HomeMy WebLinkAbout2/20/2013 - STAFF REPORTS - 4A City Council Staff Report
February 20, 2013 - Page 2
Bicycle Lanes (CP 12-08)
2) Direct staff to initiate an amendment to the Circulation Element of the 2007
General Plan and Appendix F Non Motorized Transportation Master Plan,
adopted by Resolution No. 22077, to amend the designation on Via Escuela from
m a Class II to a Class III Bike Lane.
STAFF ANALYSIS:
With the approval of the City of Palm Springs Non-Motorized Transportation Plan, many
streets were identified for bicycle routes, which included proposed bicycle lanes
throughout the City. On September 19, 2012, staff provided the City Council a detailed
list of all proposed locations for Class II bicycle lanes and categorized them according to
priorities. With the limited amount of funding available, the City Council provided
direction to staff to include the following locations for bid.
• Baristo Road —from Avenida Caballeros to El Cielo Road
• Avenida Cabelleros —from Vista Chino Road to San Rafael
• Via Escuela —from Indian Canyon Drive to Sunrise Way
Because of the limited width available on Via Escuela, City Council asked staff to
consider shared bicycle lanes (Class III) on Via Escuela lieu of designated bicycle lanes
(Class II) in order to preserve parking. The use of shared lane markings, also known as
"Sharrows", was investigated by staff. Shared lane markings are used to assist cyclists
to avoid the impact of open doors of a parked vehicle. Shared lane markings should not
be placed on roadways that have a speed limit above 35 mph. They are typically used
on narrow urban streets that have extensive on-street parking. Shared lane markings
are used on Class III bicycle lanes. If used on Class II designated bicycle routes, the
City and CVAG would have to adopt a change in the Non-Motorized Transportation Plan
from a Class II designation to a class III designation. One of the criteria for on-street
bike routes that Caltrans recommends is the removal or restriction of street parking in
areas of critical width to provide improved safety. Therefore, with the use of Sharrows
on Via Escuela in lieu of designated bicycle lanes, the costs savings for this location will
be used to extend bicycle lanes at the following location:
• Avenida Caballeros —from Alejo Road to Tamarisk Road
Staff checks the paving list to make sure any bike lanes or routes painted are not on
streets to be sealed or repaved within 2 years. Baristo Road from El Cielo to Sunrise is
in good condition and it was overlaid in November 2008. Baristo Road from Sunrise to
Caballeros needs work and will be scheduled for overlay or reconstruction this summer
2013. The bike lane will not be put in until after the State grant is approved in October.
Avenida Caballeros was slurry sealed in 2010 and is in good condition. Via Escuela
from Indian Canyon to Sunrise Way was slurry sealed in April/May 2010. The
pavement is in good condition.
02/Zo/zo��
PoD�IYf 0 nj pa-
w O
Y N
� '40eemm'4
C441FOaN�P City Council Staff Report
Date: February 20, 2013 OLD BUSINESS
Subject: APPROVAL OF PLANS, SPECIFICATIONS AND ESTIMATE (PS&E)
AND AUTHORIZATION TO BID FOR BICYCLE LANES, CITY PROJECT
12-08 & MODIFY NON-MOTORIZED TRANSPORTATION PLAN
CHANGING THE DESIGNATION ON VIA ESCUELA FROM CLASS II TO
CLASS III
From: David H. Ready, City Manager
Initiated by: Public Works and Engineering Department
SUMMARY
The City of Palm Springs adopted a Non-Motorized Transportation plan which included
bicycle routes planned throughout the City. This project includes bicycle lanes to be
constructed at Baristo Road and Avenida Caballeros, and designate Via Escuela as a
Class III bicycle route using shared lane markings. The construction documents (Plans,
Specifications and Estimate) are completed and, in accordance with Section 7.03.040 of
the Procurement and Contracting Code the City Council is required to approve and
adopt plans, specifications and working details, and authorize the bid request for all
public projects in excess of$100,000. Approval of this project will allow staff to proceed
with this public project, with an estimated cost of$283,000.
On February 6th the City Council postponed the approval of the PS&E and Authorization
to Bid for the Project and brought up the following items for staff to analyze:
• The use of shared lane markings.
• The concern of proposed bicycle lane streets being redone with slurry seal,
overlay, or reconstruction after the bicycle lane is reconstructed.
RECOMMENDATION:
1) Approve the plans, specifications, and working details for Bicycle Lanes, City
Project 12-08, and authorize staff to advertise for bids.
ITEM NO.
City Council Staff Report
February 20, 2013- Page 2
Bicycle Lanes(CP 12-08)
2) Modify the Non-Motorized Transportation Plan changing the designation on Via
Escuela from Class II to Class III.
STAFF ANALYSIS:
With the approval of the City of Palm Springs Non-Motorized Transportation Plan, many
streets were identified for bicycle routes, which included proposed bicycle lanes
throughout the City. On September 19, 2012, staff provided the City Council a detailed
list of all proposed locations for Class II bicycle lanes and categorized them according to
priorities. With the limited amount of funding available, the City Council provided
direction to staff to include the following locations for bid.
