HomeMy WebLinkAbout3/2/2005 - STAFF REPORTS (14) CITY COUNCIL March 2, 2005
CONSENT CALENDAR
Subject:: CAMINO AMAPOLA AND CAMINO PRIMROSE STREET
IMPROVEMENTS
Initiated by: David J. Barakian, Director of Public Works/City Engineer
SUMMARY:
The City Council will consider awarding a Construction Contract to the lowest
responsible and responsive bidder to construct street improvements funded through the
City's Community Development Block Grant (CDBG) program for Camino Amapola and
Camino Primrose Street Improvements, City Project 04-11.
RECOMMENDATION:
Adopt Minute Order No. _ "Awarding contract to International Pavement Solutions,
Inc. in the amount of $184,784.50 for Bid Schedules A and B and Additive Bid
Schedules C and D, for the Camino Amapola and Camino Primrose Street
Improvements, City Project No. 04-11".
STAFF ANALYSIS:
On April 7, 2004, the City Council approved the 2004/2005 CDBG Program, which
included the Public Works and Engineering Department's application for construction of
Camino Amapola and Camino Primrose Street Improvements. These streets located
between Calle Amigos and Thornhill Road, lack improvements on both sides, and are in
general disrepair. The project is a continuation of the Calle Amigos Street Improvement
project, which was completed in September 2004 and funded by CDBG dollars.
The proposed improvements will accomplish street widening, construction of curb and
gutter, standard driveway approaches and sidewalk of Camino Amapola and Camino
Primrose, as well as complete the cross-gutters at each intersection of Thornhill Road to
improve existing pavement and storm-water surface drainage and eliminate stagnant
water. The plans and specifications were prepared by the Public Works and
Engineering Department staff. The scope of work is included in two Bid Schedules of A
and B (Camino Amapola and Camino Primrose respectively), as well as in two Additive
Bid Schedules C and D (extension of re-pavement on Amapola and Primrose
respectively).
The City Council approved the plans and specifications, and authorized construction
bidding at its January 5, 2005 meeting. Subsequently, the project was advertised for
bids, and at 2:00 P.M. on February 23, 2005, the Department of Procurement and
Contracting received bids from the following contractors:
Fo001
Camino Amapola
March 2, 2005
Page 2
Contractor Sch A Sch B Sch C Sch D Total
Int'I Pavement Solutions, Inc. 77,317.00 72,050.50 17,302.00 18,115.00 184,784.50
San Bernardino, Ca
NPG Corporation 75,476.85 70,291.05 23,938.08 24,565.80 194,271.78
Perris, CA
Tyner Paving Company 89,232.50 83,292.50 17,452.00 18,247.00 208,224.00
Los Angeles, Ca
Mocon Corporation 105,601.90 99,619.50 19,462.65 19,588.70 244,272.75
Indio, Ca
Hardy&Harper, Inc. 106,558.50 96,152.00 24,054.50 25,563.00 252,328.00
Santa Ana, CA
Engineer's Estimate 82,776.00 77,777.00 13,073.00 14,159.00 187,785.00
The low bidder is International Pavement Solutions, Inc. The company is a corporation
whose officers are Dennis Rieger, CEO/Treasurer and Brent Rieger, President.
The award and completion of this contract is imperative to meet HUD's timely
expenditure standard. This action will allow the City to demonstrate that CDBG funds for
the 2004 — 2005 program year are at least encumbered, and are especially significant as
this project represents approximately 35% of the total CDBG entitlement.
FISCAL IMPACT:
There is no impact to the General Fund in that the project is being entirely appropriated
from the CDBG Account No. 137-4805-63547 (PSPubWks—Primrose Amapola), which
sufficiently covers this award.
� p
David J. Barakian, Director of David H. Ready, City Manag4er�
Public Works/City Engineer
Attachment: Minute Order
000� ..
CITY OF PALM SPRINGS
NOTICE INVITING BIDS
For the construction of CAMINO AMAPOLA AND CAMINO PRIMROSE STREET
IMPROVEMENTS - City Project No. 04-11 .
