c4`'FOSL City Council Staff Report
Date: July 11, 2012 CONSENT CALENDAR
Subject: APPROVAL OF AMENDMENT NO. 5 TO CONTRACT SERVICES
AGREEMENT NO. 4780 WITH DOKKEN ENGINEERING FOR THE
BELARDO ROAD BRIDGE & ROADWAY WIDENING, CITY PROJECT
NO. 87-49
From: David H. Ready, City Manager
Initiated by: Public Works and Engineering Department
SUMMARY
An amendment to the contract services agreement with Dokken Engineering is
recommended to include construction phase services (contract administration, materials
testing, and inspection) for the Belardo Road Bridge & Roadway Widening, City Project
87-49.
RECOMMENDATION:
1) Approve Amendment No. 5 to Agreement No. 4780 with DolCken Engineering, in
the amount of $92,500 for a total revised contract amount of $862,740 for the
Belardo Road Bridge & Roadway Widening, City Project 87-49; and
2) Authorize the City Manager to execute all necessary documents.
STAFF ANALYSIS:
On October 1, 2003, the City Council approved Agreement No. '4780 with Dokken
Engineering to provide civil engineering design services for the Belardo Road Bridge &
Roadway Widening, City Project 87-49. This project will extend Belardo Road between
Sunny Dunes Road and S. Palm Canyon Dr., including construction of a new bridge
across Tahquitz Creek and various street improvements to Sunny Dunes Road,
Mesquite Avenue, and Morongo Road.
On May 4, 2011, the City Council approved the plans and specifications, and authorized
bidding for this project. As a federally funded project, this project is subject to Caltrans
M NO. a J
City Council Staff Report
June 20, 2012- Page 2
Amendment No. 5 to Agreement No. 4780
and Federal Highway Administration (FHWA) oversight, therefore, it is recommended
that the City's consultant take on the responsibility to ensure the construction of this
project complies with all state and federal rules.
Staff has negotiated a contract amendment with Dokken Engineering in the amount of
$311,600 to provide the City with turnkey construction phase services for this project.
On June 1, 2011, the City Council approved the contract amendment with Dokken
Engineering for a total revised contract amount of$770,240.
During the construction it has become necessary to increase the consultant's inspection
and management involvement to closely monitor the contractor and to ensure
compliance with the contract documents. Due to additional tasks and extra work for
difficult weather conditions, the project has exceeded the working day allowance which
requires greater construction management presence. Liquidated damages will be
charged for unjustified contractor's delay. This contract amendment is based on a
project schedule of 180 working days which exceed the originally budgeted 140 working
days for construction management. The additional cost is $92,500 increasing the
Construction Services amount to $404,100 for a total revised contract amount of
$862,740.
The estimated construction cost of this project is approximately $3,450,000 — and the
construction phase services represents 11.79% of this cost. Generally, construction
administration/inspection costs vary from 10%-15% of the construction estimate,
depending upon the complexity of the project.
Staff recommends Council approve the contract amendment which will ensure the
consultant is available to provide the required construction services.
FISCAL IMPACT:
The total estimated cost of the construction phase of this project (including construction
inspection and administration, and contingencies) is estimated at $4,351,942. Of the
original $3,000,000 PLHD federal grant, $2,325,194 remains available for construction
(prior funds were used for the environmental and design phases). This leaves a
balance of $2,026,748 to be funded with local funds. However, the Agua Caliente Band
of Cahuilla Indians ("Tribe") has agreed to provide funding for this project with its own
federal IRR funds.
A maximum of $2,035,362 in IRR funding is available to the City pursuant to a funding
agreement with the Tribe previously approved by the City Council on May 4, 2011.
Costs associated with this contract amendment will be covered by the IRR funding
made available by the Tribe. No local miscellaneous General Funds,will be required for
this project.
02
City Council Staff Report
June 20, 2012- Page 3
Amendment No. 5 to Agreement No. 4780
SUBMITTED:
Prepared by: Recommended by:
AL
George F. Farago David J. Barakian
Associate Civil Engineer Director of Public Works/City Engineer
Approved by:
Thomas J. 0 on, Asst. City Manager David H. Ready, City MaaaggF
Attachments:
1. Amendment No. 5 to Agreement No. 4780
03
AMENDMENT NO. 5 TO CONTRACT SERVICES AGREEMENT NO. 4780
WITH DOKKEN ENGINEERING
BELARDO ROAD BRIDGE & ROADWAY WIDENING
CITY PROJECT NO. 87-49
FEDERAL PROJECT NO. PLHL-5282(020)
The following articles of Agreement No. 4780 are hereby amended to read as follows:
SECTION 2.1 Maximum contract amount is amended to Eight Hundred Sixty Two Thousand
Seven Hundred Forty Dollars ($862,740.00).
