Subject: APPROVAL OF A NOTICE TO PROCEED FOR VEOLIA WEST
OPERATING SERVICES, INC., FOR THE CONSTRUCTION PHASE OF
THE TRICKLING FILTERS ARM REPLACEMENT, CITY PROJECT 13-15
From: David H. Ready, City Manager
Initiated by: Public Works and Engineering Department
SUMMARY
Approval of this item will authorize Veolia West Operating Services, Inc., ("Veolia") to
proceed to install replacements for two existing 140' arms on the two northerly trickling
filters at the Palm Springs Waste Water Treatment Plant.
RECOMMENDATION:
Authorize the Director of Public Works/City Engineer to issue a Notice to Proceed for
Veolia West Operating Services, Inc., in the amount of $408,625 for the construction
phase of the Wastewater Treatment Plant Trickling Filters Arm Replacement Project,
City Project No. 13-15.
STAFF ANALYSIS:
The City and Veolia continue to coordinate on various capital improvement projects at
the City's Wastewater Treatment Plant (WWTP). The WWTP was initially built in the
1950's with several upgrades during the 1980's. The original trickling filter arms were
installed in 1978 and have been in almost continual use for over 34 years. In 2002,
existing lower rotary bearing units were replaced with mast type center bearing
assemblies. At that time the arms were assessed and it was determined that they were
not in need of replacement but would need to be replaced at a later date. Ten (10)
years later that time has come. This project is part of the priority project list from the 20-
Year WWTP Capital Repair and Rehabilitation Plan approved by Council on April 21,
2010.
Per agreement with Veolia, "the City agrees not to solicit or retain any Person other than
Veolia to design, construct, manage or supervise any Capital Project without inviting
Veolia to make a first proposal to do so . . ." Their proposal follows this staff report.
ITEM NO. 04
City Council Staff Report
April 17, 2013- Page 2
Veolia Notice To Proceed (CP13-15)
FISCAL IMPACT:
Sufficient funds are available in account No. 420-6800-57028 (Trickling Filter Rotator)
and account number 420-6800-50000 (Unscheduled Capital Projects).
SUBMITTED:
Prepare Recommended by:
Savat Khamp u David J. Barakian
Assistant Director of Public Works Director of Public Works/City Engineer
Approved by:
Thomas J. WilI, Asst. City Manager David H. Ready, City MWaag
Attachment:
Veolia's Proposal
02
QVEOLIA
WATER
February 6, 2013
City of Palm Springs
Waste Water Treatment Facility — Trickling Filter Arm Replacement
ST-ME-05 and ST-ME-06— Project Proposal
Veolia Water West Operating Services, Inc. is pleased to submit the following proposal to
install replacement arms for two existing 140' arms on the two northerly trickling filters at the
Palm Springs Waste Water Treatment Plant. The technical name for the trickling filters that
need the arm replacement are ST-ME-05 and ST-ME-06. The original arms were installed in
1978 and have been in almost continual use for over 34 years. In 2002 the existing lower
rotary bearing units were replaced with mast type center bearing assemblies. At that time the
arms were assessed and it was determined that they were not in need of replacement but
would need to be replaced at a later date. 10 years later that time has come. The project
includes:
Replacement Rotary Distributor Arm Assembly
Two (2) primary & two (2) secondary arms made of %4° thick carbon steel with high density
galvanizing including upper and stabilizer bearing assemblies.
All hardware and tie rods (304 stainless steel) and gaskets necessary to install the anus.
Shipping
Installation
1 year warranty
Construction Manaaement Services
Coordinate day to day construction activities with plant operations.
Monitor daily progress.
Monitor construction schedule.
Provide monthly reports.
Track progress.
Monitor construction safety.
General Liability Insurance
Veolia general liability insurance
Ovivo is the sole source for the arm replacement. Included with our proposal is their sole
source letter.
Veolia Water West Operating Services,Inc.
4375 E.Mesquite Ave 0
Palm Springs,CA 92264
www.veoliawaterna.com
Palm Springs WWTF Trickling Filter Arm Replacement 2
Timing
The trickling filters are a biological process. When the arm operation is stopped or hindered
(the arms no longer operate as intended) the biological component of the process dies off
from lack of water and food. During the summer the process can be started back up in
approximately 30 days, once the arms are functioning as intended. At the plant we need at
least two trickling filters on line and one operating as a backup during the non-peak season
(summer). The attached schedule shows that there is a long lead time for the off-site
manufacturing of the arms and equipment. That lead time along with the 30 day minimum
gap (for the biological process to start back up) between the first arm installation and the
second installation results in a long overall time to get the project completed before the start
of the peak season.
Our base not to exceed fee for the project is$408,626.
