4<1FORN� City Council Staff Report
DATE: April 5, 2005 CONSENT AGENDA
SUBJECT: CONTRACT AWARD TO HARBOR CONSTRUCTION COMPANY INC.
FOR THE EXPAND TERM I NAL/HOLDROOM CITY PROJECT 2005-10
(AIP 3-06-0181-38).
FROM: David H. Ready
BY: Aviation Department
SUMMARY
Recommend City Council accept the lowest base bid and authorize the City Manager to
execute a construction contract in a form acceptable to the FAA and the City Attorney
for the Construction of the New Regional Terminal Holdroom, FAA Project Expand
Terminal/Holdroom City Project No. CP2005-10 (AIP 3-06-0181-38).
RECOMMENDATION:
1. Approve Minute Order No. , authorizing award of a construction contract with
Harbor Construction Company, Inc. in the amount of $9,278,000 for the
Construction of the New Regional Terminal Holdroom, FAA Project Expand
Terminal/Holdroom, City Project No. CP2005-10 (AIP 3-06-0181-38) subject to
FAA approval, in a form acceptable to the City Attorney, and establishing the
Project Administrator and Administration parameters.
2. Authorize the City Manager to execute all necessary documents.
STAFF ANALYSIS:
The project was initially advertised in June 2005 and bids received in July 2005. The
anticipated level of federal funding did not become available therefore, Council agreed
to re-bid a repackaged project that would still address the throughput issues by
increasing capacity, and defer certain landscaping elements to 2008. The project was
advertised again on October 24, 2005 and November 6, 2005.
Staff solicited bids and five bidders responded on February 7, 2006 as follows:
Item No. 2 . Q.
City Council Staff Report
(April 5, 2006) -- Page 2
(Holdroom Contract Award)
1. FTR International Inc. in the amount of $13,000,000,
2. Harbor Construction Company Inc. in the amount of$9,278,000.
3. LA Contractors Corporation in the amount of 10,487,000, and
4. Mall Craft Inc. in the amount of$13,632,000,
5. Summit Builders in the amount of$9,568,000
It is recommended to accept Harbor Construction as the lowest responsible responsive
bidder for the construction of Regional Commuter Holdroom project as described in the
attached Scope of Work, subject to FAA approval. The engineer's estimate ranged
from $7.5 million to $9 million.
The attached Minute Order awards the contract to Harbor Construction Company, Inc.
and appoints the Director of Aviation as the Project Administrator and authorizes the
Project Administrator, subject to City Manager approval, to approve Change Orders up
to 10% of the total base bid.
At its regularly scheduled meeting on April 5, 2006, the Airport Commission voted to
recommend to the City Council t appr the award of this construction contract.
FISCAL IMPACT:
The construction will be funded by two 95% FAA Airport Improvement Grants during
fiscal years 2005 through 2008. The local portion (5%) has been budgeted and will be
paid from the Airport's general fund.
Richard S. Walsh, A.A.E., Director of Aviation David H. ReacTy- anager
Attachments:
Minute Order
Scope of Work
02/30/21006 14:04 FAX. 760 318 3815 PSP INT'L ARPT 0 003
r
Western-Pacific Region P.O.Box 92007
U.S.Department Airports Division
of Transportation Los Angeles,CA 90009
Federal Aviation
Adminlstratlon
RECEIVED
August 5, 2005 p
Mr. xiehard S. Walsh, Director of Aviation AUG 8-2005
3400 E- Tahquitz canyon way, suite OPC EY; DEPTOF�IVIATION
Palm Springs, CA 92262-6966
Dear Mr. Walsh:
Palm Springs International Airport
Fiscal Year 2005 Grant Offer (Multi-Year Grant)
AMP Project No. 3-06-0181-38
The Palm Springs international Airport, Fiscal Year (FT) 2005 Airport
Improvement Program (AIP) Project No. 3-06-0181-30, Contract No.
