HomeMy WebLinkAbout12/14/2005 - STAFF REPORTS (8) ;ot P ALM Sp4 �2 u in O n.aereo'9'P N City Council Staff Report DATE: December 14, 2005 CONSENT AGENDA CONSTRUCTION AND REHABILITATION OF THE COMMUTER TERMINAL APRON - CHANGE ORDER NO. 2 TO AGREEMENT NO. 5094 - DEMOLITION OF THE EASTERN COMMUTER HOLDROOM, WALKWAYS AND PAVEMENTS, CP 2005-11 (AIP 3-06-0181-39) FROM: David H. Ready, City Manager BY: Department of Aviation SUMMARY Change Order No.2 provides for demolition of the existing eastern commuter holdroom, walkways and pavements in preparation for the rehabilitation of the commuter apron and the construction of the new regional jet terminal. This demolition is required before construction of the new terminal and apron can begin. This change order falls within the work covered under AIP Grant No. 39. However, the change order amount of$277,974 required to effect this change is beyond the value of the grant. The City is authorized to overspend the value of AIP 39 up to 15% of the grant amount after having first funded the changes. Therefore, a budget amendment of $277,974 representing the total amount of this change order is requested to be transferred from the Airport Fund's Retained Earnings Account to Airport account No. 56-062 to allow the grant overspend to occur. AIP Grant No. 39 is a 95% grant, requiring a 5% local match, or $13,898.70. When FAA reimburses 95% of this change order ($264,075.30) those funds will then be transferred back into the Airport Fund's Retained Earnings Account. RECOMMENDATION: 1. Approve Minute Order No. , authorizing Change Order No. 2 to Agreement No. 5094 with AMD Construction Inc. to Provide Demolition Work on The Construction and Rehabilitation of The Commuter Terminal Apron project in the amount of$277,974. 2. Approve Resolution No. "A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PALM SPRINGS, CALIFORNIA, AMENDING THE BUDGET FOR FISCAL YEAR 2005-2006." ITEM NO. 2. E. City Council Staff Report (December 14, 2005)-- Page 2 Construction of Commuter Apron —Change Order STAFF ANALYSIS: 'This action will allow for the execution of Change Order No. 2 which will demolish and emove the existing eastern commuter holdroom, walkways and pavements in preparation for the construction of the new regional jet terminal and apron. This work was originally a portion of the building construction package for the new regional jet terminal. However, scheduling and funding source changes have allowed this portion of the work to be accomplished under AIP grant No. 39. AIP Grant No. 39 amount is $2,259,100. This total amount has been encumbered for the existing contractor to complete the scope of work in the original contract. Change Order No. 2 in the amount of $277,974 represents an overrun to the grant, requiring the Airport to overspend AIP No. 39 by 12.3%. The FAA requires that the Sponsor first fund the overspent portion of the grant and then request the 95% reimbursement through a final pay request. At that point in time, the FAA will evaluate the request and then allocate funding when available. FAA advised this may take three to six months. Therefore, a budget adjustment is required to transfer $277,974 into the Airport's AIP-39 Development account from the Airport's Retained Earnings Account to fund this change order. The Airport will receive a 95% reimbursement from the FAA, funding only 5% with local matching funds or $13,898.70. Upon receiving the 95% reimbursement from the FAA, the entire amount will be transferred back into the Airport's Retained Earnings