HomeMy WebLinkAbout10/5/2011 - STAFF REPORTS - 2.C.Date: October 5, 2011
Citv Council Staff Report
CONSENT CALENDAR
Subject: APPROVAL OF AMENDMENT NO. 5 TO CONTRACT SERVICES
AGREEMENT WITH DOKKEN ENGINEERING FOR THE INDIAN
CANYON DRIVE/INTERSTATE 10 INTERCHANGE
From: David H. Ready, City Manager
Initiated by: Public Works and Engineering Department
SUMMARY
Approval of Amendment No. 5 to the Dokken Engineering Agreement (Agreement No.
4318) revises the total contract amount for professional environmental, design, and
construction administration services to $1,831,362 for an increase of $38,880 for
additional right-of-way engineering and construction bid support services for the Indian
Canyon Drive / Interstate-10 Interchange Project, City Project No. 00-14.
RECOMMENDATION:
1) Approve Amendment No. 5 to Agreement No. 4318 with Dokken Engineering in
an amount of $38,880 for a revised total contract amount of $1,831,362 for the
Indian Canyon Drive / Interstate-10 Interchange Project, City Project No. 00-14;
and
2) Authorize the City Manager to execute all necessary documents.
STAFF ANALYSIS:
On December 6, 2000, City Council originally approved Agreement No. 4318 with
Dokken Engineering for environmental, engineering design, and construction
engineering services for the 1-10 Project: Three prior amendments were approved by
City Council to address additional services required as the environmental and design
process moved its way through Caltrans. A fourth amendment was approved last year
to accommodate additional services related to the County administering and bidding this
project, and to comply with Caltrans requirements.
Now as the construction phase is nearing completion, additional budget is required for
design oversight of roadway and structures construction, and it is necessary to have
ITEM NO. 0" L
City Council Staff Report
September 22, 2010 - Page 2
Amendment No. 4 to Agreement No. 4318
traffic signal timing plans prepared for the new traffic signals to ensure they are
coordinated with the closely spaced Caltrans signals. Additionally, Caltrans is requiring
that the City prepare a Record of Survey to document all of the new rights -of -way that
have been acquired and will be transferred to the state for this Interchange. New scope
has been added by this contract amendment to prepare and process a Record of
Survey with the County for Caltrans approval.
FISCAL IMPACT:
Sufficient funds are available in the Regional Measure A account 134-4497-50185; no
local miscellaneous general funds are required for this project.
SUBMITTED:
Prepared by:
Marcus L. Fuller
Assistant Director of Public Works
Approved by:
Recommended by:
David J. Barakian
Director of Public Works/City Engineer
Thomas J. Wi n, Asst. City Manager David H. Ready, City er
Attachments:
1. Amendment No. 5 to Agreement No. 4318
02
AMENDMENT NO. 5 TO CONTRACT SERVICES AGREEMENT NO. 4318
WITH DOKKEN ENGINEERING
INDIAN CANYON DRIVE/I-10 INTERCHANGE, CITY PROJECT 00-14
The following articles of Agreement No. 4318 are hereby amended to read as follows:
SECTION 2.1 Maximum contract amount is amended to One Million Eight Hundred Thirty -One
Thousand Three Hundred Sixty -Two Dollars ($1,831,362.00).
SCOPE OF SERVICES (Exhibit "A") —
See attached Exhibit "A" for additional services
SCHEDULE OF COMPENSATION (Exhibit "C") —
See attached Exhibit "C".
Purchase Order Number(s):
Agreement Number:
Original City Council Approval:
Original Minute Order Number:
Original Contract Amount:
Amount of Previous Increase(s)
Amount of This Increase
Amended Total:
Account Number(s):
116346
4318
December 6, 2000
6761
$ 943,842
$ 848,640
$ 38,880
$1,831,362
1344497-50185
SIGNATURES ON LAST PAGE
03
Except as specifically amended by this Amendment No. 5, all terms and provisions of
Agreement No. 4318 remain in full force and effect.
ATTEST: CITY OF PALM SPRINGS,
a California charter city
By:
City Clerk By:
City Manager
APPROVED AS TO FORM:
0
City Attorney
CONTRACTOR: Check one: _Individual _Partnership _Corporation
Corporations require two notarized signatures: One signature must be from the Chairman of Board, President, or any Vice
President. The second signature must be from the Secretary, Assistant Secretary, Treasurer, Assistant Treasurer, or Chief
Financial Officer).
Bv'
Notarized Signature of Chairman of Board,
President or any Vice President
Name:
Title:
By:
Notarized Signature Secretary, Asst Secretary,
Treasurer, Asst treasurer or Chief Financial Officer
Name:
Title:
State of t State of }
County of )ss County of Iss
On before me, On before me,
personally appeared
who proved to me on the basis of satisfactory evidence) to be
the person(s) whose name(s) is/are subscribed to the within
instrument and acknowledged to me that he/she/they
executed the same in his/her/their authorized capacity(ies),
and that by his/her/their signature(s) on the instrument the
person(s), or the entity upon behalf of which the person(s)
acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the
State of California that the foregoing paragraph is true and
correct.
WITNESS my hand and official seal.
Notary Signature:
Notary Seal:
personally appeared
who proved to me
on the basis of satisfactory evidence) to be the person(s)
whose name(s) is/are subscribed to the within instrument and
acknowledged to me that he/she/they executed the same in
his/her/heir authorized capacity(ies), and that by his/her/their
signature(s) on the instrument the person(s), or the entity upon
behalf of which the persons) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the
State of California that the foregoing paragraph is true and
correct.
