HomeMy WebLinkAbout9/7/2005 - STAFF REPORTS (30) u M ti cq</FORN�P City Council Staff Report DATE: September 7, 2005 CONSENT CALENDAR SUBJECT: AWARD TO G&M CONSTRUCTION, THE CONSTRUCTION CONTRACT FOR THE NON-REVENUE TERMINAL PARKING AT THE PALM SPRINGS INTERNATIONAL AIRPORT, CITY PROJECT NO. CP2004-07, IN THE AMOUNT OF $549,948 FROM: David H. Ready, City Manager BY: Department of Aviation SUMMARY That the City Council award to G&M Construction, the construction contract for the Non- Revenue Terminal Parking at the Palm Springs International Airport, City Project No. CP2004-07, in the amount of$549,948 as the lowest, responsive bidder. RECOMMENDATION: 1. Adopt Minute Order No. , awarding to G&M Construction, the construction contract for the NON-REVENUE TERMINAL PARKING, City Project No. CP2004-07, in the amount of $549,948; and 2. Authorize the City Manager to execute all the necessary documents in a form acceptable to the City Attorney. A STAFF ANALYSIS: The project for construction of Non-Revenue Terminal Parking was advertised July 28, 2005. The bids were due on August 19 2005. Staff solicited bids and two (2) bidders responded. The lowest responsive bid was G&M Construction at $549,948. The other bid received was from Matich Corporation in the amount of$756,756. After an extensive review of the bids, staff recommends that the City Council award to G&M Construction, the construction contract for the Non-Revenue Terminal Parking, City Project No. CP2004-07, in the amount of$549,948, and authorize the City Manager to execute all the necessary documents in a form acceptable to the City Attorney. Item No. 2 . V . City Council Staff Report (September 7, 2005) -- Page 2 (Non-Revenue Terminal Parking) (FISCAL IMPACT: The cost of construction will be funded from the Airport's general fund. Richard S. Walsh, A.A.E., Director of Aviation David H. Ready, Cify ,anager• Attachments: Minute Order Bid Tabulation MINUTE ORDER NO. AWARDING TO G&M CONSTRUCTION, THE CONSTRUCTION CONTRACT FOR THE NON-REVENUE TERMINAL PARKING, CITY PROJECT NO. CP2004-07, IN THE AMOUNT OF $549,948, AND AUTHORIZE THE CITY MANAGER TO EXECUTE ALL THE NECESSARY DOCUMENTS IN A FORM ACCEPTABLE TO THE CITY ATTORNEY I HEREBY CERTIFY that this Minute Order, awarding the construction contract to G&M Construction, 211 W. Mesquite Avenue Palm Springs, CA, for the NON- REVENUE TERMINAL PARKING, City Project No. CP2004-07, in the amount of $549,948, and authorizing the City Manager to execute all the necessary documents in a form acceptable to the City Attorney, was approved by the City Council of the City of Palm Springs, California, in a meeting thereof held on the 7th day of September, 2005. JAMES THOMPSON City Clerk TABULATION OF BID i PALM SPRINGS INTERNATIONAL AIRPORT PALM SPRINGS, CALIFORNIA August 19, 2005 E M P L O Y E E P A R K I N G L O T SCHEDULEI Including Demolition, Grading, Drainage, Curbs, and Gutter, Paving, Striping, Lighting, Signage and Landscaping Engineer's Estimate G &M Construction Matich Corporation -- -- --------- -- - - - ------------- - -- -- ---- -- - -- -- SCHEDULE I $580,000.00 549,948.00 756,756.00 Page 1 of 3 EMPLOYEE PARKING LOT - - - - SCHEDULE) - Including Demolition,Grading,Dminiage,Cut6s,and Gutter,Paving,Striping,: _ _G$ M COOStTUCffon 'M0tjC11'GiOtpofatFUfi - Lighting Aignage and Landscaping - h Item-No `- - -. D_escription__ ____ " __-Umtt " Est _Unit Cost " ___ Total-Cost" Unit_Coat i _-TotaP Cost P-100 Mobilization L.S. E 1 27,498-00 27,498.00 - 25,000-00 `. 