Account. The FAA Western Region has historically funded grant overruns where in the sponsor has demonstrated a need. Working with our Regional FAA representatives, the Airport has made a convincing argument and upon presentation of the appropriate documentation, our funding request should be approved. The Airport Commission has previously approved this city project and has been continuously updated on its progress. However, the Airport Commission does not typically recommend to approve change orders related to capital improvement projects. FISCAL IMPACT: There are sufficient funds in the Airport Fund's Retain Earnings Account 29302 to cover this transfer. / r j Graves, Finance Director C City Council Staff Report (December 14, 2005) -- Page 3 Construction of Commuter Apron—Change Order Richard S. Walsh, A.A.F;-•D[ ector of Aviation Tr,( Butzlaff As a is ant City Manager III David H. Ready, Cit ager Attachment: Change Order No. 2 MINUTE ORDER NO. AUTHORIZING CHANGE ORDER NO. 2 TO AGREEMENT NO. A-5094 WITH AMD CONSTRUCTION, INC. TO PROVIDE DEMOLITION WORK THE ON THE CONSTRUCTION AND REHABILITATION OF THE COMMUTER TERMINAL APRON PROJECT IN THE AMOUNT OF $277,974. I HEREBY CERTIFY that this Minute Order, authorizing Change Order No. 2 to Agreement No. A-5094 with AMD Construction, Inc. to Provide Demolition Work on the Construction and Rehabilitation of The Commuter Terminal Apron Project in the amount of$277,974 was approved by the City Council of the City of Palm Springs, California, in a meeting thereof held on the 14th day of December, 2005. JAMES THOMPSON City Clerk RESOLUTION NO. A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PALM SPRINGS, CALIFORNIA, AMENDING THE BUDGET FOR FISCAL YEAR 2005-2006 WHEREAS, Resolution 21283 approving the budget for the fiscal year 2005-06 was adopted on June 8, 2005; and WHEREAS the City Manager has recommended, and the City Council desires to approve, certain amendments to said budget. THE CITY COUNCIL OF THE CITY OF PALM SPRINGS DOES HEREBY RESOLVE AS FOLLOWS: SECTION 1. ADDITIONS Fund Activity Account Amount 415 Airport 6400 Airport 56-XXX AIP 39 $277'974 Development Purpose: To amend FY 2005-06 budget SECTION 2. SOURCE Fund Activit Account Amount 415 Airport Retained Earnings 29302 $277,974 ADOPTED THIS 14th day of December 2005. David H. Ready, City Manager ATTEST: James Thompson, City Clerk Resolution No. Page 2 CERTIFICATION STATE OF CALIFORNIA ) COUNTY OF RIVERSIDE ) ss. CITY OF PALM SPRINGS ) I, JAMES THOMPSON, City Clerk of the City of Palm Springs, hereby certify that Resolution No. is a full, true and correct copy, and was duly adopted at a regular meeting of the City Council of the City of Palm Springs on December 14, 2005, by the following vote: AYES: NOES: ABSENT: ABSTAIN: James Thompson, City Clerk City of Palm Springs, California CITY OF PALM SPRINGS SECURITY CHECKPOINT PHASE III CHANGE ORDER To: AMD Construction Group, Inc. Date: 14 December 2005 1403 N. Batavia, Suite 101 Project No. CP05-01 Orange, CA 92867 Project Name: Expansion/Holdroom-Security Checkpoint Phase III-Construction Change Order No. 2 Contract Purchase No. A-5094 Attn: Mr. Ali F. Navi, President Account No. Description of Change: This change order confirms the additional construction work needed for demolition existing hold room and surrounding asphalt and courtyard. (See attached'Exhibit A'for specific additional scope of work description and Exhibit 8 for unit cost breakout): Summary of Cost/Time Original Contract Price $2,780,000.00 Total of all Previous Change