HomeMy WebLinkAbout9/7/2005 - STAFF REPORTS (22) OF PALM S
P�
U N
r
q`
q City Council Staff Report
C <I FO R�\P
DATE: September 7, 2005 CONSENT CALENDAR
SUBJECT: 2004/2005 ANNUAL SLURRY SEAL, CONSTRUCTION CHANGE
ORDER NO. TWO (2)
FROM: David H. Ready, City Manager
BY: Public Works & Engineering Department
SUMMARY
This is the final balancing change order for the 2004/2005 Annual Slurry Seal
Project, City Project No. 05-02. Total quantities for Schedules A and B were under
contract estimate which resulted in a credit to the contract amount. Total quantities
for Schedules C, D, E, G, H and I were more than the contract estimate which
resulted in an increase to the contract amount. Overall total for all increased and
decreased quantities resulted in an increase to the contract amount.
RECOMMENDATION:
1) Adopt Minute Order No. "APPROVING CONSTRUCTION
j CHANGE ORDER NO. TWO (2) TO AGREEMENT NO. 5053 WITH BOND
BLACKTOP, INC., IN THE AMOUNT OF $26,280.20 FOR A TOTAL
REVISED CONTRACT AMOUNT OF $766,454.77 FOR THE 2004/2005
ANNUAL SLURRY SEAL PROJECT, CITY PROJECT NO. 05-02."
2) Authorize the City Manager to execute all necessary documents.
i STAFF ANALYSIS:
i
The Public Works Department oversees the maintenance of the City's street
system. Each year, the Department assembles a capital project to continue its
slurry seal program on various city streets. This year's slurry seal program, was
scheduled to include streets within Section 1 (Bid Schedule A), streets within
Section 6 (Bid Schedule B), streets within Section 7 (Bid Schedule C), Alejo Road
and Avenida Caballeros within Section 14 (Bid Schedule D), streets within Section
27 (Bid Schedule E), streets within Section 34 (Bid Schedule F), streets within
Section 35 (Bid Schedule G), Sunrise Way from San Rafael Road to Vista Chino
and Ramon Road to East Palm Canyon Drive and from Sunrise Way to El Cielo
Road (Bid Schedule H), Ramon Road from Belardo Road to Indian Canyon Drive
FTEM NO. L1 Y
City Council Staff Report
September 7, 2005 - Page 2
CCO#2 for 2004/2005 Annual Slurry Seal
and from Sunrise Way to El Cielo Road (Bid Schedule 1), and new traffic striping
and markings on several major city streets (Bid Schedule J). Provided slurry seal
prices did not exceed the engineer's estimate, over 6,7000,000 square feet of city
streets were scheduled for a slurry seal this year. The budget, however, did not
allow for all of the Bid Schedules to be awarded and Schedule F (Section 34) was
not awarded by City Council. City Council awarded the slurry seal contract to Bond
Blacktop, Inc, on March 9, 2005.
All slurry street quantities were measured by both City Staff and the Contractor.
Final as-built quantities were more than the contract estimate.
An additional fifteen (15) working days were added to the contract time due to a
delay caused by the REAS aggregate supplier.
FISCAL IMPACT:
This project was budgeted as part of the 2004/2005 Capital Improvement Plan, with
$756,782.42 in Local Measure A Funds. The recommended Construction Change
Order No. Two (2) amount is $26,280.20. Sufficient funds are available in Local
Measure A account 134-4498-50100 (Slurry Seal Program).
David J. Barakian David H. Ready v
Director of Public Works/City Engineer City Manager
Attachments:
1. Minute Order
2. Construction Change Order
MINUTE ORDER NO.
APPROVING CONSTRUCTION CHANGE
ORDER NO. TWO (2) TO AGREEMENT NO.
5053 WITH BOND BLACKTOP, INC., IN THE
AMOUNT OF $26,280.20 FOR A TOTAL
REVISED CONTRACT AMOUNT OF
$766,454.77 FOR THE 2004/2005 ANNUAL
I
SLURRY SEAL PROJECT, CITY PROJECT
NO. 05-02.
I
I
I, James Thompson, City Clerk of the City of Palm Springs, California, hereby certify
that this Minute Order approving Construction Change Order No. Two (2) to
Agreement No. 5053 with Bond Blacktop, Inc., in the amount of $26,280.20 for a
total revised contract amount of$766,454.77 for the 2004/2005 Annual Slurry Seal
i Project, City Project No. 05-02, was adopted by the City Council of the City of Palm
Springs, California, in a meeting thereof held on the day of
2005.