Thank you for the opportunity to present this proposal for the arm replacement for two
trickling filters. We look forward to working with you on this project. Please do not hesitate to
contact me should you have any questions or need additional information on this proposal.
Sincerel
Jeff Phillips
Senior Project Manager
Veolia Water West Operating Services, Inc.
949-878-8461 -cell
Veolia Water West Operating Services,Inc. O
4375 E Mesquite Ave.
Palm Spnngs,CA 92264
w .veoliawateme.com 04
0I PS F Tmlhnu FOYrNm aen%nt ....WWfi 8 0]10N13 vis Pe
Proleq Name: PSWW3 -l-
Job rvumber Master
Lor'ew� JOO Cost F .w All e
p�ppp®I Mared Versl n 19 CM/oT Palm Springs
D R =, PossvroN(1E11)
eamoft v
CONTINGENCY MARKUP
Como 6glEulwnb m:', } T}y," Estimate Tot01 S 408,625
EnO,neerMgG .fiwn6:.y,.. . - Mark Up E 81,ISO
Imetwmpam SeMceY �
MaWald Epayan.m ..4i
,a o
Tn aW WnS
Tm¢s BOMY ONer S:-
SYeLYY
TOTAL.
• • ��- Stalk TOY,
1 pempWw�S batbla _
101 D1 Sae Remeae80n Subronbxlms E -
S P E 0 %- A
1@ EeNmmlk Babppntr clga E - $ E - �`e - am
103 CMaCailneM SubcNiBacpws
158 Gamnm Suhcanbatws $ Szl'm S - E 41,150 370.3% 90.0%
105 M.M*al M9a11a8on SubaanB. E - E - E 0.0%
-
108 EleNkal InSMIIaGOn Bubamcrors $ $ - E - �a - 00%
10] Fieltl EreatM Tanks Subcanbactors E - $ - E - 00%
108 MvzlMneouslmYllalbn Su%wibacbxa E - $ - E 00%
1S0 PraYaebnNSaeKeY $ - $ - E _ - 00%
180 SaMpo E E S 0.0%
SUBTOTPI 1-77-7 3M WB%
1 LeM wa,tuO T tzl
210 EleNenl u _ E - E - E -
0.0%
220 k8armm n en[ E - E - E - - 0.0%
230 ONer a am 8 E 0.0%
e, s ;:f T xm ".�. .. �;'an 0.0%
' Soo• Me E GeM E E NW* To l
305 SeYx Eb E ],35] E _ E - 1 m
310 E 5�21 $ - E ¢ ],35] 1S%
MD 5281 13%
330 Cd�Yca0n S - E - E - - Om B
380 A $ $ - E 'j- - 1
$ 6,753 $ - E - S,]53 3B
350 E - - am
350 &Cwreeu[4on E ta, E - E - 1e,E - E - 0.a%
370 x $ - $ - E - - Oft380 Labar-Commveam E - $ - a - - a
39D O mtlons labor $
8 E 0m
0%
SUBTOTAL S z `P.. .. `d ; �,0.k, n 7.195 fl8%
WO Tlaald �-�- CaMnnxrcr 1N1k ua TO l
800 TnrvNd Otlw S E - S
S $ E 00%
•aaxe g tttLs nenev Mark., L
610 Ta•eld _ _
00.0%
61D Tmveld Amer S - S Conin E '"'
511BTGTAL ,.,0 2sh r,. ram.. rz _ 1 0.0%
Da F -m Q) 1 ca%ae.na. Malkffi L
sM SOIL S E - E - - Om
- E - yf.., - 0.0%
500 6E BOMe $ - $ - E - $z=' - 0.0%
500 E - $ - E - 00%
500 Cemml 8®nahe E 1,080.00 E - E - e,080 t p%
500 SeMad Ut $ - E - E - - 0096
500 limmTenrt Fem E - E - E - 0.0%
500 SauBwn CeffarnM Erman 4%YIMOon E - $ 0.0%
SUBTOTAL .
Cnrt C of cQ<Caal CmBnaen Ma k Tp l
800 General ElM LmY E - E E 0.0%
800 CM S - E - E - 0.0%
810 FMMVeNM S - S E ' '... - 0.0%
Imo sdnr cpa� a -
SUHTGTu:'
628.68. 100.0%
Coat VerMOagon True 05
summery sneer P�1 aC1 l�
Job Cost Estimate
Subcontractors u`EOLIA
xi/ATER
Job No. Project Name Revision
•.