Orders $ 7,109.70 Total of this Change Order $ 277,794.00 Total Contract Price $3,064,903.70 This Change Order(increases) (decreases) (unchanged)the contract time by a5 working days. I have received a copy of this Change Order Construction Manager: and the above AGREED PRICES are acceptable to the contractor Approval: Date: Parsons Aviation Department Approval: By: _ Reviewed By: Date Assistant Aviation Director Title: . Approved by: Date: Date: Aviation Director City Approval: Date: City Clerk Date: City Manager Distribution: Original Conformed Copies Conformed - File Copy City Clerk (1) Aviation Director (1) Contractor (1) Procurement& Contracting (1) Finance (1) Attachments: 1. Exhibit A—Scope of Work Parsons (1) 2. Exhibit B—Cost EXHIBIT A Change Order No. 2—Scope of Work Description of Change: This change order is in conformance with existing contract documents specifically Section 40 of the Contract documents and confirms the additional construction work needed by the owner. (Additional scope of work): A. COMMUTER HOLD ROOM DEMOLITION—Demolish and Dispose of Commuter Hold Room Building (Gates 17A, 17B, 18A, 18B, 19A, 19B) and Adjacent Gate(s) 14, 15A, 15B, 16A, 16B, Areas, Walkways and Landscape complete as shown on the plan or as directed by the engineer including, but not limited to: All structures, roofs, canopies, slabs, sidewalks, walls, glass walls, retaining walls, stairs, ramps, furnishings, systems (HVAC and HVAC controls, water, fire sprinkler, electrical, phones, pay phones, public address, Flight Information Display, Security Access Control, CCTV, airline data), curb and gutters, irrigation, landscaping and trees. Notes: Salvage Items: box (and/or palletize) and deliver to airport maintenance)— 1. Signs—Interior and Exterior(Gates, Directional, Exits and Clock) 2. Lights and Speakers—Ceiling Cans Lights (w/bulbs) and Ceiling Speakers 3. HVAC Registers 4. Door Panic Hardware complete 5. "Microlite" Light Control System components 6. Fire Sprinkler Valve Assembly/Controls 7. Sliding Doors and Frame 8. Palm Trees (all 10' and taller)— Dig out, haul to storage and plant(irrigation by other) a) Provide alternative costs assessment to replace instead of haul and store. Systems: (allowances for system disconnects)— 1. Plumbing (domestic and fire)disconnect and cap, allowance 2. Electrical Power—disconnect and cable, allowance 3. Electrical Low Voltage, Misc. Data, Public Address and Communication—allowance to disconnect and reprogram 4. HVAC—allowance to disconnect and reprogram Siemens system, use airport vendor 5. Fire Sprinkler System—allowance to disconnect and reprogram Simplex System, use airport vendor 6. CCTV, Security Access Control and Flight Information Display Systems—allowance to disconnect, reprogram and salvage equipment, use airport vendor 7. Gate 2 (Remote) Microwave Transmitter—relocate from canopy to Generator Bldg, roof, use airport vendor Plans,Specifications and References—The attached plans and specifications and references are a part of this Change Order.The references (plans and specifications marked reference only) shall be used in pricing and work to further clarify the demolition scope of work.All conditions, requirements, plans and specifications of the original contract shall apply. B. ASPHALT CONCRETE PAVEMENT REMOVAL—Demolish and Dispose of Asphalt Concrete Pavement for construction of New Regional Jet Terminal.All work shall be accomplished in accordance with the plans and specifications. P-140 PAVEMENT REMOVAL specification shall apply. C. SCHEDULE—Provide