WITNESS my hand and official seal.
Notary Signature:
Notary Seal:
LIE
Exhibit "A"
Additional Scope of Services
Indian Canyon Drive/interstate 10 Interchange, City Project 00-14
EXHIBIT A is amended to provide the additional required professional services as follows:
Task 2.15 Prepare Record of Survey
At the request of the County and City, Contractor shall complete field surveys, prepare, and
submit a Record of Survey (ROS) meeting Riverside County Surveyor standards and
requirements, subject to the Riverside County Surveyor's review and approval.
Task 2.16 Approved Record of Survey
Contractor shall respond to plan check comments on the draft Record of Survey (ROS), and
shall submit a revised ROS for County approval.
Task 6.07 Prepare City Signal -Timing Plans
Development of Signal -Timing Plans: Contractor shall coordinate with City and Caltrans staff to
develop City signal -timing parameters, such as cycle lengths, splits, yellow time, etc., based on
traffic volume, capacity, and the speed limits at the two intersections. Contractor shall develop a
Synchro model for the study intersections. Contractor shall develop one set of signal -timing
plans for each intersection (Indian Canyon Drive/20th Avenue, and Indian Canyon Drive/Garnet
Avenue).
05
EXHIBIT C is replaced with the following exhibit:
SCHEDULE OF COMPENSATION
Tasks listed below are identical to tasks identified in Exhibit A of this Agreement. Payments to Contractor
shall be made no more frequently than monthly. Lump sum payments shall be made to Contractor based
upon completion of tasks, or pro-rata portions thereof noted below.
Sub -Task Total Task Total
Lump Sum Lump Sum
Task 1.0. Proiect Administration
—
$ 126.705.00
Task 2.0, Planning and Project Development
---
$ 661,861.29
Task 2.1, Research and Data Gathering
$ 1,083.00
—
Task 2.2, Project Development Team Meetings
$ 66,333.00
---
Task 2.3, Survey
$ 40,297.00
---
Task 2.4, Preliminary Hydrology Report
$ 26,819.00
--
Task 2.5, Preliminary Geotechnical Report
$ 6,066.00
---
Task 2.6, Traffic Operations Analysis
$ 41,026.00
--
Task 2.7, Environmental Approval
$171,334.00
---
Task 2.8, Value Engineering
$ 5,633.00
--
Task 2.9, Project Report and Project Approval Report
$112,185.00
—
Task 2.10, Geometric Approval Drawings
$ 65,136.00
—
Task 2.11, Geotechnical Design Report
$ 29,834.00
---
Task 2.12, Right of Way Engineering
$ 66,503.29
—
Task 2.13, Agreements
$ 2,925.00
---
Task 2.14, Utility Coordination/Relocations
$ 11,807.00
---
Task 2.15, Prepare Record of Survey
$ 10,725.00
---
Task 2.16. ADDroved Record of Survev
$ 4.155.00
---
Task 3.0, Structures
---
$ 157,520.00
Task 3.1, Preliminary Structure Design
$ 5,915.00
---
Task 3.2, Geotechnical Coordination and Foundation Report
$ 31,988.00
---
Task 3.3, Structural Design and Calculations
$ 41,441.00
---
Task 3.4, Demolition of Existing Bridge
$ 5,000.00
---
Task 3.5, Structural Special Provisions
$ 18,440.00
---
Task 3.6, Estimate
$ 9,600.00
---
Task 3.7, Independent Check Review and Quality Control
$ 19,146.00
---
Task 3.8, Draft PS&E
$ 22,590.00
---
Task 3.9. Final PS&E
$ 3,400.00
---
Task 4.0, Roadway
—
$ 602,833.71
Task 4.1, Basic Roadway Plans
$191,470.00
---
Task4.2, Drainage Plans
$115,570.00
—
Task 4.3, Traffic Plans
$120,490.00
---
Task4.4, Miscellaneous Plans
$ 39,920.00
---
Task 4.5, Specifications and Estimate
$ 41,230.00
—
Task 4.5(a), Design Exception Fact Sheets
$ 3,550.00
---
Task 4.5(b), Construction CPM Schedule
$ 11,590.00
---
Task 4.5 (c), Utility Potholing
$ 34,543.71
---
Task 4.6, Roadway Deliverables
Task 4.6.1, Submittals
$ 2,000.00
---
Task 4.6.2, Draft PS&E (95% Complete)
$ 5,000.00
—
Task 4.6.3, Final PS&E (100% Complete)
$ 5,000.00
---
Task 4.6.4, Project Files and Resident Engineer's File
$ 6,800.00
—
Task 4.6.5. SIoDe Stake Notes
$ 25.670.00
---
Task 5.0. Construction Biddina Plans
—
$ 61.058.00
Task 6.0, Construction Support Phase
---
$ 221,384.00
Task 6.0, General Construction Support
$26,874.00
---
Task 6.01, Roadway Design Construction Support
$51,350.00
---
Task 6.02, Structures Design Construction Support
$44,550.00
---
Task 6.03, Shop Drawing Review
$16,700.00
---
Task 6.04, Geotechnical Design Support
$15,550.00
---
Task 6.05, Electrical Design Support
$15,350.00
--
Task 6.06, Utility Relocation Coordination
$11,110.00
---
Task 6.07, Prepare City Signal -Timing Plans
$ 7,000.00
---
Task 6.1. "As -Built' Plans
$32,900.00
---
Total of all Tasks of this Contract
—
1,831,362.00
06