Oq<�FORN,P City Council Staff Report
Date: September 21, 2011 CONSENT CALENDAR
Subject: INDIAN CANYON DRIVE AT VISTA CHINO TRAFFIC SIGNAL
MODIFICATION, CITY PROJECT NO. 08-17
From: David H. Ready, City Manager
Initiated by: Public Works and Engineering Department
SUMMARY
Approval of Contract Change Order No. 1 to Agreement No. 6093 with PTM General
Engineering Services is necessary to accommodate required changes in the work
related to the Indian Canyon Drive at Vista Chino Traffic Signal Modification, City
Project No. 08-17.
RECOMMENDATION:
1) Approve Change Order No. 1 to Agreement No. 6093 with PTM General
Engineering Services, in an amount of $27,354.83 for a revised total contract
amount of $230,557.83 for the Indian Canyon Drive at Vista Chino Traffic Signal
Modification, City Project No. 08-17; and
2) Authorize the City Manager to execute all necessary documents.
STAFF ANALYSIS:
On November 17, 2010, the City Council awarded a contract to PTM General
Engineering Services for modification and upgrade of the existing traffic signal at the
Indian Canyon Drive and Vista Chino intersection. Previously, the existing traffic signal
had no left-turn phasing in any direction, which made turning left difficult during peak
hours of traffic at this highly congested intersection. Vista Chino is also State Highway
111, and Caltrans operates and maintains this traffic signal.
Construction of this project has been under inspection by Caltrans, and during
construction Caltrans imposed certain requirements related to installation of underground
conduit and trench pavement repairs. These additional requirements were not originally
included in the project, and complying with these requirements incurred additional cost to
the contractor.
Item No. 2A .
City Council Staff Report
September 21, 2011 - Page 2
Contract Change Order No. 1 to CP 08-17
Staff has negotiated the cost to comply with the Caltrans requirements, and recommends
Council approve Contract Change Order No. 1 to compensate the contractor for the work
completed pursuant to Caltrans requirements.
FISCAL IMPACT:
Sufficient funds are available in Local Measure A account 134-4498-50271. No local
miscellaneous General Funds are being used for this project.
SUBMITTED:
Prepared by: Recommended by:
l
Marcus L. Fuller David J. Barakian
Assistant Director of Public Works Director of Public Works/City Engineer
Approved by:
Thomas J. Wils , Asst. City ManageT David H. Rea WEi anager
Attachments:
1. Change Order No. 1
02
i
CITY OF PALM SPRINGS
CONTRACT CHANGE ORDER
To: PTM General Engineering Services Date: August 11, 2011
1312 E.Warner Avenue Project No.: 08-17
Santa Ana, CA 92705 Project: Indian/Vista Chino Traffic Signal
Change Order No.: One(1)
Contract Purchase No.: 11-0520. 0
Account Number: 134-4498-50271
Agreement No.: 6093
Chances to Contract
New Items:
A. Open Trench Conduit Installation Time and Materials $23,624.10
B. Trench Paving Grind and Cap Lump Sum $11,445.00
C. Credit for Original Scope of Work Lump Sum $-7,714.27
Total— Contract Increase Amount $27,354.83
REASONS FOR CHANGES:
A. Specified conduit installation method was not allowed by State of California officials.
Contractor was required to place all conduits via open trenching and excavation to a minimum
depth of 30". The conduit placement as well as the placement of aggregate base and AC paving
of trenches was performed on a time and materials basis. The actual time and materials required
to complete the work was monitored and all applicable mark ups were applied to determine the
price of the work indicated above.
B. In accordance with State of California Requirements,the conduit trenches will be ground 18"
outside of trench edges and final paving cap will be placed. The lump sum price indicated above
was obtained by obtaining bids to complete the work. The low bidder was the originally listed
subcontractor and the price is inclusive of the allowable 5% mark up for work performed by a
subcontractor.
C. The cost for the originally specified installation method (which was not performed), is being
credited to the contract in the amount indicated above.
This is a final balancing change order. There are no other additional items of work on this contract.
SOURCE OF FUNDS
Account No. 134-4498-50271 will be charged $27,354.83
1 03
Summary of Costs Contract Time
Original Contract Amount: $203,203.00 Original Completion Date: 8-23-11
This Change Order: $27,354.83 Days Added for this C.C.O. 0
Previous Change Order(s): $0.00 Previous Days Added: 0
Revised Contract Amount: $230,557.83 Revised Completion Date: 8-23-11
1 have received a copy of this Change City Approval:
Order and the above AGREED PRICES
are acceptable to the contractor. Submitted by Date
Senior Public Works Inspector
By Approved by Date
PTM Engineering Services, Inc City Engineer
Date Approved by Date
City Manager
Attested by Date
City Clerk