SCHEDULE OF COMPENSATION (Exhibit`C")— Exhibit`C" is amended as follows:
See the attached Exhibit "C" SCHEDULE OF COMPENSATION "REVISED CONSTRUCTION
SERVICES"
Purchase Order Number(s): 416389
Agreement Number: 4780
Original City Council Approval: October 1, 2003
Original Contract Amount: $ 325,000
Amount of Prior Increases $ 445,240
Amount of This Increase $ 92,500
Amended Total: $ 862,740
SIGNATURES ON NEXT PAGE
04
Except as specifically amended by this Amendment No. 5, all terms and provisions of
Agreement No. 4780 remain in full force and effect.
ATTEST: CITY OF PALM SPRINGS,
a California chartercity
By:
City Clerk By:
City Manager
APPROVED AS TO FORM:
By:
City Attorney
CONSULTANT: DOKKEN ENGINEERING
Check one:_Individual_Partnership X Corporation
Corporations require two notarized signatures: One signature must be from the Chairman of Board;President,or any vice
President.The second signature must be from the Secretary,Assistant Secretary,Treasurer,Assistant T,treasurer,or Chief
Financial Officer).
By: Lz_r � By: I` G
Notarized Signature of Chairman of Board, No rud Si egnal e S cretary,Asst Secretary,
President or any Vice President Treasurer,Asst treasurer or Chief Financial Officer
Name: ��-, �/ LOB Name:
Title: Title:
State of Ccx( Stateof CC&(114r✓ 1'e,
Countyof Scnc✓'a4 ,em4�_ss County of Sacramalp,40 sss
On 465 12 before me, Ca w«a v, &S CkF On 6 1S 1 Z before me, CAkK rn v. Sc"ct(c'
personally appeared lCtc�Aa CL T- L P personally appeared Cet4!) C(n CL,
who proved to me on the basis of satisfactory evidence)to be who proved to me on the basis of satisfactory evidence)to be
the person(e)whose name(e) is/are-subscribed to the within the person(s) whose name(*is/ere subscribed to the within
instrument and acknowledged to me that helsheAheq instrument and acknowledged � to me that he/she/they
executed the same in hisA%Aheir authorized capacity(ies} executed the same In hislher/their, authorized capacity(ie*
and that by his/hadtheir_signature(* on the instrument the and that by hielher/their signatufe(s}on the instrument the
person*, or the entity upon behalf of which the persons) person(,): or the entity upon behalf of which the person(s}-
acted,executed the instrument. acted,executed the instrument '
I certify under PENALTY OF PERJURY under the laws of the I certify under PENALTY OF PERJURY under the laws of the
State of California that the foregoing paragraph is true and State of California that the foregoing paragraph is true and
correct. correct.
WITNESS my hand and official seal. WITNESS my hand and official seal.
Notary Signature: Notary Signature:
Notary Seal: Notary Seal:
CAMRAN SADEGHI r. CAMRA i SADEGHI
19; COMM. #1945483 z o COMM. #1945483 =
m Notary Public-California o rc m Notary Public -California o
Z Sacramento County Sacra o County
My Comm.Ex ices Jul 25,Wls Comm.Ex yres;u 25,20151
05
EXHIBIT "C"
SCHEDULE OF COMPENSATION
The following is the revised Exhibit"C", Schedule of Compensation, including Amendment No.5:
PHASE 1 - Preliminary Engineering and Studies: $155,100
PHASE 2- Final Engineering Design: $199,900
PHASE 3- ENVIRONMENTAL MITIGATION AND MONITORING SERVICES
Task 1.0 Environmental Permitting $32,160
Task 2.0 Environmental Specification Review $ 9,970
Task 3.0 Mitigation Monitoring Plan $61,510
REVISED CONSTRUCTION SERVICES
The following budgeted hours are based on a project schedule of 180 working days.
Previous This Incrtase
Project Manager: ( 36 + 23) hours @ $200/hour = $7,200 + $4,600= $11,800
Resident Engineer: (360+240) hours @ $150/ hour= $54,000 + $36,000 = $90,000
Structures Inspector: (320+320) hours @ $120/ hour= $38,400 + $38,400 = $76,800
Inspector: 360 hours CD $100/ hour = $36,000 = $36,000
Subtotal-Construction Inspection: $135,600 + $79,000 = $214,600
Materials Testing: $45,000 $45,000
Quality Assurance Testing: $10,000 $10,000
Labor Compliance: $27,000 + $9,000 = $36,000
Architectural Fabrication: $26,000
Design Support: $50,000
Equipment/ Per Diem: $18,000 + $4,500' _ $22,500
Subtotal Construction Services: $311,600 + $92,50q = $404,100
TOTAL PHASE 3: $415,240 + $92,500 = $507,740
GRAND TOTAL OF CONTRACT $770,240 + $92,500 = $862,740
END OF EXHIBIT°C'