a schedule of events sufficiently detailed to track progress. Submit the initial schedule with Exhibit B for review and agreement.The schedule will reflect a start date NLT 3 January 2006 with completion NLT 31 January 2006. Z—�XFdBiT— EXHIBIT B UNIT PRICE/QUANTITY CHANGE ORDER NO.2 Central City Item No Description Quantity UOM Unit Price Amount 1 Mobilization AMD 1 LS 26,962.00 26,962.00 2 Asphalt and PCC Removal(Complete) 4000 SY 12.00 3 Structure(s) Demolition-CHR, Gates and Walkways 1 LS 154,950.00 154,950.00 4 Site Preparation and Earthwork for Structures and Walkways 1000 CY 20.00 20,000.00 5 Dry Well Removal and Sub grade Reconstruction 1 LS 7,500.00 7,500.00 6 Disconnect Fire Sprinkler System Allowance T&M 5,000.00 5,000.00 7 Disconnect Low Voltage, Misc. Data, Public Address and Communication Allowance T&M 5,000.00 5,000.00 8 Disconnect CCTV, SACS and PIDS Allowance T&M 10,000.00 10,000.00 9 Gate 2(Remote) Microwave Transmitter relocation Allowance T&M 8,000.00 8,000.00 10 Relocate Palm Trees 15 Ea 2,500.00 33,000 00 COST $270,412 AMD MARK-UP 15% $40,562 Contengency $0 TOTAL CHANGE ORDER COST with tree relocation $310,974 Tl� TOTAL CHANGE ORDER COST without tree relocation $277,974 D3 Signature: 1 TO 11/28/2005 16:46 9513432010 CENTRAL CITY ENTERPR PAGE 02 TvIXOPO AL 1576 CENTRAL CITY ENTERPRISES raga�orz C'antrdctOrs License 0661929 5935 Rickenhacker Avenue RIVERSIDE, CALIFORNIA 92504 (951) 343.2000 FAX (951) 343.2010 pNONE bFlTa '- -C`: AMD CONSTRUCTION GROUP 714-771-2924 11/28/2005 1403 N.BATAVIA JOB NA i acnTION SUITE 101 PALM SPRINGS INTERNATIONAL AIRPORT ORANGE CA 92867 COMPUTER HOLDROOM DEMO 3400 TAHQUITZ CANYON WAY JOB Nl1MBt5n �, JOB PHONE a'hereby'sudwllt�p�dihoatmns:an�'eanmAtes,lar REVISED 11.28-05 ABOVE JOB BID PER PLANS BY GENSLER,DATE"-05,SHEETS A A01.00A,L01.03,SCOPE OF WORK AS FOLLOWS: (CHANGE ORDER 1): 1.REMOVE EXISTING COMPUTER HOLD ROOM MEASURING APPROXIMATELY 2000 SQ.FT.FOOTINGS UP TO 3' THICK- 2,REMOVE EXiSTTNG ASPHALT PAVING MEASURING APPROXIMATELY 12,200 SQ.FT,UP TO I'THICK. 3,REMOVE EXITING CANOPY MEASURING APPROXIMATELY 200'X 16% 4,REMOVE EXISTING CONCRETE WALKWAY MEASURING APPROXIMATELY 200'X 16'X UP TO 6"THICK- 5-DEMOLISH EXISTING COURTYARD PAVING. 6.DEMOLISH EXISTING STEEL AND GLASS GUARD RAIL. MOBILIZATION:$7,500.00INCLUDES(1)MOVE-ON. ASPHALT AND PCC REMOVAL=$52,950.00 STRUCTURE DEMO AND WALKWAY=$85,000A0 DEMOLISH PALM TREES(17)_$9,500,00 PRICE=$154,950-00 NOW:PRICE IS BASED ON ONE MOVE-ON. e Propose hereby to furnish material and labor—complete in accardancB with the above specification,(or the sum of: _ onf'd dollars($ Coned P ment to be made as fallow$. VERY 30 DAYS PERCENTAGE COMPLETE- RETENTION TO DE PAID WITHIN 30 DAYS OF COMPLETION OF EMOLITION, II material IS guamnWad to be as sedWiad.NI work to be ocrnpleled 1n a p/ofd5aranal annar E301 rg to Standard practices.Any aNarelion or deviation from above wi ciBoa. AVlhofized involving extra costs will hU exaculed only upon wrtaen orders,and will become an extra 51goature alga over and above the es11111a1a.NI agreements ocnbrigent opon slnhea accidents or Mayo heyond our mnlrot.Oww to carry fire,tornado,and other neo,asoly insurance.Our Note:This proposal may ba rkory are lull" omcsd by Workers Cddmaneation insurance. withdrawn by us if not accepted within 5 days. l'.e('.11ance Of P(T POSPal—^The above prices.epeclllcavons arld Cot Itions am Satisfactory and ark herahy accepted.You Are sulhpdzod to do tntr work Signature as vt0led.Payment will be made es outlined above. 5ignature Da �=Klgd�r7--t3