Date: October 6, 2010
Subject: WASTEWATER
UPGRADE
Citv Council Staff Report
NEW BUSINESS
TREATMENT PLANT ELECTRICAL SYSTEM
From: David H. Ready, City Manager
Initiated by: Public Works and Engineering Department
SUMMARY
On April 15, 2009, the City Council authorized the Director of Public Works/City
Engineer to issue a Notice to Proceed for Veolia West Operating Services, Inc.,
("Veolia") for the design phase of the Wastewater Treatment Plant Electrical System
Upgrade, City Project No. 09-03. The design effort has been completed, and Veolia is
prepared to solicit construction bids on the City's behalf for the project. Given the
magnitude of the cost of this project (estimated at $5.8 Million), staff is recommending
that the City Council confirm its intention to fund this project.
RECOMMENDATION:
1) Authorize Veolia to solicit bids for the Wastewater Treatment Plant Electrical
System Upgrade, City Project No. 09-03; and/or
2) Provide direction to staff as appropriate.
STAFF ANALYSIS:
The City and Veolia continue to coordinate on various capital improvement projects at
the City's Wastewater Treatment Plant (WWTP). The WWTP was initially built in the
1950's with several upgrades during the 1980's. The electrical system, including the
main power feed, motor control centers, and other components are 40 or more years
old and have met their life expectancy. Upgrading the existing electrical system is the
most critical and highest priority project of the WWTP Capital Improvement Plan (CIP).
Since Council's authorization to move forward with the design phase of this project,
Veolia and its consultants have coordinated this very complex project, where the entire
WWTP must continue to operate as certain portions of the existing electrical
City Council Staff Report
October 6, 2010 - Page 2
WWTP Electrical System Upgrade
infrastructure is taken offline and replaced with a new system. In the end, an entirely
new electrical system with complete back-up will be installed.
Ordinarily, in accordance with Section 5.3 "Capital Projects" of the agreement between
the City and Veolia related to operation and maintenance of the WWTP, Veolia is
entitled to solicit construction bids and propose on any WWTP capital project. Seeking
the City Council's approval in advance to solicit bids is not required. However, given
recent Council action to defer an increase to sewer service charges to fund the WWTP
20-year CIP, staff recommended to Veolia that the City Council confirm their intention to
fund the electrical system upgrade given the estimated cost of the project of $5.8
Million.
Veolia has submitted a construction estimate for this project, which is outlined as
follows:
1. Demolition, Site Work and Mechanical:
$858,769
2. Electrical:
$4,278,375
3. PLC Equipment:
$51,514
4. SCE Costs:
$67,743
5. Landscaping Repairs:
$57,843
6. Professional Construction Services:
$150,855
7. Veolia Integrated/Automated Services:
$33,750
8. Veolia Construction Management Services:
$254,793
9. Veolia General Liability Insurance:
$50,460
Total:
$5,804,102
The preliminary estimate for this project, as reported to the Council earlier this year as
part of its review and approval of the WWTP 20-year CIP, was $3.6 Million. The
increased final estimate is a direct result of the complex challenges of phasing the
construction of this project in a way where the WWTP remains in operation while
different segments of the WWTP electrical system are taken offline and replaced.
Items 1 and 2 will be the scope of work solicited for bids by Veolia, representing over $5
Million in estimated costs. Given the size of this project, it is important to ensure the
City is committed to funding this project to avoid obtaining construction bids and bonds
from contractors if the project were not to be awarded.
The City issued a Notice Inviting Statements of Qualifications ("SOQ") on March 24,
2009, on behalf of Veolia, requesting qualifications from contractors in the following
trades: Scaffolding, Fencing, Earthwork, Paving, Demolition, Concrete, Metals,
Coatings, Painting, Mechanical, HVAC and Electrical. To ensure a far-reaching and
broad solicitation, Notices for the SOQ were published in the following newspapers:
The Desert Sun, The Orange County Register, the Press Enterprise and San Diego
Union -Tribune. The deadline to submit qualifications was May 8, 2009, and at that time
City Council Staff Report
October 6, 2010 - Page 3
WWTP Electrical System Upgrade
29 firms submitted qualifications. After reviewing the submitted qualifications, 26 of the
firms were pre -qualified for future wastewater capital projects.
