HomeMy WebLinkAbout9/21/2005 - STAFF REPORTS (9) OF PALM B
PP
City Council Staff Report
DATE: September 21, 2005 CONSENT CALENDAR
SUBJECT: VISITORS' CENTER LANDSCAPING AND SEATING AREA
FROM: David H. Ready, City Manager
BY: Public Works & Engineering Department and
Community & Economic Development Department
SUMMARY
Award of this contractwill allow for construction of the landscaping and irrigation as
well as the concrete work, stone paving, seat walls and lighting at the Palm Springs
Visitors' Center.
RECOMMENDATION:
1) Adopt Minute Order No. "APPROVING THE PLANS AND
SPECIFICATIONS FOR THE VISITORS' CENTER LANDSCAPING, CITY
PROJECT NO. 05-05."
2) Adopt Minute Order No. "APPROVING AGREEMENT NO.
WITH AMERICA WEST LANDSCAPING, INCORPORATED IN THE
AMOUNT OF$124,858.05 FOR THE VISITORS' CENTER LANDSCAPING,
CITY PROJECT NO. 05-05."
3) Authorize the City Manager to execute all necessary documents.
STAFF ANALYSIS:
In early 2004 as the City was wrapping up the remodeling project that converted the
recently acquired historic Albert Frey-designed Tramway Gas Station from its prior
use as an art gallery to become the City's Visitors' Center, the local Rotary Clubs
proposed financial assistance to complete the construction of an outdoor
amphitheater-style seating area and related landscaping enhancements at the
Center. Rotary's proposed $20,000 financial assistance for the terraced seating
area and landscaping installations was initiated as its Centennial Year community
service project to be celebrated during the 2004-05 fiscal year. Item No. 2 . 1�C
.
City Council Staff Report
September 21,2005-Page 2
Visitors' Center Landscaping
The seating area and landscaping, along with several other improvements, were
previously deleted from the original remodeling project by the City Council due to
budget constraints. As a result, while these elements were included in the original
concept plans for the Center, they had never progressed to the stage of construction
plans and specifications forthe eventual public bidding for construction. In addition,
the various review bodies required by City procedures had not fully considered these
elements of the original concept plan. As a City-owned facility with Class I historic
site status, the review bodies included a City Council subcommittee comprised of
Mayor Oden and Council Member Mills, the Historic Site Preservation Board
(HSPB), the Design Review Committee, Planning Commission and ultimately the full
City Council.
In addition to the extensive review process, the project was challenged by limited
financial resources, making the Rotary contribution especially important in bringing
the project to fruition. The initial "guesstimate" of $20,000 for the amphitheater
seating area did not include architectural design fees orfull landscaping costs so the
need for additional funds was always anticipated for completion of the project. TKD
Associates, Inc. was enlisted on a volunteer basis to prepare the conceptual plans
needed to begin the review process simultaneously with City staff efforts to identify
additional funding sources for this and other improvement projects desired for the
Center. In mid-2004 it was acknowledged that while the schedule would be
aggressive, all efforts should be targeted toward completion of the project and a
"ribbon cutting" event to be held in February 2005 in conjunction with Rotary's
Centennial Anniversary.
During September 2004, TKD continued working on the conceptual plans and staff
pursued the installation of landscaping around the perimeter wall utilizing the
previous irrigation system from the former art gallery. During its efforts, staff
discovered that the previous irrigation system was no longer functional and also
lacked an appropriate water source to serve this area and the eventual landscaping
to be installed throughout the site. As a result, the perimeter landscaping was
folded into the seating area project for an integrated approach to the entire site's
landscaping needs.
The HSPB reviewed the project on October 12, 2004 and recommended several
revisions in the conceptual plans. A similar process was completed with the Design
Review Board on October 25. A follow-up meeting with the Council sub-committee
was required to address some of the issues raised by the Design Review Board.
The Planning Commission approved the revised conceptual plan on November 10
and on December 14, 2004 the HSPB was updated on the revisions made by the
other groups. Rotary was kept appraised of these efforts and the increasing
certainty that the project would not be completed by the end of February 2005 as
previously hoped. The goal was revised to complete the project prior to the
completion of Rotary's year-long anniversary celebration, which would mean
installation no later than June 2005. Staff proceeded with drafting a formal contract
with TKD Associates to prepare the required plans and specifications forbidding out
the eventual construction and installation of the seating area and landscaping under
City Council Staff Report
September 21, 2005- Page 3
Visitors' Center Landscaping
the assumption that the City Council would approve the conceptual plan, which it
did, on January 5, 2005. All parties executed the $7,500 contract with TKD in mid,-
January.