0 PS YYWTF Trickling Fiker Arm Replacement 0 2/6/2013 v1 a vs e
Instructions:
Input Only Light Yellow Colored Cells
11 Subcontractors
Cam an Name/Descriction OtinnfiN I Unit Measure I Unit Cost Extended Cost
100 IDemolition Subcontractors
603010 1001 - $ _ $ _
603010 1002 - _ $ _ $ _
503010 1003 _ $ _ $ _
603010 1004 _ $ $ _
603010 Igoe - $ _ $
Total Demolition $
Company Name/Descr tion Quan' Unit Measure Unil Cost 6dended Cost
101 Site Remediation Subcontractors
603010 1011 _ $ _ $ _
603010 1012 - _ $ _ $ _
603010 1013 - _ $ $
603010 1014 - $ $
603010 1016 - _ $ _ $ _
0.00 Total Site Remedtation $
Cam an Name/Descn lion I n....tity I Unit Measure I Unit Cosi Extended Cost
102 Earthwork Subcontractors
603010 1021 - _ $ $
603010 1022 - _ $ - $ -
603010 1023 - _ $ $ -_
603010 1024 $ $
603010 1025 $ $
Total Earthwork $
Conquam,Name/Descri tion I Quanti Unit Measure Unit Cost Extended Cost
103 ClAUConcrets Subcontractors
603010 1031 - _ $ $ _
603010 1032 - _ _ _
603010 1033 _ $ _ $
603010 1034 _ $ _ $ -
603010 1035 - $ $ -
Total Demolition f
Com an Name/Descti tion Quanli 10 Unit Measure Unit Cost Extended Cost
re 4 GeneUBaildln Subcontractors
603010 1041 Ovivo 1.00 1 $ 329,200.00 5 329,200,00
603010 1042 _
$603010 1043
$603010 1044 _
603010 t5 - $
o4
Total Germ uilding 329,200.00
Compam,Name/Descripbon 0IIAntinj Unit Measure Unit Cast Extended Cost
105 Illilechanical Installation Subcontractors
603010 1951 _ $ _ $ _
603010 1052 - _ $ _ $ _
603010 1063 - _ $ _ $ _
6030110 1054 - _ $ _ $ _
603010 1055 - $ _ $ _
Total Mechanical $
Com n Name/Descni tion uan i Unit Measure Unit Cost Extended Cost
106 Electrical Installation Subcontractors
603010 1061 _
603010 1062 $ _
603010 1063 $ _
603010 10" $ _
603010 1065 $ _
Total Electrical $
Company Name/Description Ouantitv Unit Measure Unit Cost Extended Cost
107 Field Erected Tanks Subcontractors
603010 1071 _ $ $
603010 1072 - _ $ $ _
603010 1073 - _ $ _ $
603010 1074 - _ $ _ $ -
603010 1075 - $ _ $ -_
Total Tanks $
Company Name/Descri tion Quan- Unit Measure Unit Cost Extended Cost
108 Miscellaneous Installation Subcontractors
603010 Iasi _
$
603010 1082 _
603010 1 1053 _ _ $
$ $
06
1.0 Subcontractors Page 1 ol2
Job Cost Estimate
Subcontractors -' EOLIA
AIATER
Job No. Project Narbe Revision Date JCE Model
A PS V WTF Trickling Fifer Arm Replacement 0 216/2013 w.a Ps
coons:
1110WAbnly Light Yellow Colored Calls
603010 1094 - -
§ $
603010 1086 - $ S
603010 1086 - -$ $
- -
603010 1087 - $ $ -
603010 1088 - $ $ -
603010 1089 - $ $
603010 10" - $ $
603010 1091 - $ $ -_
603010 1092 $ $
603010 1093 - § $
603010 1094 - - $ - $ -_
603010 1095 - $ $
Total Misc.Subcontractors f
1 Professional
Com n Name/Descri 'on QuantityUnit Measure Unit CostEEdendedoat150 Professional Services603125 1601 _603125 1602 _603125 1603 _603125 1604 _603126 1605 _803125 1606 603126 1607 -
W3125 1608 -_
603125 1509 $
603126 1510 $ _-
603126 1b11 S
60 _
3125 1b12 $ _
603126 1513 $ _
W3125 1514 $ _
M125 1616 $ _
Total Professional Services $
Company Name l Description Quantib, I Unit Measure Unit Cost Extended Cost
iInter-Company Services
160 Inter-Company Services
603020 1601 $ _
603020 1602 $ $
603020 1603 _ $ _ $ -
603020 1604 _ $ $ -_
603020 1605 - _ $ _ $ _
603020 1606 _ $ $
603020 1607
603020 1608 _ $ _ $
603020 1609 $ g
603020 1610 $
Total Intercompany Services 1$
ENE)OF SHEET
07
1.0 Subcontractors Page 2 of 2
LABOR SCHEDULE(HOURS) ®®�� • , ®��
Labor-
•• - • o0000000000
to• - = o0000000000
r
Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-t3 YR1
Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10 Month 11 Month 12 TOTAL
PM No. 1 $ $ $ $ $ $ $ $ $ $ $
.