N-1 . NOTICE IS HEREBY GIVEN that sealed bids for the CAMINO AMAPOLA AND CAMINO
PRIMROSE STREET IMPROVEMENTS will be received at the office of the Director of
Procurement and Contracting of the City of Palm Springs, California, until 2
P.M. on February 23, 2005 at which time they will be opened and read aloud.
N-2 . DESCRIPTION OF THE WORK: The Work comprises the construction of asphalt
concrete pavement; crushed miscellaneous base; Portland cement concrete curb
and gutter, cross-gutter, spandrel, curb return, sidewalk and driveway
approaches; removal of existing asphalt concrete pavement and Portland cement
concrete improvements; adjustment of sewer manholes to grade; traffic
striping, signage and markings; cold planing and grinding of existing asphalt
concrete pavement; construction of asphalt rubber hot mix (ARHM) overlay; and
all appurtenant work on Camino Amapola and Camino Primrose in Palm Springs .
N-3. AWARD OF CONTRACT:
a) The City reserves the right after opening bids to reject any or all bids,
to waive any informality (non-responsiveness) in a bid, or to make award to the
lowest responsive, responsible bidder on the basis of the total sum of Bid
Schedules A & B and Additive Bid Schedules C & D, and reject all other bids, as
it may best serve the interest of the City. Bidders shall bid on all Bid
Schedules.
(b)As a condition of award, the successful bidder will be required to submit
payment and performance bonds and insurance.
N-4. BID SECURITY: Each bid shall be accompanied by a certified or cashier's
check or Bid Bond in the amount of 10 percent of the total sum of Bid Schedules
A, & S and Additive Bid Schedules C & D. payable to the City of Palm Springs.
N-5. BIDS TO REMAIN OPEN: The Bidder shall guarantee the Total Bid Price for a
period of 60 calendar days from the date of bid opening.
N-6. CONTRACTOR'S LICENSE CLASSIFICATION: The Contractor shall possess a valid
Class A Contractor license at the time of award.
N-7. CALIFORNIA WAGE RATE REQUIREMENTS: The Contractor shall pay the general
prevailing rate of per diem wages as determined by the Director of the
Department of Industrial Relations of the State of California for the locality
where the work is to be performed. A copy of said wage rates is on file at the
office of the City Engineer. The Contractor and any subcontractors shall pay
not less than said specified rates and shall post a copy of said wage rates at
the project site.
N-8. FEDERAL WAGE RATES: The general prevailing rate of wages by the Secretary
of Labor are included in the Contract. If there is any difference between the
State or Federal wages rates, the Contractor must pay the higher of the 2
rates.
N-9. RETAINAGE FROM PAYMENTS: The Contractor may elect 'to receive 100 percent
of payments due under the Contract Documents from time to time, without
retention of any portion of the payment by the City, by depositing securities
CAM.AMAPOLA&CAM. PRIMROSE STREET IMPROVEMENTS k✓� _ _ `
CITY PROJECT NO.04-11
1/24/05 NOTICE INVITING BIDS
PAr'=1
4 .M
of equivalent value with the City in accordance with the provisions of Section
22300 of the Public Contract Code.
N-10. FEDERAL NON-DISCRIMINATION PROVISION: Bidders shall comply with the
President 's Executive Order No. 11246.
N-11. FEDERAL INTEREST EXCLUSION: Any contract or contracts awarded under this
Notice Inviting Bids are expected to be funded in part by a grant from the
United States Government. Neither the United States nor any of its departments,
agencies, or employees is or will be a party to this Notice Inviting Bids or
any resulting Agreement. This procurement will be subject to regulations
contained in 40 CFR Part 33 and 35.
N-12. OBTAINING OR INSPECTING CONTRACT DOCUMENTS:
(a) Contract Documents may be inspected without charge at the office of the
City Engineer, 3200 East Tahquitz Canyon Way, Palm Springs, CA 92262.
(b) Complete sets of said Contract Documents may be purchased at $30.00 per
set and are obtainable from the office of the City Engineer, 3200 East Tahquitz
Canyon Way, Palm Springs, CA 92262. No refund will be made of any charges for
sets of Contract Documents.
(c) An additional fee of $20.00 will be charged for sets of documents sent
by mail.
