HomeMy WebLinkAbout11/16/2011 - STAFF REPORTS - 2F ?ALM SAR
iy
G
Y N
* R
w ,r
City Council Staff Report
Date: November 16, 2011 CONSENT CALENDAR
Subject: APPROVAL OF CONTRACT CHANGE ORDER NO. 1 FOR THE TRACT
NO. 13257 SEWER IMPROVEMENTS (PHASES 1 & 2), CITY PROJECT
10-02
From: David H. Ready, City Manager
Initiated by: Public Works and Engineering Department
SUMMARY
Approval of Contract Change Order No. 1 adds a portion of the Phase 2 sewer
improvements to the contract.
RECOMMENDATION:
1) Approve Change Order No. 1 to Agreement No. 6142 with G&M Construction, in
an amount of $72,370.15 for a revised total contract amount of $416,858.40 for
the Tract No. 13257 Sewer Improvements, City Project No. 10-02; and
2) Authorize the City Manager to execute all necessary documents.
STAFF ANALYSIS:
The Public Works and Engineering Department requested and received funding from
the City's 2010/2011 and 2011/2012 CDBG Programs. The Department has proposed
to design and construct a new sewer system to serve the low-to-moderate income
neighborhood located west of Gene Autry Trail and south of Via Escuela (referred to as
"Tract No. 13257"). Tract No. 13257 was developed during the 1980's when it was part
of unincorporated Riverside County. At the time, Riverside County did not require
extension of public sewer to the tract, and all 87 homes in Tract No. 13257 have private
septic systems, some of which have begun to fail. Some lower income property owners
have had to request financial assistance from the City for pumping and servicing of their
septic systems.
On March 17, 2010, the City Council approved the 2010/2011 CDBG Program, and
awarded the Department $267,118 for the first phase of this project. On March 16,
2011, the City Council approved the 2011/2012 CDBG Program, and awarded the
ITEM NO.__S!_C_—
City Council Staff Report
November 16, 2011 - Page 2
Tract No. 13257 Sewer Improvements (City Project 10-02)
Department $180,951 for the second phase of this project (this amount was reduced to
$160,855 as a result of a lower overall CDBG Program distribution to the City).
Ultimately, this phased CDBG project proposes to install approximately 3,800 feet of 8"
VCP public sewer line and 3,480 feet of 4" VCP sewer laterals. The existing on-site
septic tanks will be disconnected and abandoned in accordance with the City's Building
Department requirements. The costs to convert from private septic systems to a public
sewer system are included in this proposal, including the $3,000 per unit sewer
connection charge imposed by the City at the time a property is connected to the City's
sewer system.
Given the $1,200,000 total estimated cost to provide public sewer to Tract No. 13257,
this project is proposed as a multi-year CDBG phased project.
On September 7, 2011, the City Council awarded a construction contract to G&M
Construction. As the full cost of Phases 1 and 2 exceeded the total amount of CDBG
funds available, the Council limited its award to Phase 1 only, at a cost of $344,488.25.
Additional costs for Phase 1 also covered by CDBG funds as part of construction are:
Phase 1
Construction: $344,488.25
Sewer Connection Fees: 21 @ $3,000 = $63,000
Materials Testing: $9,708
Construction Administration/Inspection: $15,000
Total: $432,196.25
On September 7, 2011, the Council also adopted a Budget Resolution to allocate
additional unexpended CDBG funds from prior years to supplement current funding for
this project.
Staff has negotiated a construction change order with G&M Construction to add some of
the Phase 2 sewer improvements to the contract. The portion of work to be ,added
includes only the public sewer main and sewer laterals within Zachary Court. No on-site
building sewer extensions and septic tank abandonments for the homes on Zachary
Court are included at this time given the budget constraint. It will be staffs intention to
submit an application for Fiscal Year 2012/2013 CDBG funding to complete the Phase 2
sewer construction work originally contemplated with this project.
FISCAL IMPACT:
Sufficient funds will be available in account 137-4813-63583.
02
City Council Staff Report
November 16, 2011 - Page 3
Tract No. 13257 Sewer Improvements(City Project 10-02)
SUBMITTED:
Prepared by: eJ(2-,
Recommended by:
Marcus L. Fuller David J. Barakian
Assistant Director of Public Works Director of Public Works/City Engineer
Approved by:
Thomas J. Wilso , Asst. City Manager David H. Ready, 2Wnager
Attachments:
1. Contract Change Order
03
CITY OF PALM SPRINGS
CONTRACT CHANGE ORDER
To: G&M Construction Date: September 7, 2011
211 W. Mesquite Ave. Project No: 10-02
Palm Springs, CA 92262 Project: Tract No. 13257 Sewer
Tel: (760) 322-6918 Improvements (Ph 1 &2)
Fax: (760) 778-6708 Change Order No: 1
Purchase Order 12-0464
Attn: George Marantz Account 137-4813-63583
Agreement No: 6142
CHANGES IN WORK:
In lieu of awarding the entire Bid Schedule B, this Contract Change Order No. 1 shall add the following scope
of work from Phase 2 of the plans:
Construct 8"VCP sewer main in Zachary Court (Station 10+05 to 12+36.20)
Construct 4" VCP sewer laterals at Station 10+59.98, 10+74.29, 11+16.77, 11+36.77, 11+81.12, 11+86.12,
12+19.20, 12+24.20, and 12+29.20
Construct 48" sewer manhole at Station 12+36.20
Mobilization, traffic control and sheeting/shoring/bracing associated with the above additional work.