PM No. 2 $ - $ - $ $ - $ - $ - $ - $ - $ - $ $
Senior Project Management
SR.PM No. 1-Jeff Phillips $ $ 3,503.20 $ 350.32 $ 350,32 $ 350.32 $ 350.32 $ 350.32 $ 350.32 $ 1,751.60 $ $ 7,356.72
SR.PM No. 2 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $
Principal
Principal No. 1-Fadi Alabbas $ $ 2,405.20 $ 481.04 $ 481.04 $ 481.04 $ 481.04 $ 481.04 $ 481.04 $ $ $ 5,291.44
Principal No.2 $ - $ $ - $ - $ - $ - $ - $ _ $ - $ - $ -
Administration
Admin. No. 1 $ $ $ $ $ $ $ $ $ $ $
Admin. No.2 $ - $ - $ - $ - $ - $ - $ - $ - $ _ $ - $ -
Construction Manager
CM No. 1 $ $ $ $ $ $ $ $ $ $ $
CM No. 2 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $
Assistant Project Manager
Asst Pro Manager-Michelle McLa $ $ 1,350.50 $ 675.25 $ 675.25 $ 675.26 $ 1,350.50 $ 675.25 $ 1,350.50 $ $ $ 6,752.50
Asst Proj Manager No.2 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ -
Sr.Construction Manager
Sr. CM No. 1-Jeff Phillips $ $ $ $ $ $ 5,917,60 $ 1,479.40 $ 5,917.60 $ 1,479.40 $ $ 14,794.00
Sr.Construction Manager No.2 $ - $ - $ - $ - $ - $ $ - $ $ - $ - $
Sr PM w/travel
Sr PM w/travel No. 1 $ $ - $ $ $ $ $ $ $ $ $
Sr PM w/travel No. 2 $ - $ - $ - $ - $ - $ $ - $ _ $ - $ - $ -
X
X $ $ $ $ $ $ $ $ $ $ $
Labor-Commissions
Commissions $
Operations Labor
O s Resource No. 1 $ $ $ $ $ $ $ $ $ $ $
O s Resource No.2 $ $ $ $ $ $ $ $ $ $ $
O s Resource No.3 $ $ $ $ $ $ $ $ $ $ $
Ops Resource No.4 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ -
O
cU 3.0 Labor Schedule Page 1 of 1
Job Cost Estimate ® VEOIfA
2010 Palm Springs CPM
Labor Rates WATER
.. No. Project Name Revision Date JCE Modell
s « a
CPM Group
2012 City of Palm Springs Rates By Class
Labor Burdon Indirect
Portion Portion OH/Hr FBC
601025 601382 607670
Rates
Project Manager(PM) 3000 $ 161.59 $
Sr. Project Manager(SPM) 3050 $ 175.16 $ -
Principal 3100 $ 240.52 $ -
Admin 3200 $ 71.11 $ -
Construction Manager(CM) 3300 $ 111.74 $ -
Assistant Project Manager 3400 $ 135.05 $ -
Sr.Construction Manager(SCM 3500 $ 147.94 $ -
Sr. PM w/Travel 3600 $ 189.46 $ -
X 3700
Labor Burdon Indirect
Portion Portion OH/Hr FBC
601025 601382 607670
Rates
Project Manager(PM) 3000 100-00% 0.00% 0.00% 100.00%
Sr. Project Manager(SPM) 3050 100.00% 0.00% 0.00% 100.00%
Principal 3100 100.00% 0.00% 0.00% 100.00%
Admin 3200 100.00% 0.00% 0.00% 100.00%
Construction Manager(CM) 3300 100.00% 0.00% 0.00% 100.00%
Scheduler/Estimator 3400 100.00% 0.00% 0.00% 100.00%
Sr.Construction Manager(SCM 3500 100.00°k 0.00°G 0.00% 100.00%
Project Engineer(PE) 3600 100.00°� 0.00% 0.00% 100.00%
X 3700
END OF SHEET
2010 Labor Rates Page 1 of 1 10
Ovivo USA,LLC
4255 Lake Park Blvd.,Suite 1.00 Telephone:801.931.3000
Salt Lake City,Utah Facsimile:801.931.3080
N 71".,C,I It 1 V 'c-i2C
8 412 0-9 2 0 1
USA www.ovivowater.com
June 13, 2012
City of Palm Springs, CA WWTP
Palm Springs, CA 92264
Re: EIMCO Water Technologies Equipment
To Whom It May Concern:
Please be advised that Ovivo USA, LLC (formerly EIMCO Water Technologies
- EWTTM) is the exclusive distributor and sole manufacturer of all EIMCO
parts and equipment in the municipal market. Our exclusive agent for this
equipment in your geographic area is:
Coombs-Hopkins
5411 Avenida Encinas
Suite 250
Carlsbad, CA 92008
Matt Rebmann
760 931-0555 - Office
760 579-9411 - Mobile
760 931-9115 - Fax
Please direct all inquiries for municipal water treatment equipment to above
agent.
