DATE: June 15, 2005 Unfinished Business
SUBJECT: ADDITIONAL CHANGE ORDER AUTHORITY FOR THE CONVENTION
CENTER PROJECT
FROM: David H. Ready, City Manager
BY: City Manager— Convention Center
SUMMARY
Staff requests that City Council ratify previous Administrator approved Change Orders
and approve an additional $500,000 in change order authority for the Convention
Center Project
RECOMMENDATION:
Adopt Resolution No. _, "A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF PALM SPRINGS, CALIFORNIA, RATIFYING ALL CONSTRUCTION
CHANGE ORDERS FOR THE CONVENTION CENTER PROJECT, CITY
PROJECT NO. 02-27, APPROVED BY THE PROJECT ADMINISTRATOR
FROM DECEMBER 16, 2004 THROUGH JUNE 15, 2005 AND AUTHORIZING
AN ADDITIONAL $500,000 IN CHANGE ORDER AUTHORITY TO THE
PROJECT ADMINISTRATOR."
STAFF ANALYSIS:
On October 15, 2003 the City Council adopted Resolution No. 20766, which established
project administrative provisions for the Convention Center Project. One of the
administrative provisions was the establishment of Change Order Authority for the
Project Administrator to ensure timely completion of the project. The initial allowance
was $500,000 and in December of 2004 the City Council authorized an additional
$500,000. Staff now seeks an additional allocation of $500,000 per the attached
Resolution.
It should be noted that the project was initially budget with a contingency for Change
Orders at over $3 million and at this time there remains over $2.1 million in that
contingency. Attached to this report are copies the Contract Status Report and Budget
Item No. 4.A.
City Council Staff Report
June 15, 2005 -- Page 2
Convention Center Change Order Authority
Status Report for the Convention Center project. They currently show, as of May 31,
2005, $667,145 in approved Change Orders and with an additonal $300,000 out for
Contractor signature the current authority of$1 million will soon be met.
FISCAL IMPACT:
The Project Bond Issue includes over $3 million for Project Change Order Contingency
and there currently remains over$2.1 million.
Allen F. Smoot, Project Administrator David H. Ready, CityKA g r
Attachments:
1. Resolution
2. Contract Status Report
3. Budget Status Report
RESOLUTION NO.
OF THE CITY COUNCIL OF THE CITY OF PALM
SPRINGS, CALIFORNIA, RATIFYING ALL
CONSTRUCTION CHANGE ORDERS FOR THE
CONVENTION CENTER PROJECT, CITY PROJECT
NO. 02-27, APPROVED BY THE PROJECT
ADMINISTRATOR FROM DECEMBER 16, 2004
THROUGH JUNE 15, 2005 AND AUTHORIZING AN
ADDITIONAL$500,000 IN CHANGE ORDER AUTHORITY
TO THE PROJECT ADMINISTRATOR.
WHEREAS Resolution No. 20766 was approved by City Council on October 15, 2003 to
establish, among other parameters, the ability of the Project Administrator to approve
Change Orders up to $500,000 and then return for further authorization; and
WHEREAS on December 15, 2004 the City Council approved an additional $500,000 in
Change Order authority; and
WHEREAS with the project approximately 75%complete additional authority is now needed
to ensure the continue smooth construction process and the City Council desires to allocate
this additional authority;
NOW THEREFORE BE IT RESOLVED by the City Council of the City of Palm Springs, as
follows:
Section 1: That the City Council does hereby ratify all Construction Change Orders issued
by the Project Administrator from December 15, 2004 through June 15, 2005.
Section 2. That the City Council does hereby authorize an additional $500,000 of Change
Order Authority for the Project Administrator under the same parameters as established in
Resolution No. 20766.
ADOPTED this 15" day of June, 2005,
David H. Ready, City Manager
ATTEST:
James Thompson, City Clerk
CERTIFICATION
STATE OF CALIFORNIA )
COUNTY OF RIVERSIDE ) ss.