N-13. ADDRESS AND MARKING OF BIDS: The envelope enclosing the Bid shall be
sealed and addressed to the City of Palm Springs, and shall be delivered or
mailed to the Director of Procurement and Contracting at 3200 East Tahquitz
Canyon Way, Palm Springs, CA 92262. The envelope shall be plainly marked in the
upper left hand corner with the name and address of the Bidder and shall bear
the words "Bid For. . " followed by the title of the Project and the date and
hour of opening Bids. The certified or cashier's check or Bid Bond shall be
enclosed in the same envelope with the Bid.
BY ORDER OF THE CITY OF PALM SPRINGS CITY OF PALM SPRINGS
Date By
9 `L,� ,
'/�is/0� _ _
David J. Barakian, P.E.
Director of Public Works/City Engineer
City of Palm Springs
CAM.AMAPOLA&CAM.PRIMROSE STREET IMPROVEMENTS
CITY PROJECT NO.04-11
1/24/05 NOTICE INVITING BIDS
CITY OF PALM SPRINGS
NOTICE INVITING BIDS
For the construction of CAMINO AMAPOLA AND CAMINO
PRIMROSE STREET IMPROVEMENTS
City Project No 04-11.
N-1. NOTICE IS HEREBY GIVEN that sealed bids for the
CAMINO AMAPOLA AND CAMINO PRIMROSE STREET
Proof of Publication IMPROVEMENTS will be received of the office of the Director
of Procurement and Contracting at the City of Palm Springs,
In Newspaper
California,until P.M.on February 23,2005 at which time they
will be opened and read aloud
STATE OF CALIFORNIA
will DESCRIPTION ad THE WORK:The Work comprises the
County of Riverside constructionbase;
asphalt concrete pavement crushed m,cross-
getter,base;Portland cement sidewalk
[e curb and gutter,cross-
r,spandrel,curb return,sitla It c and driveway approach-
as; d
removal of existing asphalt concrete pavement and
Laura Reyes says, Portland cement concrete improvements;adjustment of sewer
manholes to grade;traffic striping,signage and markings;cold
planing and grinding of existing asphalt concrete pavement,
1. 1 am a citizen of the United States, a construction of asphalt rubber hat mix(ARHM)overlay;and all
resident of the City of Indio, County of appurtenantl5°rk°n Camino Amebae and Camino Primrose in
Riverside, State of California, and over the N-3.AWARD OF CONTRACT:
a)The City reserves the right after opening bids to reject
age of 18 years, any or all bids,to waive any informality(non-responsiveness)in
2. 1 am the Office & Production Manager of a bid,or to make award t0 the lowest responsive,responsible
9 bidder on the basis of the total sum of Bitl Schedules A&B and
The Public Record, a newspaper of Additive Bid Schedules C&D,and reject all other bids,as it
general circulation printed and published in may best serve the interest of the City Bidders shall bid on all
- - - _ -- — ------- --
the City of Palm Springs,_ —Eid-scn°dules.County of (b) As acondilicn of award,the successful bidder will
Riverside State of California. Said The be r to submit payment and performance bonds and
, I insurance.
Public Record is a newspaper of general iBID SECURITY:Each bid shall be accompanied byacer-
eirculation as that tang is defined In tified or cashier's check or Bid Bond in the amount of 10 per-
cent of the total sum of Bid Schedules A&B and Additive Bid
Government Code section 6000, its status Schedules C&D,payable to the City of Palm Springs.
as such having been established b edictal N-5,BIDS TO REMAIN OPEN:The Bidder shall guarantee[he
9 y J Total Bid Price for a period of 60 calendar days from the date
decree of the Superior Court of the State of of bid opening.
N-S. CONTRACTOR'S LICENSE CLASSIFICATION: The
California in and for the County of Riverside Contractor shall possess a valid Class A Contractor license at
in Proceeding No. Indio 49271, dated March the lime of award
i CALIFORNIA WAGE RATE REQUIREMENTS: The
31, 1987, entered In Judgment Book No. Contractor shall pay the general prevailing rate of per diem
129, page 355, on March 31, 1 987. wages as determined by the Director of [he Department of
Industrial Relations of the Slate of California for the locality
3. The Public Record is a newspaper of where[he work is to be performed.A copy of said wage rates
general circulation ascertained and is on file at the office of the City Engineer The Contractor and
any subcontractors shall pay not less[ban said specified rates
established in the City of Palm Springs in and shall post a copy 0l said wage rates at the project site.
the County of Riverside, State of California, N-11.FEDERAL WAGE RATES:The general prevailing rate of
wages by the Secretary of Labor are Included in the Contract.