25,000-00 P-140a Asphalt Pavement Removal Complete S.Y. 1,500 9.00 13,500.00 7.00 ; 10,500.00 P-140b Curb, Curb and Gutter Removal s L.F. 30 15.00 I 450.00 70.00 2,100.00 P-140c I Concrete Barrier Relocation Ea. 2 100.00 200.00 700.00 1,400.00 P-140d Asphalt Pavement Removal Partial(for Taper Joint) S.Y. _ 500 r 10.00 ; 5,000.00 14.001 7,000.00 P-151 Clearing and Grubbing L.S. 1 1,000.00 j 1,000.00 151,280 151,280.00 P-152 Unclassified Excavation I C.Y. 1,000 50.00 50,000.00 39.00 39,000.00 P-199 Excavation,Trenches, and Earthwork Protection - L.S. E 1 5,000.00 5,000.00 1.00 1.06 P-209 I Crushed Aggregate Base Course C.Y. i 450 50.00 x 22,500.00 I 54.00 24,300.00 P-217 Soil Sterilization S.Y. 4,000 .20 800.00 - .50E 2,000.00 ' P-401a Plant Mix Bituminous Pavement Ton 750 80.00 60,000.00 59.00 44,250.00 P-401b Bituminous Material (AR-8000) Ton 50 1 150.00 7,500.00 700.00 35,000,00 P-601 - Crack Seal Lb. 500 15.00 7,500.00 3.25 1,62500 P 602 Bituminous Prime Coat - Gal. - 1,300 10.00 13,000.00 2.50 3,250.00 - -- -� ------- '-------=--------- `------------ ---=----- ------ P-603a Bituminous Tack Coat - Gal. 100 ' 15.00 1,500.00 18.00 1,800.00 P-603b = Polymer Modified Fog Seal Gal. 500 j 5.00 2,500.00 9.50 4,750.00 P-610a Install A1-6 Vertical Curb L.F. 1,200 30.00 36,000.00 : 39,00 46,800.00 ---- ------------- ------ ---- -------_ P-610b - Install A2-6 Curb and Gutter L.F. 600 : 35.00 '. 21,000.00 36.00 21,600.00 P-610c Install Concrete Sidewalk with Handicap Ramp - S.Y. 80 : 50.00 4,000.00 : 100.00 8,000.00 ----------------- - ---"----------- ----------- - ---- --- -----= P-613a = Install New Roadway Sign Posts Ea. 5 200.00 1,000.00 155.00 775.00 P-613b Install New Roadway Sign Panels S.F. 25 40.00 : 1,000.00 25.00 625.00 E - P-620 Install Pavement Markings S.F. 2'000 2.50 - 5,000.00 2.50 5,000.00 D-701 Install 18" RCP, Class III L.F. 8 300.00 2,400.00 i 550.00 : 4,400.00 Page 2 of 3 ':-EMPLOYEE PARKING LOT- - - - - - - - - - - - - SCHEDULE L--Including Demolition,Grading;Drainage,Curbs,and Gutter,Paving,Striping, = G&M-Construction - Matich Corporation - Lightin ,Siyna9e_and Landscaping - - `, - - - -- ItemNo. - Description_. - - Unit Est - -Unit Cost _,_-Total Cost-- 'Umt.Cost TotarCost D-751 Install Curb Inlet C.P.S.Type A(700) Ea. 1 - 7,50D.00 : 7,500.00 15,000 00 15,000.00 It T-902 Dust Palliative Ac. - 2 2,000.00 4,000.00 1,800.00 3,600.00 LS-100 Landscape and Irrigation Complete L.S. T 1 55,000.00 55,000.00 88,000.00 88,000.00 L-101 Saw Cutting, Removal, Disposal and Replacement of ; L.F. 250 30.001 7,500.00 60.00 15,000.00 Pavement for Trench L-103 Trenching with CLSM Backfill to Finish Sub Grade in L.F. 1,200 ' 20.00 24,000.00 - 15.00 18,000.00 ; Pavement Areas L-104a Install Type "1" New 17" x 24" x 3 Deep Pre-Cast Ea. 8 { 1,000.00 ; 8,000.00 550.00 4,400.00 Concrete Pull Box with Steel Frame and Cover - -- ---- - -- - ------------------ ---- =-- - -- L-104b Install Type "2" New 12" x 22" x 24" Deep Pre-Cast : Ea. 1 1,000.00 1,000.00 500.00 - 500.00 Concrete Pull Box L-105a Install One%"PC Conduit L.F. 200 : 5.00 1,000.00E 12.00 2,400.00 i L-105b Install One'/,"EMT Conduit L.F. 100 10.00 1,000.00 13.00 1,300.00 L-105c all One 2" PVC Conduit L.F. 2,400 5.00 12,000.00 13.00 : 31,200.00 I L-105d Install One 4" PVC Conduit L.F. 100 6.00 600.00 20.00 2,000.00 L-106 Install 3#4 Wires L.F. 2,000 6.00 - 12,000.00 3.50 - 7,000.00 L-108a Install Concrete Base Extending 30"Above Grade Ea. 12 1,250.00 - 15,000.00 1,000.00 12,000.00 L-108b Install Concrete Base Flush with Grade with Pull Box Ea. 2 1,500.00 - 3,000.00 ; 400.00 800.00 and Surrounding Concrete =- - ------------------------------=----------------------------------- -=-----=- - --------= L-109a Install New Luminarie on Existing Type 15 Ea. 1 3,000.00 3,000.00 1,900—.00 - 1,900.00 L-109b Install Parking Lot Light Pole with 2 Luminaries 180 Ea. 12 3,000 36,000.00 3,800.00 : 45,600.00 ! Degrees Apart_on Elevated Concrete Base,_Type 28 i L-109c Install Roadway Light Pole with One Luminarie on 3,000.00 : 6,000.00 3,800.00 7,600.00 Flush Concrete Base with Pull Box and Surrounding Ea. 2 Concrete,Type 30 L-110 Install Wireless Lighted Crosswalk Warning System L.S. 1 55,000.00 55,000.00 55,000.00 - 55,000.00 - L-111 - Miscellaneous Electrical Work L.S. - 1 10,000.00 10,000.00 ' 5,000.00 5,000.00 TOTAL ESTIMATED COST—SCHEDULE I $549,948.00 $756,755.00 Page 3 of 3