CITY OF PALM SPRINGS )
I,JAMES THOMPSON, City Clerk of the City of Palm Springs, hereby certify that Resolution
No. _ is a full, true and correct copy, and was duly adopted at a regular meeting of the
City Council of the City of Palm Springs on by the following
vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
James Thompson, City Clerk
City of Palm Springs, California
A
CONTRACT STATUS REPORT
PALM SPRINGS CONVENTION CENTER EXPANSION PROJECT
DATED: 31-May-05 Note: Contract Amount includes any change orders approved at time
of award.
Trade# Description Contract Amt. Change Orders Adjusted Contract
1 Demolition 369,233 15,698 384,931
2 Dry Utilities 114,406 0 114,406
3 Site Demolition 325,000 -2,562 322,438
3A Site Grading 400,000 91,552 491,552
3B Shoring 22,154 -21,970 184
4 Drilled Caissons 153,000 44,488 197,488
6 Site Concrete 352,276 -10,010 342,266
7 Landscape& Irrig. 381,800 4,857 386,657
8 Conc. & Reinforcing 1,857,000 67,939 1,924,939
9 Stone/Masonry 1,863,306 -17,382 1,845,924
10 Structural Steel 8,540,000 30,335 8,570,335
12 Drywall/Stucco/Studs 5,970,740 11,744 5,982,484
13 Roofing 573,170 11,180 584,350
14 Flash/Sheet Met. 348,095 303,378 651,473
15 Doors,frames,Hardwan 179,200 5,705 184,905
16 Glass & Glazing 585,700 4,961 590,661
17 Acoustical Ceilings 1,530,777 21,393 1,552,170
18 Tile 94,500 0 94,500
19 Carpet 251,350 21,425 272,775
20 Painting 498,000 -22,376 475,624
21 Plumbing 700,000 11,690 711,690
22 HVAC 2,626,743 11,345 2,638,088
23 Fire Sprinklers 269,000 77,595 346,595
24 Electrical 1,511,000 -58,589 1,452,411
25 Wet Utilities 623,880 -5,281 618,699
26 Mill Work 97,947 0 97,947
27 Waterproofing 62,749 -6,768 55,981
29 Special Doors 56,705 0 56,705
30 Asphalt Ch to 3A 78,200 0 78,200
31 Misc. Concr3A 64,272 0 64,272
32 Toilet Compartments 24,895 0 24,895
33 Misc. Specialties 17,210 0 17,210
34 Signage 70,950 0 70,950
35 Operable Walls 499,630 0 499,630
38 Direct Purchase Equip. 1,598,120 9,853 1,607,973
40 N. Parking Lot 553,178 0 553,178
41 Carpet Tile 221,052 0 221,052
42 Utility Relocation 84,953 3,600 88,553
43 Misc. 0 11,115 11,115
44 Mesquite Carpet 0 52,230 52,230
TOTALS 33,570,191 667145 34,237,336
BUDGET STATUS REPORT
PALM SPRINGS CONVENTION CENTER EXPANSION PROJECT
31-May-05
BUDGET ITEM AMOUNT
Funds Available From Bond Issue 44,580,542
Funds Available From (Others 12,938
TOTAL AVAILABLE FUNDS 44,593,480
Soft Cost Items
Architectural Design 3,235,547
Environmental Documents 58,000
Topo Survey 18,000
Pre-construction CM services 174,502
CM Services 1,966,825
CM Fee Increase 336,014
City Representative 349,080
Plan Check 21,601
Testing & Inspection 180,000
Blueprinting 200,000
City Administration Cost 160,000
Builders Risk Insurance 50,031
Pre-opening Marketing 350,000
Subtotal Soft Costs 7,099,600
Construction Costs
FF&E Set Aside 400,000
Security Set Aside 50,000
Utility Relocations 84,953
Beverage Equipment 24,000
General Requirements 641,025
North Parking Lot 553,178
Direct Purchase Equipment 1,598,120
Original Trade Contractor Costs 31,333,940
Change Orders 667,145
Subtotal Construction Costs 35,352,361
TOTAL COSTS 42,451,961
CONTINGENCY REMAINING 2,141,519