c4<IF0IRt CITY COUNCIL STAFF REPORT
DATE: January 4, 2006 Unfinished Business
SUBJECT: CONVENTION CENTER — CONTINGENCY ALLOCATION
1=ROM: David H. Ready, City Manager
BY: City Manager - Convention Center
SUMMARY
RECOMMENDATION: Staff requests that City Council determine the final allocation of
the remaining Convention Center Contingency dollars.
1. Provide direction to staff as to which capital improvements the remaining
Convention Center Contingency dollars are to be applied to.
2. If the choice is to proceed with the Kitchen Build-out then; Adopt Minute Order
No. , approving the Plans and Specifications for the Convention Center
Kitchen Build-out Project and authorize the immediate bid of the project.
STAFF ANALYSIS:
City Council previously allocated Convention Center Contingency dollars to the
following Capital Projects:
1. Replace Old Chiller $301,171
2. Re-roof Exhibit Hall $579,900
3. Amado Cross Gutter $ 33,892
4. SE Lawn ABC Enclosure $ 23,000
5. Triangle Property Cleanup $ 29,350
Projects 1 & 2 above are under way, projects 3, 4 &5 have been completed.
The Convention Center Contingency Fund currently has an unencumbered/non-
reserved balance of $374,799. Attached is an accounting of the Palm Springs
Convention Center Project Remaining Funds which details the $374,799. In addition to
Convention Center—Contengency Allocation
Item No. 4. /�" .
City Council Staff Report
January 4, 2005 -- Page 2
Convention Center—Contingency Allocation
this remaining balance there are reserves of $197,947 for Pre-opening Marketing and
$200,070 for FF&E.
Attached is the Convention Center's Wish List for expenditure of Contingency dollars.
'The list has been modified to indicate a new Expansion Enhancement Project No. 3a of
Triangle Interim Improvements.
Staff seeks City Council direction on how to spend the remaining Contingency dollars. A
few limitations to the decision making process:
1. All Bond Proceeds must be expended by 6/30/06.
2. Plan and Specs are ready on the Kitchen Build-out and could be ready in a
couple of weeks on the SE Trellis.
3. There is not enough time to prepare bid documents for the restroom remodels
and complete construction prior to 6/30/06.
4. The Convention Center staff places the Kitchen Build-out as their highest priority
and have offered to allow utilization of prior years budget savings, set aside for
capital: $ 148,921 Unscheduled Capital Projects. With these dollars there is
enough to cover the Kitchen Build-out.
FISCAL IMPACT: Finance Director Review:, ,, - 3—
��( .<
There will be no impact to the General Fund as the dollars remaining in the convention
center accounts are bond proceeds which must be spent on'°improvements to the center
or for debt reduction. These dollars remain because the overall project was brought in
under budget. Additionally, the saving dollars from previous years Convention Center
activities have been set aside for Capital Improvements and will not take from some
other activity,
Allen Smoot, Project Administrator
David H. Ready, City IM r
45:0-
Attachments:
Minute Order
Remaining Funds Analysis
Wish List
City Council Staff Report
,January 4, 2005 -- Page 4
Convention Center—Contingency Allocation
MINUTE ORDER NO.
APPROVING PLANS AND SPECIFICATIONS FOR THE PALM SPRINGS
CONVENTION CENTER KITCHEN BUILD-OUT PROJECT AND
AUTHORIZING THE IMMEDIATE BIDDING OF THE PROJECT.
I, James Thompson, City Clerk of the City of Palm Springs, hereby certify that this
Minute Order approving Plans and Specifications for the Palm Springs Convention
Center Kitchen Build-out project and authorizing the immediate bidding of the project
was adopted by the City Council of the City of Palm Springs, California, in a meeting
thereof held on the 4th day of January 2006.
James Thompson, City Clerk
PALM SPRINGS COMVENTION CENTER REMAINING FUNDS
Kitchen Build-out Estimate (At Bottom of page. )
Funds Available as of 12/15/05 845,141
Advertising Reserve -197,947
FF&E Reserve -200,070
Total Reserves -398,017
Funds Available After Reserves 447,124
Known Remaining Costs
A/C Valves -13,500
East Side ABC -3,500
Amado Gutter soft cost/contingency -3,500
Verizon Broken Line Repair -1,625
Additional Landscaping -20,000
Chiller Contingency/soft cost -10,000
Reroof Contingency/soft cost -15,000
Triangle Parcel Soil Stabalization -1,700
SCE Vault Top Repair -3,500
Total Remaining Costs -72,325
FUNDS AVAILABLE FOR OTHER PROJECTS 374,799
Kitchen Build-out Project
Estimated Construction Cost -430,000
Plan Check/Permits -3,500
Testing and Inspection -2,500
Admin Costs 4.5 months -22,500
Architectural Fees -19,000
Contingency -43,000
Total Project Funds Needed -520,500
Remaining Funds (Negative number-shortfall) -145,701
WISH LIST - PALM SPRINGS CONVENTION CENTER Sept. 14, 2005
Priori Project Description Const Est Soft Cost Total Cost
O&M Projects
1 Replace Old Chiller $288,671 $12,500 $301,171
2 Re-roof Exhibit Hall $564,900 $15,000 $579,900
3 Amado Cross Gutter $30,392 $3,500 $33,892
Sub Total $914,963
Expansion Enhancement Projects
1 SE Lawn ABC Enclosure 20,000 3,000 23,000
2 Triangle Cleanup/stabalization 27,350 2,000 29,350
3 Kitchen Build-out $430,000 $90,500 $520,500
3a Triangle Interim Improvements $300,000 $45,000 $345,000
4 SE Trellis $190,000 $18,000 $208,000
5 Exist Exh Hall Relamping $300,000 $35,000 $335,000
6 FF&E Chairs $335,000 $0 $335,000
7 Oasis Men's Restroom $75,000 $15,000 $90,000
8 Mesquite Restrooms $160,000 $28,000 $188,000
9 Smoketree Restrooms $160,000 $28,000 $188,000
10 Operable Wall Exh Hall $225,000 $5,000 $230,000
11 Landscpe @ Hotel $50,000 $7,500 $57,500
12 Landscape @ Caballeros $50,000 $15,000 $65,000
13 Mesquite Ceiling Redo $75,000 $12,000 $87,000
14 New Marquee $650,000 $65,000 $715,000
Subtotal $3,071,350
Grand Total $3,986,313
Note:: The above prioritization was provided by SMG.