During the preparation of the plans and specifications several issues arose that had
to be addressed, including ADA concerns about wheelchair access to the seating
area, pre-existing utility locations for serving the expanded electrical and water
requirements of the improvements and other miscellaneous clarifications needed by
our Engineering Department to eventually publicly bid the project. During this time
staff continued its efforts to obtain additional funding for both this project and future
improvements at the Center. As TKD Associates, Inc. was wrapping up their work
on the Plans and Specifications for bidding the project, they calculated a probable
construction budget forthe project of$40,300. Therefore, the project cost, including
design fees was now estimated at approximately $48,000. Staff was successful in
obtaining funds from a new assessment district tied to the development of the
Mountain Gate II subdivision by Century Homes with $150,000 of those funds
earmarked for this project and future anticipated enhancement projects to be
determined through a separate process. With the additional Century funding in
hand, the decision was made to proceed with bidding out the project with an
anticipated groundbreaking ceremony in June 2005.
The project was initially advertised for bids in May 2005. However at the May 31,
2005 bid opening, no bids were received. The common response from potential
bidders was that the project was either too small or that they were just too busy with
other construction projects around the Valley to bid on the project. With that
information, staff consulted with Rotary and accepted Rotary's decision to postpone
the groundbreaking ceremony until some time in the future when it would be more
likely that press coverage would be forthcoming for the project's implementation,
including an on-site work effort by Rotary members in the planting of the new
landscaping, and the eventual ribbon cutting for the completed facility.
In June and early July Engineering and Economic Development staff contacted
several contractors in an attempt to solicit proposals for the project, which it is
generally allowed to do in the instance of no bids, and was successful in obtaining
two proposals. Unfortunately, both proposals were significantly higher than
anticipated with an average cost estimate of approximately $127,000.
In comparing the original construction cost estimate of $40,300 with the two
proposals of$101,145 and$152,280,the largest single difference was the estimated
cost of the concrete seat wall, flatwork and flagstone for the seating area. The
original estimate for these elements was $12,613 while the average proposal cost
was $63,218. Other significant differences were original estimates of$18,581 for
landscaping versus average proposal costs of$37,421, $2,610 for irrigation versus
$14,505; and $2,800 for lighting versus $8,618.
City Council Staff Report
September 21,2005-Page 4
Visitors'Center Landscaping
Given that disappointing news, it was eventually decided to re-bid the project
simultaneously with the City's new entry sign to be located just north of the Visitor's
Center in the hope that a more acceptable bid would be forthcoming from an
expanded list of potential contractors, as well as the potential that aggregating the
two projects could potentially create some economy of scale. Therefore, on August
9 and 16, 2005 the project was re-advertised for bids and on August 30, 2005 the
Procurement & Contracting Manager received the following construction bid: 1)
America West Landscaping, Incorporated, Downey, CA in the amount of
$124,858.05. This company is a corporation with the following officers: Duane
Groen, President, Humberto Raigoza, Vice President. Although invited to bid,
neither of the two firms previously submitting informal proposals responded.
As previously indicated this projectwas initially estimated at less than$100,000 and
therefore was not brought to Council for approval of the plans and specifications.
Under the terms of the City's Procurement Ordinance, when the actual bid amount
exceeds $105,000 the contract is required to be re-bid as a formal contract. In this
case, all advertising for this contract, with the exception of going to Council for
approval of the plans and specifications, was done the second time as if this was a
formal contract bid. This was not because Staff felt the landscape architect's
estimate was necessarily incorrect and that the bid would be more than $100,000,
but to get the bid as much exposure as possible. Therefore, upon the advice of the
City Attorney and the Procurement&Contracting Manager, Council also is required
to approve the Minute Order approving the plans and specifications concurrently
with the bid award.
FISCAL IMPACT: "
Funds for this project are available in the VisitorInformation Center- Building and
Equipment Account which has a current balance of$149,802. Combined with the
$20,000 contribution from the local Rotary Clubs, this would leave a balance of
approximately $45,000 for any future site improvements or other incidental costs.
�Aj—
David J. Barakian, Director of Public Works/ ity Engineer
John Ra&�direct of Community & EconomicIbevelopment
David H. Ready, City Man er ,.'
Attachments:
1. Minute Order - Approving Plans & Specifications
2. Minute Order -Awarding Bid
MINUTE ORDER NO.
APPROVING THE PLANS AND
SPECIFICATIONS FOR THE VISITORS'
CENTER LANDSCAPING, CITY PROJECT NO.
05-05.
I, James Thompson, City Clerk of the City of Palm Springs, California, hereby certify
that this Minute Order approving the plans and specifications forthe Visitors'Center
Landscaping, City Project no. 05-05, was adopted by the City Council of the City
of Palm Springs, California, in a meeting thereof held on the day
of ,2005.
James Thompson, City Clerk
MINUTE ORDER NO.
APPROVING AGREEMENT NO. WITH
AMERICA WEST LANDSCAPING,
INCORPORATED IN THE AMOUNT OF
$124,858.08 FOR THE VISITORS' CENTER
LANDSCAPING, CITY PROJECT NO. 05-05.
I, James Thompson, City Clerkof the Cityof Palm Springs, California, hereby certify
that this Minute Order approving Agreement No. With America West
Landscaping, Incorporated in the amount of $124,858.08 for the Visitors' Center
Landscaping, City Project No. 05-05, was adopted by the City Council of the City of
Palm Springs, California, in a meeting thereof held on the day of
12005.
James Thompson, City Clerk