If Council approves bidding this project, Veolia will solicit bids from its prequalified
contractors. Given the complexity of this project, and the safety risks inherent at this
type of facility, a general solicitation of bids from unqualified contractors is not
recommended. However, in the event the bids received by Veolia from its prequalified
contractors are unacceptable, staff can return to Council with several options for
consideration, including re -issuance of a bidder prequalification process.
On July 7, 2010, the City Council did not approve the recommended increase to sewer
service charges necessary to fund the WWTP 20-year CIP. However, despite Council's
prior action, staff recommends that the Council fund this project as it is the most critical
of all the WWTP capital projects for the following reasons:
• The existing standby generator is not capable of operating the entire WWTP in the
event of a power failure;
• Not all WWTP equipment is connected to a standby generator and must be
connected to a redundant power source to allow plant operation to continue in the
event of a power failure;
• The aging main switch gear has no backup in the event of the failure of one or more
switches fusing open or closed;
• The existing electrical system is undersized, at 1600 amps/480 volts the WWTP
requires 4000 amps/480 volts to efficiently operate all existing and future WWTP
equipment
If a complete power failure were to occur today, the WWTP would not be able to
operate which may cause sanitary sewer overflows.
FISCAL IMPACT:
As of June 30, 2010, the Wastewater Fund carried an adjusted cash balance of
$13,513,224.05. Of this total, $2,923,717.57 was reserved for encumbrances (open
Purchase Orders) and another $6,410,456.48 was reserved for continuing
appropriations (funds budgeted for future use), leaving an unrestricted cash balance
("reserve") of $4,179,050.
Previously, Council budgeted $1,000,000 for the digester gas treatment system, and
$3,000,000 for the renewable energy project (fuel cell) at the WWTP. As these projects
are now considered a lower priority, it will be staff's recommendation that the
$4,000,000 budgeted for that project be reassigned to the electrical system upgrade.
The Wastewater Fund is also carrying nearly $2,000,000 in an unscheduled capital
project account to cover unexpected or emergency work. It will be staff's
recommendation that these funds be used to cover the balance of the costs for the
City Council Staff Report
October 6, 2010 - Page 4
WWTP Electrical System Upgrade
electrical system upgrade with the understanding that there will be no funds budgeted
for unexpected or emergency work.
The $6,000,000 currently budgeted for the fuel cell, renewable energy project, and
unscheduled capital projects represented most of the $6,410,456.48 that was reserved
for future projects. Any future project will need to be funded from unrestricted cash
balance ("reserves"). For the 2009/2010 fiscal year ending June 30, 2010, the
Wastewater Fund had the following revenue and expenditures:
Revenue
Interest Income:
$234,436.53
Unrealized Loss:
($26,687.83)
Sewer Service Charges:
$5,411,063.81
Sewer Connection Fees-
$499,092.35
Sewer Street Maint. Charge: $8,646.00
Miscellaneous Receipts-
$10,025.00
Total Revenue
$6,136,575.86
Expenses
Contractual Services: $3,308,122.70
Capital Projects:
$1,681,560.93
Insurance:
$670,925.00
Electricity:
$213,087.44
Vehicle Repair/Maint.:
$111,590,00
Salary Charges-
$36,126.60
Other/Misc.-
$14,834.37
Total Expenses
$6,036,247.04
"Other/Mist." expenses include- worker's compensation charges, office supplies,
dues/subscriptions, auditing services, and the grease trap subsidy program. Capital
Projects expenses were costs incurred related to previously approved and budgeted
WWTP capital projects (i.e. Digester No. 1 Rehabilitation, Storm Drain Line 22, Gravity
Thickener Upgrade, etc.).
The Wastewater Fund ended the 2009/2010 fiscal year with an approximate balance
(surplus) of $100,000. As previously indicated, the Wastewater Fund carried an
unrestricted cash balance ("reserve") of $4,179,050 as of June 30, 2010, which is
insufficient to cover any future WWTP capital projects, and should be reserved for
unforeseen or emergency use.
SUBMITTED:
Prepared by:
/ U � 11"
4&t.7
Marcus L. Fuller
Assistant Director of Public Works
Approved by:
Thomas J. Wilson, Asst. City Manager
Recommended by:
David J. Barakian
Director of Public Works/City Engineer
David H. Ready, nager
T