On-site building sewer extension and septic tank abandonment work is excluded.
Add the following work:
Construct 1" asphalt pavement grind and overlay in Norloti Street, Amico Street (between Zachary Court and
Norloti Street), and in Zachary Court.
Eliminate Bid Schedule A, Item 30 "Reconstruct Drainage Channel'.
Modify existing drainage channel by removing 4 feet wide section and constructing 24"x24" drainage inlet with
8" diameter PVC drainage pipe, with new inverted concrete cross-section, in accordance with detail attached
hereto.
CHANGES IN COST:
Decreases in Cost:
Bid Schedule A, Item 30, "Reconstruct Drainage Channel": 205 LF @ $260.00 per LF = ($53,300.00)
Total Decrease: $53,300.00
Increases in Cost:
Item 1, Mobilization, Lump Sum (LS) @ $5,000
Item 2, Traffic Control, Lump Sum (LS) @ $1,750
Item 3, Construct 8" VCP Sewer Main, 231.20 linear feet (LF) @ $98.25 per LF = $22,715.40
Item 4, Construct Sewer Manhole (13=48"), 1 each (EA) @ $2,500.00
Item 5, Construct 4"VCP Sewer Lateral, 281.00 linear feet(LF) @ $101.00 per LF = $28,381.00
Item 6, Sheeting, Shoring & Bracing or Equivalent Method, Lump Sum (LS) @ $1,000
Item 7, Grind and Overlay Existing AC Pavement (1"), 16,775 square feet (SF) @ $1.45 per SF = $24,323.75
Item 8, Modify Existing Drainage Channel, $40,000 (Time & Materials Estimate)
Total Increase: $125,670.15
04
Contract Change Order No. 1
City Project#10-02, Tract No. 13257 Sewer Improvements
Page 2 of 3
The prices listed above for Items 1-6 are consistent with the prices listed in Bid Schedule B, and shall
constitute full compensation, including all markups for this additional work, and no additional payment will be
made.
As specified in the Special Provisions, compensation for removal and replacement of existing improvements
related to the sewer construction shall be considered as included in the prices paid, and no additional
compensation will be allowed therefore.
The price listed above for Item 8 is a time and material estimate, final cost of Item 8 will be determined upon
review of actual time and material costs incurred including appropriate mark-up, in accordance with the Special
Provisions.
SOURCE OF FUNDS:
Funds are available in the following account(s): 137-4813-63583
REASONS FOR CHANGE:
Bid Schedule B not included in original contract award due to budget constraints. This Contract Change Order
adds the sewer construction in Zachary Court to contract. On-site sewer connections are excluded.
Bid Schedule A, Item 30 'Reconstruct Drainage Channel' is being eliminated, and a new item is being added
by this Contract Change Order to modify the existing drainage channel by removing a 4 feet wide section,
constructing a 24°x24" drainage inlet with 8" diameter PVC drainage pipe, with new inverted concrete cross-
section, in accordance with detail attached hereto.
Additional asphalt pavement grind and overlay is being added by this Contract Change Order to include areas
beyond the limits of the trench repairs associated with the sewer main and sewer lateral excavations. Given
the multiple trenches involved with installation of the new sewer improvements, some areas of existing asphalt
pavement would remain leaving isolated floating sections of asphalt pavement in poor condition. This work
ensures the entire street section of Norloti Street, Arnico Street (between Zachary Court and Norloti Street),
and in Zachary Court, will have a new asphalt pavement surface.
SUMMARY OF COSTS:
Original Contract Amount: $ 344,488.25 Original Completion TBD
This Change Order: $ 72,370.15 Days Added for this CO: —10--
Previous Change Order(s): $ 0.00 Previous Days Added: -0—
Revised Contract Amount: $ 416,868.40 Revised Completion TBD
05
Contract Change Order No. 1
City Project#10-02, Tract No. 13257 Sewer Improvements
Page 3 of 3
1 have received a copy of this Change Order and the above AGREED PRICES are acceptable to Contractor
Contractor Approval:
Signature Date
Printed Name and Title
City Approval:
Submitted By:
Assistant Director of Public Works/ Date
Assistant City Engineer
Approved By:
Director of Public Works/City Engineer Date
Approved By:
City Manager Date
Attest By:
City Clerk Date
Distribution:
Original Conformed Coov: Conformed - File Coov:
Contractor (1) Engineering Pay File (1)
City Clerk (1) Resident Enqineer (1)
Procurement (1)
Finance (1)
06
6'
' 4--- f.
N �
EXIST CHANNEL
W
�- - - 6" A11N_ »
144 BROOKS BOX
C'DRAIN PIPE PVC,
v
--8" SEWER MAIN
STORM DRAIN CHANNEL
WEST END
N.T.S.
6'
i' 4' r
-�
N , EXIST CHANNEL
- i
y
6" MIN.
DRAIN PIPE WG
-8- SEWER MAIN
STORM DRAIN CHANNEL
EAST END
N.TS
07