Cq</FORN�P City Council Staff Report
Date: January 16, 2013
Subject: DISCUSSION OF LIQUIDATED DAMAGES AND APPROVAL OF
CONTRACT CHANGE ORDER No. 12 FOR THE BELARDO ROAD
BRIDGE AND ROADWAY, CITY PROJECT NO. 89-49.
From: David H. Ready, City Manager
Initiated by: Public Works and Engineering Department
SUMMARY
Approval of Contract Change Order No. 12, provides for an addition of 23 working days
for the placement of rock excavation as required by the Riverside County Flood Control
District (RCFCD) adjacent to the roadway and channel. The work has been completed
within the contractual time frame and no liquidated damages are proposed to be
assessed.
RECOMMENDATION:
1) Approve Change Order No. 12 to Agreement No. 6129 with G&M Construction at
no additional cost to the City but granting 23 additional working days.
2) Authorize City Manager to execute all necessary documents.
STAFF ANALYSIS:
Staff met with representatives of G&M Construction on January 9 along with Dokken
Engineering, the City's consultant contract administrator and inspector. At that meeting
G&M informed staff that the rock placement was required by RCFCD and agreed to by
the Tribe. City staff was not in on this discussion between G&M and RCFCD. Given that
placement after bridge construction was required, rather than rock removal prior to,
granting of additional time would be appropriate. Staff reviewed project records to
determine that 23 days should be granted and confirmed with RCFCD that the
placement was indeed required.
City Council Staff Report
January 16, 2013-Page 2
Belardo Road Bridge (City Project 87-49)
FISCAL IMPACT:
None, as Change Order No. 12 has no cost. Payment for the quantity of rock was
granted by Change Order No. 10.
SUBMITTED:
Prepared by:
David J. Barakian
Director of Public Works/City Engineer
Approved by:
David H. Ready, City Mawr
Attachments:
1. Contract Change Order 12
Contract Change Order No. 12
City Project#87-49, Belardo Road Bridge and Roadway Widening Project
Page 1 of 2
CITY OF PALM SPRINGS
CONTRACT CHANGE ORDER
To: G&M Construction Date: January 9, 2013
211 West Mesquite Avenue Project No: 87-49
Palm Springs, CA 92264 Project: Belardo Road Bridge Project
Tel: (760)322-6918
Fax: (760)778-6708 Change Order No: 12
Purchase Order 12-0332
Attn: George Marantz Account- PLHD 261-4491-50169
Account- IRR 261-4491-50297
Agreement No: 6129
CHANGES IN WORK:
No adjustment in work.
CHANGES IN COST:
No adjustment in cost.
CHANGES CONTRACT TIME:
Increase in Working Days due to Additional "Rock Excavation" (Item 14)
This Change Order No. 12 provides an adjustment of the time due to the increased quantity of Item 14, 'Rock
Excavation".
By reason of this order, the time of completion will be adjusted as follows: 23 Working Days Extension.
SOURCE OF FUNDS:
No additional funds are required by action of this Contract Change Order.
REASONS FOR CHANGE:
Increase in Working Days due to Additional "Rock Excavation" (Item 14)
It has been discovered that Contract Change Order No. 10 did not allow for G&M Construction additional
working days due the increased quantity of Item 14, "Rock Excavation". Contract Change Order No. 10
provided adjustment for the change in cost and an allowance for working days was not made because
placement incorporation into the job site was not required. However given that RCFCD requested rock be
placed in and adjacent to the channel additional working days are appropriate. It is noted that this Change
Order No. 12 provides for the completion of Item 14, and no additional work, cost, or time will be considered for
incidental costs incurred for these additional 23 working days.
Contract Change Order No. 12
City Project#87-49, Belardo Road Bridge and Roadway Widening Project
Page 2 of 2
SUMMARY OF COSTS:
Original Contract Amount: $2,221,366.06 Original Completion Date: April 26, 2012
This Change Order: $ 0.00 Days Added for this CCO: —23—
Previous Change Order(s): $ 398,087.18 Previous Days Added: —52—
Revised Contract Amount: $2,619,453.24 Revised Completion Date: August 9, 2012
1 have received a copy of this Change Order and the above AGREED PRICES are acceptable to Contractor
Contractor Approval:
Signature Date
Printed Name and Title
City Approval:
Submitted By:
Resident Engineer Date
Approved By:
Director of Public Works/City Engineer Date
Approved By:
City Manager Date
Attest By:
Citv Clerk Date