Very truly yours,
Ovivo USA, LLC
n
Chad Layton
Territory Development Manager
U.S. Rebuild Group
I �
Proposal No. 012913—CL
Proposal Date:January 29,2013
7777 Page 1 of 9
V0
er to life
PREPARED FOR
Palm Springs WWTP
PG lot Sing 5 , 0/4
Attention: Jeff Phillips
Sr. Project Manager
AREA REPRESENTATIVE
Coombs Hopkins
Matt Rebmann
(760) 579-9411
matt@coombshopkins.com
PROJECT
Replacement Arms for Two Existing
140'dia. EWTr"' Mast Type Rotary Distributors
Serial #22405 & BAP1384
PREPARED BY
Ovivo USA, LLC
4255 Lake Park Blvd.—Suite 100
Salt Lake City, Utah 84120
Chad Layton
Phone (801) 931-3240
Fax (801) 931-3090
chad.layton@ovivowater.com
PROPOSAL
Ovivo USA,LLC
4255 Lake Park Blvd.•Suite 100•Salt Lake Gty,Utah 94120-8201 USA
Tel:(801)931-3000•Fax:(801)931-3080
www.ovivowater.com 12
ovivo Proposal No. , —CL
Proposal Date:January
29 29 2013
Bringing water to life Page 2 of 9
PROJECT SUMMARY:
Ovivo USA, LLC is pleased to offer the following proposal to provide materials and labor for two
(2)sets of direct replacement rotary distributor arm assemblies for two(2)existing 140'dia.
mast type rotary distributors. Rotary distributors originally manufactured by Eimco Process
Equipment Company in 1977(2)and 1981(2),serial numbers of units are 22405&BAP-1384.
Ovivo is including labor for removal&installation in this proposal.
Replacement Rotary Distributor Arm Assembly
Ovivo will manufacture and supply two(2)complete sets of distributor arms to include the
following:
• Two(2) primary&(2)secondary arms, 1/4"thick carbon steel. All arms HDG
• Horizontal tie rods(304 SS)
• Vertical tie rods(304 SS)
• Turnbuckles,fittings,clamps etc.(304 SS)
• Assembly hardware(304 SS)
• High density polyethylene spreaders and orifice plates;including leading edge orifices
• Gaskets-neoprene
• Shear gate assembly
• Upper bearing assembly
• Stabilizer bearing assembly
• Engineering
• Freight
• One(1)year warranty on parts and installation
Items Not Included
• Center mast or center well
• Anchor bolts
• Influent line,cover plates or vent pipes
• New 0&M manual
• Filter media or media supports
• Tank or concrete center pier
• License fees
Labor Services:
Ovivo will supply supervision, labor,service and equipment necessary to complete this project.
We Include:
• Site mobilization
• Removal of existing rotary distributor arms
PROPOSAL
Ovivo USA,LLC
4255 Lake Park Blvd.•Suite 100•Salt Lake City,Utah 84120-8201 USA
Tel:(801)931-3000•Fax:(801)931-3080 13
www.ovivowater.wm
OVIVO
Proposal No. —CL
Proposal Date:January
29 29, 2013
Bringing water to life Page 3of9
• Installation of new rotary distributor arms
• Removal of existing upper bearing&stabilizer bearing
• Installation of new upper bearing&stabilizer bearing
• Support of superstructure as needed
• Crane, mats, rigging and related equipment
• Demobilization of personnel and equipment
• One shift, 10 hours per day
• Field Service -factory trained Ovivo technician on site for(2)trips of(1)day each to
witness start-up,assist with check out and adjustment of newly installed rotary
distributor arms,and to validate the (1)year warranty
Items NOT Included
• No draining or cleaning of tank
• No electrical installation or alteration of existing electrical supply
• No finish or touch up painting
• No lubricants
• No disposal of any old lubricants/fluids
• No overtime work hours or removal of old debris
Pricing for materials&installation for(2)units complete as described above..............$321,000.00
Lead time is 8-10 weeks for materials
Installation of new arms anticipated at 3-4 days per rotary distributor
California sales tax(9%) on replacement parts................................................................$8
ao
Total......................»....................................................................................................... ......$329,200 00
Jobs will be performed one at a time,approximately one month apart.