D'1'FA08-05-C-21920, has been approved. Enclosed are five copies of the
grant agreement, under which the United States commits itself to
participate in the allowable cost of the project not to exceed
$3,545,400.00 for FY-2005, as part of a multi-year project for FY-2005,
FY-2006 (estimated at $3,545,400-00) , and FY-2007 (estimated at
$3,545,400.00) , with total federal share of $10,636.200,00for ET-2005
through FY-2007.
Your acceptance of the grant offer will obligate the City of palm
Springs (sponsor) to accomplish the described development without undue
delay. An official of the sponsor shall accept this offer on or before
August 26, 2005 by signing the enclosed grant agreement in the space
provided.
The date of the execution of the grant agreement should be the same ad,
or later than, the "Date of offer" on page one. The date of attorney's
signature must be the same or later than, the date of execution.
When the documents are fully executed, certified, attested, and the
appropriate seals impressed, please return, three copies to our office.
Sincerely,
John-p.Uldlligan
Supervisor, Standards Section
Enclosures
MINUTE ORDER NO.
AUTHORIZING AWARD OF A CONSTRUCTION CONTRACT WITH
HARBOR CONSTRUCTION COMPANY, INC. IN THE AMOUNT OF
$9,278,000 FOR THE CONSTRUCTION OF THE NEW REGIONAL
TERMINAL HOLDROOM, FAA PROJECT EXPAND
TERM I NAL/H OLDROOM, CITY PROJECT NO. CP2005-10 (AIP 3-06-0181-
38) SUBJECT TO FAA APPROVAL, IN A FORM ACCEPTABLE TO THE
CITY ATTORNEY, AND ESTABLISHING THE PROJECT ADMINISTRATOR
AND ADMINISTRATION PARAMETERS.
I HEREBY CERTIFY that this Minute Order, awarding a construction contract
with Harbor Construction Company, Inc. in the amount of $9,278,000 for the
Construction of the New Regional Terminal Holdroom, FAA Project Expand
Terminal/Hold room, City Project No. CP2005-10 (AIP 3-06-0181-38) subject
to FAA approval, in a form acceptable to the City Attorney, and establishing
the Project Administrator and Administration parameters was approved by the
City Council of the City of Palm Springs, California, in a meeting thereof held
on the 5th day of April, 2006.
JAMES THOMPSON
City Clerk
CITY OF PALM SPRINGS, CALIFORNIA
SCOPE OF SERVICES
EXPAND TERMINAL/HOLDROOM PROJECT
PALM SPRINGS INTERNATIONAL AIRPORT
CITY PROJECT NO. 2005-10 FAA AIP 3-06-0181-38
DESCRIPTION OF THE WORK — The Project is construction of a new Regional Holdroom,
separate restroom facility, modifications to passenger conveyance walkway, drainage/irrigation,
existing restroom modifications at Palm Springs International Airport. Work includes
approximately 15,000sf of new construction for regional holdroom, 1,600sf restroom, 600sf
electrical room, new walkway, and courtyard landscaping. The Airport will remain open and
operational during the construction period.
The Work involved is described in the bid documents and includes the following:
Including, plant, engineering, labor, tools, transportation, services, supervision, temporary
facilities, materials and equipment required to complete the work. The work involved includes:
Temporary Security Fence, Site Work, Earthwork, Grading, Site Demolition, Selective
Demolition, Drainage, Irrigation, Walkway, Erosion Control, Concrete Foundations/Slabs/Wall,
Site Concrete, Concrete & Concrete Reinforcing, Structural Steel and Decking, Unit Masonry,
Insulation and Roofing, Doors and Windows, Glass and Glazing, Interior Finishes, Mechanical,
Plumbing, Electrical, Fire Control and Protection, Signage, Start-up and Commissioning.
LOCATION OF WORK—The Work to be performed hereunder is located at the Palm Springs
International Airport, 3400 E. Tahquitz Canyon Way, Palm Springs, California, 92262.
SCHEDULE OF WORK - Project is anticipated to start on or about May, 2006 and be
completed on or about May 1, 2007.