Case No. RIC 358286, Filed June 8, 2001. If there is any difference between the Slate or Federal wages
4. The notice, of which the annexed is a true rates,the Contractor must pay the higher of the 2 rates.
N-9. RETAINAGE FROM PAYMENTS: The Contractor may
printed copy was published in the elect t0 receive 100 percent of payments due under the
newspaper on the following publication Contract Documents from time lc lime,without retention of any
portion of the payment by the City,by parcelling securities
dates to wit: _ of equivalent value with the City in accordance with the provi- -
slons of Section 22300 of ie lic ContracTC.d—.._-'--""
N-10. FEDERAL NON-DISCRIMINATION PROVISION:
February 1, 2005 B[do.,
shall comply with the President's Executive Order No
February 8, 2005 N'116 FEDERAL INTEREST EXCLUSION: Any contract or
contracts awarded under this Notice Inviting Bids are expected
I certify under penalty of perjury that the to be funded in soft by a grant [ram the United States
y P y P er y Government Neither the United Slates nor any of its depart
above is true and correct. moms, agencies, or employees is or will be a party to this
Dated at Palm Springs, California, this 9th Notice Invitiill be subject Bids to any resulting Agreement This prod 33
motif will be Bids or any resulting
contained in 40 his Part 33
day of February, 2005. and35.
N-12. OBTAINING OR INSPECTING CONTRACT DOCU-
MENTS:
IJd' `. (a) Contract Documents may be inspected without
jsr(� oSp�n charge at the office of the City Engineer,3200 East Tahgmtz
Cf .v`W�., Canyon Way,Palm Springs,CA 92262.
(b)Complete sets of said Comfort)Documents may be
r fir- jo0 purchased at$30.00 per sot and are obtainable from the office
I LipI1 23 r 'JJnnCC r„•,, of the CityEngineer,3200 East Tehgmtz Canyon Way,Palm
Spnngs,CA 92262.No refund will be made of any charges for
^F) sets of Contract Documents
(c)An additional fee of$20.00 will be charged for sets of
.11�Z�y documents sent by mail.
N-13 ADDRESS AND MARKING OF BIDS: The envelope
enclosing the Bid shall be sealed and addressed to the City of
Palm Springs,and shall be delivered or mailed 10 the Director
of Procurement and Contracting at 3200 East Tahquld:Canyon
f/ Way,Palm Springs,CA 92262 The envelope shall be plainly
L�a Reyes marked in the upper left hand corner with the name and
address of the Bidder and shall bear the words"Bid For"fol-
\�_� ice &Prod ction Manager lowed by the title of the Prefect and the dale and hour of open-
ing Bids The certified or cashier's check or Bid Bond shall be
amended in the same envelope with the Bid.
BY ORDER OF THE CITY OF PALM SPRINGS
CITY OF PALM SPRINGS
/s/David J.Barakian,P.E.
Director d Public Works/City Engineer
City of Palm Springs
February 1,8,2005
MINUTE ORDER NO. 7G ! O
AWARDING CONTRACT TO INTERNATIONAL
PAVEMENT SOLUTIONS, INC. IN THE AMOUNT OF
$184,784.50 FOR BID SCHEDULES A AND B AND
ADDITIVE BID SCHEDULES C AND D, FOR THE
CAMINO AMAPOLA AND CAMINO PRIMROSE STREET
IMPROVEMENTS, CITY PROJECT 04-11. A D✓lOif.S
I HEREBY CERTIFY that this Minute Order, awarding contract to International Pavement
Solutions, Inc. in the amount of $184,784.50 for Bid Schedules A and B and Additive Bid
Schedules C and D, for the Camino Amapola and Camino Primrose Street
Improvements, City Project 04-11, was adopted by the City Council of the City of Palm
Springs, California, in a meeting thereof held on 2nd day of March, 2005.
JAMES THOMPSON
City Clerk