Cost per rotary distributor...............................................................................................$164,600.ao
DELIVERY
Ovivo intends to ship all Products as indicated above after receipt of approved purchase
order and approved submittal drawings from Purchaser. However, the date of shipment
of the Products represent Ovivo's best estimate, but is not guaranteed, and Ovivo shall
not be liable for any damages due to late delivery.The Products shall be delivered to the
delivery point or points in accordance with the delivery terms stated in this proposal. If
such delivery is prevented or postponed by reason of Force Majeure, as defined in
Ovivo's standard terms and conditions of sale, Ovivo shall be entitled at its option to
tender delivery to Purchaser at the point or points of manufacture, and in default of
Purchaser's acceptance of delivery, to cause the Products to be stored at such a point or
PROPOSAL
Ovivo USA,U.0
4255 Lake Park Blvd.•Suite 100•Salt Lake City,Utah 94120-8201 USA
Tel:(801)931-3000•Fax:(801)931-3080 1
w .ovivowater.mm 1
CL
OVIVO
Proposal No. 29, —13Proposal Date:January
29 2013
Bringing water to life Page 4of9
points of manufacture at Purchaser's expense. Such tender, if accepted, or such storage,
shall constitute delivery for all purposes of this proposal. If shipment is postponed at
request of Purchaser, or due to delay in receipt of shipping instructions, payment of the
purchase price shall be due on notice from Ovivo that the Products are ready for
shipment. Handling, moving, storage, insurance and other charges thereafter incurred
by Ovivo with respect to the Products shall be for the account of Purchaser and shall be
paid by Purchaser when invoiced.
PRICING TERMS
All prices quoted are in US Dollars. Prices are good for 45 days. After expiration of the
pricing effective period, prices will be subject to review and adjustment. Prices quoted are
FOB point of shipment, with freight included to an accessible point nearest the jobsite.
Federal, state or local sales, use or other taxes are not included in the sales price.
PAYMENT TERMS
Payment terms are: One hundred percent (100%) payment due within thirty (30) days
after Purchaser's receipt of invoice. Invoice will be submitted after all materials have been
received at the job site or they have been successfully installed by an Ovivo contractor and
the field service check-out and start-up procedure is finalized. Credit is subject to
acceptance by the Ovivo Credit Department.
Purchaser shall remit payment for proper invoices received from Ovivo in accordance with
the payment terms stated above even if the Purchaser has not been paid by the
Purchaser's customer (the "Owner"), if Purchaser is not the end-user of the Products.
Payments are due within thirty(30) days after Purchaser's receipt of invoice. Overdue and
unpaid invoices are subject to a service charge of 2%per month until paid.
If Purchaser requests or causes cancellation, suspension or delay of Ovivo's work,
Purchaser shall accept transfer of title and pay Ovivo all appropriate charges incurred up
to date of such event plus Ovivo's overhead and reasonable profit. Additionally, all
charges related to and risks incidental to storage, disposition and/or resumption of work
shall be borne solely by Purchaser. Full payment for all work shall be due and payable
thirty(30) days from the date work is placed into storage.
TAXES
Federal, State or local sales, use or other taxes are not included in the sales price. Such
taxes, if applicable,shall be for Purchaser's account.
PROPOSAL
Ovivo USA,LLC
4255 Lake Park Blvd.•Suite 100•Salt lake City,Utah 84120-8201 USA
Tel:(801)931-3000•Fax:(801)931-3080 15
www.wv water.mm
OVIVOProposal No.ary 29, 013Proposal Date:January 29, 2013
Bringing water to life Page 5 of 9
BACKCHARGES
In no event shall Purchaser/Owner do or cause to be done any work, purchase any services
or material or incur any expense for the account of Ovivo, nor shall Ovivo be responsible
for such work or expenses, until after Purchaser/Owner has provided Ovivo's PROJECT
MANAGER full details (including estimate of material cost and amount and rate of labor
required) of the work, services, material or expenses, and Ovivo has approved the same in
writing. Ovivo will not accept Products returned by Purchaser/Owner unless Ovivo has
previously accepted the return in writing and provided Purchaser/Owner with shipping
instructions.
"PURCHASE ORDER SUBMISSION•"
In an effort to ensure all purchase orders are processed timely and efficiently, please
submit all purchase order documentation to the following department and address:
Attn:Order Entry Administrator
Ovivo USA, LLC
4255 Lake Park Blvd.,Suite 100,
Salt Lake City, Utah 84120
Fax#:801-931-3080
Tel.#:801-931-3000
ADDITIONAL FIELD SERVICE
When included and noted in the Product pricing of each proposal item, Ovivo will supply the
service of a competent field representative to inspect the completed installation and
adjustment of equipment, supervise initial operation, and instruct Owner's personnel in the
operation and maintenance of each proposal item for the number of eight (8) hour days.
Notwithstanding Ovivo's performance of the above-referenced services, Ovivo shall not be
held liable for any faulty workmanship or other defects in the Products' installation, or for
other goods and/or services, performed by third parties unless such goods and/or services are
expressly included under Ovivo's scope of work.