i
James Thompson, City Clerk
CITY OF PALM SPRINGS
I
CONTRACT CHANGE ORDER
I
To: Bond Blacktop, Inc. Date: Auqust 29, 2005
P.O. Box 616 Project No.: C.P. 05-02
Union City, CA 94587 Project Name: 2004/2005 Annual Slurry
Seal
Change Order No.: Two (2)
Attn: Ed Dillon, President/Secretary Contract Purchase No.: 516353
Account Number(s): 134 - 4498 - 50100
Agr.#5053 M.O. #7343 Res. #
I
A. CHANGES IN WORK:
Increases and decreases to Contract quantity for the following Bid Schedules:
I Schedule A- Bid Items 2 and 3 Schedule B - Bid Item 1 Schedule C - Bid Item 1
Schedule D - Bid Item 1 Schedule E - Bid Item 2 Schedule G - Bid Item 1
Schedule H - Bid Item 1 Schedule I - Bid Item 2
B. CHANGES IN CONTRACT COST:
Increases and decreases to Contract quantity for the following Bid Schedules
Schedule A- Section 1
No. Description
2 Construction of Type II Slurry Seal, including mobilization,traffic control, removal and replacement
of reflectorized raised pavement markers and pavement markings, and all appurtenant work on
various City streets (as listed in the Appendix) within Section 1
(44,971) SF @ $0.09 $ (4,047.39)
3 Construction of Rubberized-Emulsion Aggregate Slurry seal, REAS (or FLEX SEAL) including
mobilization,traffic control, removal and replacement of reflectorized raised pavement markers and
pavement markings, and all appurtenant work on Racquet Club Road from Sunrise Way to Farrell
Drive and on Farrell Drive from Racquet Club Road to Vista Chino
2SF@ $0.155 $ .31
Schedule B - Section 6
No. Description
1 Installation of hot asphalt-rubber sealant material in designated pavement cracks, installation of
asphalt concrete in designated pavement cracks, and construction of Type II Slurry Seal, including
mobilization,traffic control, removal and replacement of reflectorized raised pavement markers and
pavement markings, and all appurtenant work on various City streets (as listed in the Appendix)
within Section 6
(31,769) SF @ $0.1215 $ (3,859.93)
Schedule C - Section 7
No. Description
1 Installation of hot asphalt-rubber sealant material in designated pavement cracks, installation of
asphalt concrete in designated pavement cracks, and construction of Type II Slurry Seal, including
mobilization,traffic control,removal and replacement of reflectorized raised pavement markers and
pavement markings, and all appurtenant work on various City streets (as listed in the Appendix)
within Section 7.
16,493 SF @ $0.104 $ 1,715.27
i
August 29, 2005
C.P. 05-02 2004 /2005 Annual Slurry Seal
Change Order No. Two (2)
Page 2 of 3
Continuing,
B. CHANGES IN CONTRACT COST:
Increases and decreases to Contract quantity for the following Bid Schedules:
Schedule D- Section 14
No. Description
Schedule D - Section 14
No. Description
1 Installation of hot asphalt-rubber sealant material in designated pavement cracks, installation of
asphalt concrete in designated pavement cracks, and construction of Rubberized-Emulsion
Aggregate Slurry seal, REAS (or FLEX SEAL) including mobilization, traffic control, removal and
replacement of reflectorized raised pavement markers and pavement markings,and all appurtenant
work on Alejo Road from Indian Canyon Drive to Sunrise Way and on Avenida Caballeros from
Ramon Road to Alejo Road
39,052 SF @ $0.1855 $ 7,244.15
Schedule E- Section 27
No. Description
2 Construction of Type II Slurry Seal, including mobilization,traffic control, removal and replacement
of reflectorized raised pavement markers and pavement markings, and all appurtenant work on
various City streets (as listed in the Appendix) within Section 27
12,900 SF @ $0.096 $ 1,238.40
Schedule G - Section 35
No. Description
1 Construction of Type II Slurry Seal, including mobilization,traffic control, removal and replacement
of reflectorized raised pavement markers and pavement markings, and all appurtenant work on
various City streets (as listed in the Appendix) within Section 35
5,473 SF @ $0.086 $ 470.68
' Schedule H -Various Segments on Sunrise Way
No. Description
1 Installation of hot asphalt-rubber sealant material in designated pavement cracks, installation of
asphalt concrete in designated pavement cracks, and construction of Rubberized-Emulsion
Aggregate Slurry seal, PEAS (or FLEX SEAL) including mobilization, traffic control, removal and
replacementof reflectorized raised pavement markers and pavement markings,and all appurtenant
work on Sunrise Way from San Rafael Road to Vista Chino and on Sunrise Way from Ramon Road
to East Palm Canyon
106,206 SF @ $0.1915 $ 20,338.45
Schedule I -Various Segments on Ramon Road
No. Description
2 Construction of Rubberized-Emulsion Aggregate Slurry seal, REAS (or FLEX SEAL) including
mobilization,traffic control,removal and replacement of reflectorized raised pavement markers and
pavement markings, and all appurtenant work on Ramon Road from Sunrise Way to El Cielo Road
and on Ramon Road from Belardo Road to Indian Canyon Drive
18,225 SF @ $0,1745 $ 3,180.26
TOTAL CHANGE ORDER $ 26,280.20
NOTE: No additional markup will be added to any items in this Contract Change Order.
All cost per each item are final.
August 29, 2005
C.P. 05-02 2004/2005 Annual Slurry Seal
Change Order No. Two (2)
Page 3 of 3
C. REASON FOR CHANGE:
Measurement of square foot quantity was verified by both the City Inspector and the Contractor and the
amount represents the increases and decreases for each bid schedule.
Additional eighteen(18)working days were approved.2 were weather related, 1 for additional quantities and
15 was for a delay caused by the contractor's aggregate supplier. Liquidated damages will be assessed to
the contractor for two (2) working days. All work was completed by July 8, 2005.
D. SOURCE OF FUNDS: 134 - 4498 - 50100 = $ 26,280.20
Summary of Costs Contract Time
Original Contract Amount: $ 728,174.57 Original Completion Date: June 7, 2005
This Change Order: $ 26,280.20 Days Added for this C.C.O.: 18
Previous Change Order(s): $ 12,000.00 Previous Days Added: 3
Revised Contract Amount: $ 766,454.77 Revised Completion Date: July 6, 2005
I have received a copy of this Change Order and the City Approval:
above AGREED PRICES are acceptable to the
contractor. Submitted By Date
Street Maintenance Manager
By Approved Bye Date
City Engineer
Title
Approved by Date
Date City Manager
Distribution:
Original Conformed Copies Conformed-File Copy
City Clerk (1) Engineering File (1)
Contractor (1) Engineering Field Inspector (1)
Engineering Field Supervisor (1)
Purchasing Agent (1)
Engineering Project Pay File (1)
Finance (1)