.30/SF ($399.60)
Item No. 4 1.5" ARHM Overlay -2000 @ $1.14/Sp ($2,280.00)
Item No. 6 Adjust Sewer Manhole -2 @$700.00/EA ($1,400.00)
Subtotal (decrease amount) ($4,079.60)
Schedule C
Item No. 3 Cold Mill AC 3632 @ $0.30/SF $1,089.60
Item No. 4 1.5" ARHM Overlay 1000 @ $1.14/SF $1,140.00
Item No. 5 Adjust Water Valve -7 @$500.00/BA ($3,500.00)
Item No. 6 Adjust Sewer Manhole l @ $700.00/BA $700,00
Subtotal (decrease amount) ($570.40)
Schedule ID
Item No. 3 Cold Mill AC 1700 @ $030/SF $510.00
Item No. 4 1.5" ARAM Overlay -700 @ $1.14/SF ($798.00)
Item No. 5 Adjust Water Valve I @ $500.00/LA $500,00
Item No, 7 Detector Loops -1 @ $300.00/EA (S300.00)
Subtotal (decrease amount) (S88.00)
Schedule E
Item No. 3 Cold Mill AC -1 100 @ $0.30/SF ($330.00)
Item No. 4 1.5" ARHM Overlay -2500 @ $1.14/SF ($2,850.00)
Item No. 5 Adjust Water Valve -1 @ $500.00/EA ($500.00)
Subtotal (decrease amount) ($3,680.00)
1
Schedule F
Item No, 3 Cold Mill AC -150 @$0.30/SF ($45.00)
Item No. 4 1.5"ARHM Overlay -800 @ $1.14/SF ($912.00)
Item No. 5 Adjust Water Valve -4 @ $500.00/FA ($2,000.00)
Item No. 6 Adjust Sewer Manhole -1 @ $700.00/EA ($700.00)
Subtotal (decrease amount) ($3,657.00)
Schedule G
Item No. 3 Cold Mill AC 900 @ $0.30/SF $270.00
Item No. 4 1.5"ARHM Overlay 10000 @ $1.14/SF S11,400.00
New Item A Adjust Water Valve 3 @ S500.00/EA $1,500.00
Subtotal Increase amount $13,170.00
Change Order No. 1
A. 1.5" ARHM Overlay 19169 @ $1.14/SF $21,852.66
B. Cold Mill AC -1 OS36 @ $0.30/SF ($3,250.80)
C. Detector Loops 6 @ $300.00/EA $1,800.00
D, Adjust Water Valve 12 @ $500.00/EA $6,000.00
E Adjust Sewer Manhole 1 @ $700.00/EA $700.00
Force Account Striping Lump Sum $173.25
Subtotal Increase amount S27,275.11
New Items
H. Cold Mill AC 7900 @ $0.30/SF $2,370.00
1. 1.5" ARHM Overlay 18900 @$1.14/SF $21,546.00
J. Adjust Water Valve 1 @ $500/EA $500.00
K. Adjust Sewer Manhole 2 @ $700.00/EA $1400.00
L. Mobilization Lump Sum $2,400.00
M. Traffic Control Lump Sum $1,500.00
N. Pavement Markings Lump Sum $525.00
O. Reimbursement of Overpay Lump Sum ($3,782.00)
Subtotal Increase amount $26,459.00
TOTAL NET CHANGE ORDERIINCREASE AMOUNT $52,495.51
REASONS FOR CHANGES:
All increases and decreases to the original bid quantities and to change order No. 1, were due to the actual
quantities required in the field being more or less than the original estimate.
New items H thru N were added to the project in order to complete improvements on Riverside Place
(Riverside Dr. to North end), and Parocela Pl. (Warm Sands to Grenfall), after it was determined that they
could not be maintained as a part of the recent slurry seal project due to their poor condition-
2
New item 0 reimburses the City for items that were overpaid prior to the final determination of contract
quantities.
$10,367.10 of the increase amount to Bid Schedule G,was provided by the developer ofDinks Bar and Grill.
These funds have been received by the City and will be utilized to compensate for additional paving
performed along the Via Escucla frontage of this project.
Note: costs incurred by the City to adjust water valves on ibis project are to be reimbursed by DWA per
prior agreement. Reimbursement is expected to be $46,000-00-
Note: No additional mark ups will be added to any itew on this Change Order. All costs are
final.
D. SOURCE OF FUNDS
The following accounts utilized: 134-4498-50225 local Measure A,ARAM Overlay ($42,128.41), and
001-4201-43200 Contractual Services ($10,367.10 - funds previously deposited to be withdrawn).
Summary of Costs Contract Time
Original Contract Amount: $998,86o.00 Original Completion Date: November 1 ,2008
This Change Order: $52,495.51 Days Added for this C.C.O.: —o—
Previous Change Order(s): $445,684.00 Previous Days Added: —0—
Revised Contract Amount_ $3,497,039.51 Revised Completion Date: November 14,
2008
I have received a copy of this Change C•ty App al:
Order and the above AGREED PRICES
are acceptable to the contractor- Submitted by _ Date --"
Senior Public Works Inspector
B ��d#"•CFyarr2 Approved by
r.L- �0r_
Contractor City-Engineer
Date /d 3 015 Approved by Date
City-Manager
Attested by Date
C1ly Clerk
Distribution:
Original Executed Copies Conformed-FilQ__Qop_v
Contractor (1) Engineering File (1)
City Clerk (1) Senior Public Works Inspector (1)
Finance (1)
3