If additional service is required over and above the Field Services described above, it will be
furnished to the Purchaser and billed to him at the current rate for each additional day
required, plus travel and lodging expenses incurred by the service personnel during the
additional service days.
It shall be the Purchaser's responsibility to provide for all necessary lubrication of all
equipment prior to placing equipment in operation. All equipment must be in operating
condition and ready for the Field Service Engineer when called to the project location. Should
PROPOSAL
OVivo USA,LLC
4255 Lake Park Blvd.•Suite 100•Salt lake City,Utah 84120-8201 USA
Tel:(901)931-3000•Fax:(801)931-3080 1 �^
www.ovi4owater.com i
OVIVO Proposal No.January
29, —CL
Proposal Date:January 29 2013
Bringing water to life Page 6 of 9
the Contractor not be ready when the Field Service Engineer is requested or if additional
service is requested,the Ovivo current service rates will apply for each additional day required.
Plus, travel and lodging expenses incurred by the service personnel during the additional
service days.
SURFACE PREPARATION AND PAINTING GENERAL INFORMATION
If painting the Products is included under Ovivo's scope of work, such Products shall be
painted in accordance with Ovivo's standard practice. Shop primer paint is intended to serve
only as minimal protective finish. Ovivo will not be responsible for condition of primed or
finished painted surfaces after equipment leaves its shops. Purchasers are invited to inspect
painting in our shops for proper preparation and application prior to shipment. Ovivo
assumes no responsibility for field service preparation or touch-up of shipping damage to
paint. Painting of fasteners and other touch-up to painted surfaces will be by Purchaser's
painting contractor after mechanism erection.
Clarifier motors, gear motors and center drives shall be cleaned and painted with
manufacturer's standard primer paint only.
It is our intention to ship major steel components as soon as fabricated,often before drives,
motors and other manufactured components. Unless you can insure that shop primed steel
shall be field painted within thirty (30) days after arrival at the jobsite, we encourage you to
purchase these components in the bare metal (no surface prep or primer)condition.
Ovivo cannot accept responsibility for rusting or deterioration of shop applied prime coatings
on delivered equipment if the primed surfaces have not been field painted within thirty (30)
days of arrival at the jobsite using manufacturers'standard primers. Other primers may have
less durability.
GENERAL ITEMS NOT INCLUDED
Unless specifically and expressly included above, prices quoted by Ovivo do not include
unloading, hauling, erection, installation, piping, valves, fittings, stairways, ladders,
walkways, grating, wall spools, concrete, grout, sealant, dissimilar metal protection,
oakum, mastic,field painting, oil or grease, electrical controls, wiring, mounting hardware,
welding, weld rod, shims, leveling plates, protection against corrosion due to unprotected
storage, special engineering, or overall plant or system operating instructions or any other
products or services.
PROPOSAL
Ovivo USA,LLC
4255 Lake Park Blvd.•Suite 100•Sait lake City,Utah 84120-8201 USA
Tel:(801)931-3000•Fax:(801)931-3080 t T
w .oviv terxom i
OVIVO Proposal , —CL
Proposal Date:January
29 29 2013
Bringing water to life Page 7 of
MANUALS
The content of any and all installation, operation and maintenance or other manuals or
documents pertaining to the Products are copyrighted and shall not be modified without
the express prior written consent of Ovivo. Ovivo disclaims any liability for claims resulting
from unauthorized modifications to any such manuals or other documents provided by
Ovivo in connection with the Project.
Attachments:
Ovivo USA, LLC General Terms and Conditions,QFORMEWT 0115-02031 Rev H
Ovivo USA 2010 North American Field Service Rate Schedule
PROPOSAL
ovivo USA,LLC
4255 Lake Park Blvd.•Suite 100•Saft lake City,Utah 84120-8201 USA
Tel:(801)931-3000•Fax:(801)931-3080 f Q
www.ovivowatermm 1 Q
OVI V
® CONDITIONS Proposal No. 29, —13 TERMS& proposal Date:January
29 2013 Bringing water to life Page 8 of 9
1.ACCEPTANCE.The laoposel of OWO USA,LLC C`SELLER'),as well m Wren mmm and rorditons of spplo,iblc to We Proms mpplkd.
