Date: September 5, 2012 CONSENT CALENDAR
Subject: APPROVAL OF CONTRACT CHANGE ORDER NO. 22 FOR THE
INDIAN CANYON DRIVE WIDENING, CITY PROJECT 01-25.
From: David H. Ready, City Manager
Initiated by: Public Works and Engineering Department
SUMMARY
Approval of Contract Change Order No. 22 is the final change order for the Indian
Canyon Dive improvements through the Whitewater Wash. This change order provides
payment for additional asphalt concrete due to a change in the design cross section of
the roadway.
RECOMMENDATION:
1) Approve Change Order No. 22 to Agreement No. 6108 with Griffith Company, in
an amount of $188,511.94 for a revised total contract amount of $3,258,526.94
for the Indian Canyon Drive Widening, City Project No. 01-25; and
2) Authorize the City Manager to execute all necessary documents.
STAFF ANALYSIS:
On June 15, 2011, the City Council approved an agreement with Griffith Company in the
amount of $2,865,821.50 (A6108). On October 19, 2011 Council authorized the City
Manager to approve cumulative change orders up to 10% of the contract amount. This
change order is the final change order for the project and takes the amount of
cumulative change orders over the 10% City Manager authorization limit. This change
order consists of additional asphalt placed due to a change in the cross section. The
amount of the change order is $188,511.94 bringing the cumulative total to $392,705.44
or 13%.
FISCAL IMPACT:
Sufficient funds will be available in Regional Measure A account 134-4497-50216.
ITEM NO. 2• Y
City Council Staff Report
September 5, 2012 - Page 2
Indian Canyon Drive Widening (City Project 01-25)
SUBMITTED:
Recommended by:
David J. Barakian
Director of Public Works/City Engineer
Approved by:
Thomas J. Wilson, Asst. City Manager David H. Re aek , Wanager
Attachments:
1. Contract Change Order
02
CITY OF PALM SPRINGS
CONTRACT CHANGE ORDER
To: Griffith Company. Date: June 12, 2012
12200 Bloomfield Ave. Project No: 01-25
Santa Fe Springs, CA 90670 Project: Indian Canyon Drive Widening
Tel: (562) 619-8344
Fax: (562) 864-8970 Change Order No: 22
Purchase Order 12-0262
Attn: Charlie Pessa Account 134-4497-50216
Agreement No: 6108
CHANGES IN WORK:
This change order provides for a contract quantity adjustment for Items 18 "HMA Type B".
CHANGES IN COST:
Increase in Contract Item at Contract Price
Item number 18, "HMA Type B,"2,198.39 Tons @$85.75 = $188,511.94 (+19.1%)
The estimated increase in cost resulting from this change order is $188,511.94.
CHANGES CONTRACT TIME:
There will be no adjustment in contract time by reason of this order.
SOURCE OF FUNDS:
Funds are available in the following account(s): 134-4497-50216
REASONS FOR CHANGE:
The original plan cross section for the overlay section from station 49+00 to 113+00 would have put the crown
of the roadway in the fast lane of the northbound traffic. Discussions were had with the City and the Contractor
to determine a potential solution to change the cross section to allow the crown of the roadway to be located at
the centerline of the road. After discussing all of the options, it was determined that the final overlay would be
placed thicker than the plan section to allow for an adjustment in the crown location. This was accomplished
by holding the 2" lift at the inside lane line and carrying a 1% cross fall to the centerline of the roadway. This
resulted in a varying depth overlay from 2"to 4" of HMA Type B. Additionally; there were wheel ruts that varied
in depth in the existing asphalt that added to the depth of the overlay. These ruts were typically 1" deep. This
accounts for the contract overage for Item 18, HMA Type B.
This Change Order requires Council approval. The total contingency approved for this project was 10% of the
original bid price. This change order increases the overage to 13.7% of the original bid price.
03
Contract Change Order No. _ ZZ
City Project#01-25, Indian Canyon Drive Widening
Page 2 of 2
SUMMARY OF COSTS:
Original Contract Amount: $2,865,821.50 Original Completion Dec. 30, 2011
This Change Order: $ 188,511.94 Days Added for this --0—
Previous Change Order(s): $ 204,193.50 Previous Days Added: —39—
Revised Contract Amount: $3,268,526.94 Revised Completion Mar 9, 2012
1 have received a copy of this Change Order and the above AGREED PRICES are acceptable to Contractor
Contractor Approval: ►^ I/`^ 2�i 6 / ISliz
a � Date
Printed Name and Title
City Approval:
Submitted By:
Resident Engineer Date
Approved By:
Director of Public Works/City Engineer Date
Approved By:
City Manager Date
Attest By:
City Clerk Date
Distribution:
Original Conformed Cow: Conformed- File Copy:
Contractor (1) Engineering Pay File (1)
City Clerk (1) Resident Engineer (1)
Procurement (1)
Finance (1)
04