• Baristo Road —from Avenida Caballeros to El Cielo Road
• Avenida Cabelleros —from Vista Chino Road to San Rafael
• Via Escuela —from Indian Canyon Drive to Sunrise Way
Because of the limited width available on Via Escuela, City Council asked staff to
consider shared bicycle lanes (Class III) on Via Escuela lieu of designated bicycle lanes
(Class 11) in order to preserve parking. The use of shared lane markings, also known as
"Sharrows", was investigated by staff. Shared lane markings are used to assist cyclists
to avoid the impact of open doors of a parked vehicle. Shared lane markings should not
be placed on roadways that have a speed limit above 35 mph. They are typically used
on narrow urban streets that have extensive on-street parking. Shared lane markings
are used on Class III bicycle lanes. If used on Class II designated bicycle routes, the
City and CVAG would have to adopt a change in the Non-Motorized Transportation Plan
from a Class 11 designation to a class III designation. One of the criteria for on-street
bike routes that Caltrans recommends is the removal or restriction of street parking in
areas of critical width to provide improved safety. Therefore, with the use of Sharrows
on Via Escuela in lieu of designated bicycle lanes, the costs savings for this location will
be used to extend bicycle lanes at the following location:
• Avenida Caballeros—from Alejo Road to Tamarisk Road
Staff checks the paving list to make sure any bike lanes or routes painted are not on
streets to be sealed or repaved within 2 years. Baristo Road from El Cielo to Sunrise is
in good condition and it was overlaid in November 2008. Baristo Road from Sunrise to
Caballeros needs work and will be scheduled for overlay or reconstruction this summer
2013. The bike lane will not be put in until after the State grant is approved in October.
Avenida Caballeros was slurry sealed in 2010 and is in good condition. Via Escuela
from Indian Canyon to Sunrise Way was slurry sealed in April/May 2010. The
pavement is in good condition.
02
City Council Staff Report
February 20, 2013- Page 3
Bicycle Lanes (CP 12-08)
The plans and specifications prepared by staff are ready for City Council approval and
subsequent advertisement for construction bids. Section 7.03.040 of the Procurement
and Contracting Code requires that for public projects in excess of $100,000 Council
approve and adopt the plans, specifications and working details, and authorize staff to
advertise for construction bids. The City Engineer's Estimate for this project is
$283,000. Approval of the recommended action will allow staff to proceed with bidding
of this project.
FISCAL IMPACT:
Funding for this project is made available through the Sustainability accounts (138-
1270-50000 [$50,000] and 138-1270-58033 [$50,0001) and potentially a grant in the
amount of $350,000 from the Environmental Enhancement and Mitigation Program
(EEMP). The City had applied for this grant in January 2013. If awarded, funds will be
available in the fall of 2013.
SUBMITTED:
Prepar y: Recommended by:
avat Khamphou David J. Barakian
Assistant Director of Public Works Director of Public Works/City Engineer
Approved by:
�9 -
Thomas J. W� on, Asst. City Manager David H. Ready, Cit r
03
i
AERIAL MAP OF PARKED VEHICLES ON VIA ESCUELA
,6
.�, .,gBl�i
- ... . -
- r. 9 I �
� MII
ti
i
Q v%ff
p�1 p
way. seg
ment
Indian an on to Sunrise rk on the 1 mile segment of Via Escuela fromC
A total of 10 vehicles were counted parked gYY g
above, between Hermosa Drive and Paseo De Anza, represents one tenth of a mile within the 1 mile segment, shows 6 parked
vehicles.
0
Q.
40'
I
PARKING I PARKING
I
I V V
CURB & GUTTER
u
I
VIA ESCUELA - SHARED LANE MARKINGS ("SHARROWS")'
BICYCLE LANES - CLASS III
CITY OF PALM SPRINGS, CALIFORNIA
05
GARNET AVE
Soaft4it
U.P.RAILROAD
�F PALM S
A
—a Uy N
1RINNEr MIX T` T
DESERT Q cqC I FD �P
Rxa�.AN» lA5 MUkS RD.
PAW 10
R RANRo In
SAN RAPAEL W.
FAMISS M. PAW
SW YIP[0 mMRt/WM
NOT TO SCALEqp CM
ROAD AFAORA RD. � 10
QB RA
RWWc
111 YA MESCIEtA
VWA'< aem ROAD 111 vmn cum mw 10
7 ice\
K _
xowra
TAO O . 8 \\\ \\\
SS8333iISO
\\
IL
3
O
AMMO ROM
-3
&�g NRPORT
P ��
TANWTZ CANYON RAT
U
RMR YAK NNww o j �'-1'' i
mlRn RARSIO ROM t�
SAYIMp
�» PaNs NNE i 10 =D
RAYON ROM ORN R Ys RAYON ROAD
AAIar sANDs
r
RNRnr DNNNEs Rao
91RfN pRl SO, Y
d d PN ORa E OWN 'sve yq�Wjjf
P ,e s�m�nn
saxaRA ROM
PAR O�RF
EAST PALM CANYON DRIVE a�yg
BDTWN
.ADRs
VICINITY MAP
LEGEND: PROPOSED BIKE LANES FOR CITY PROJECT NO. 12-08 111
® PROPOSED BIKE LANES INCLUDED ON FEDERAL SAFE
ROUTES TO SCHOOL PROJECT CITY PROJECT NO. 08-10 06