sale(collxuvclY We"Ageamt'7,canmbmv SEI,LER's ruvvxmd odor d'gds and asmciamd caviar,vd 11,SOFVIiki E PURCHASER"I Eeve a tmexclavc and nonbmsfaaMe license to use soot wfmmaton
PURCHASERSs accelimL oCWp of«is c�pealY limilMmtlr emn oLlhe Agreement The cope and bon pooEssin pogo®suppliW by SELLER with der:Proctors. PURCHASER acLwwlMgs tlut nab pro erns and
sort oaostoovs of this Agmmmr opruml the mtim oHL by SELLER and supnsEe W poor solicirtions, the infaoaEm cma«d Nvca is Confihad htfwmstiun sod ogees:a)to b turf or d&trek pm dogma
Oisuaons,aprmmm,whnNWngs evil opeamapom bawmn We paves. Air, cope L tarots sort 11.PATENT INDEMNITY.SELLER soft deknd m m own Es,,ros,my.Sit imtiMd amw.a PURCHASER
cmAtioM i&luded or PURCHASER's acceptsocv/pvcluz«tic the ere or addition to«diRcmt Sour this bswd opus clsrstis"SELLER'S Psduct hvwdv in soil a itF1L of any valid
Agrcmmt. orsh,rgafed sPpamns distorts of soot Unied Stet ryEst m d and wsmg as a de bu,of this ABmmetL d mlidie)
L DEW VERY. Am rmaanm rt1aWg male time of dip®t of the Protlm¢(a hfioei bebw)rtpcxm prv�tly m String sod pum ell mf«madaq amamrc,mtl mk Worry m defad and rWc Ur Same,and
SELLERS bon rstimec,but a or g osaad,and SELLER"I sot Is,IodIk far,my dmugm don b lam SELLER Sall ia4vmi6 rh PURCHASER n M etch chin of inRiv m.FmWamwc,W ra¢the uSe of
OrSELL Thc proprcm Supbe his is We ddivay pdutoordby msc cWFoOcM desOrs soot Camel WC Producs is®)oimlw nrhmtaw cam SELIERalhmsiahcros iutmiable.SELLERs(b)Mitsown
SELLER R's proposal, if sorts oPm is prtve«M L poo PLIR by lSER ofFace r or
Fr(a ofGoN below), — offid Wwenov,(e)Prod ,(r)t PURCHASERlit,i.[m scour, uswg tle Praducu,(b)repl-the
SELLER soup he EEhct m its s sss m tevder t,,O y t m PURCHASER m the dorm a pours of manoOmre, same with nw-mst tpng Prodmu,(c)omdify the PmWat m rt banes SELLER
Arill or,L,omove We
Of iv defmlt of RMCH SEER ccepurceSorl, vaymcw•a the,msorbmbe CasMmmchapointoory SO PMCIErostossis aa ofua We rood,SpriMIt,
so, chmgo anddepr troo.SEL(s)i,o sot beliab4 fL,and
Of monu6cnOf m PURCHASERS cproo. .Such corder,if occstm4 L n�h wage,step,to&I,delivery fL PURCHASER shill ur thrit fo SELLER f.ary claim W SELLER,(E rt.. b(a)de m i We PmWmm fL
all puyoss Of this sgeemmt.If the lxot is posruc I rcym4 m PURCHASER L elm m delay r taryR of SY puryoss dher Wm Non for which i[was G&i�d by SELLER @)mmptsom wiW egWpmaN logos M
shippwg imtrucEma pe}mem of the purohme dice shall be due m mEa Gam SELLER Wm tlm Prdurs>< fiodshod by SELLER a(c)ua of We Prodmm w canGrWim vaW my otter&uipvam. The f goivg sores
rtNy kr Stipl Pro Haodfipg SO,
iii, &e,ioav PURC aM csorgs sti Iss r iamrtd by SELLER wild We mlc liE p ofSELLERIlf.S b, to
t1ii, of mthreryer m sort o for.
res in the Probb¢shall be 6t tlrc mcmm of PURCHASER and steal h dirt by PURCHASER Stem ls.GENERAL MD PLI Y SiSER m Me tights obli tockm avd SELLER,
mS of liabilities of tit,pelves t
3.THE AND RISK OF LOSS SELLER shall rtteiv the Ulm Egh,d4,it iomtm m M piohrs m th pso, 's this AgeErmL PURCHASER SrW prat and i^d�CY SELLER its nldm F mL M orri a
emml probed by applkaNe law,rod ding a�MiV'amrm m the ProAms,tool the furl twrnt's abaNaia mtl rah of Weo rapctivc oBeuaa dirtnaa evylwar sort agmm,Gam sod epoC W
bcE pdm ShcER lbe gviog sod pagofdMarmandlL trade plvrdm priEM cle®s,d®sods and ca,»"of ctim ffipby e%mty brbc ctlmtof PURCHASER'S rmgligoaawrpfW
elm SrW rd canmiem Lhe emmtdapay�tmampmrSELLERsidassiosmz¢mslm ssevdidm1sjE,mpay&mmNor6 14,DEhFaAtUkLTa.®stirm wiWWa Agemmt
TERMINATION Its the acme that PURCHASER bcmm immlvem,m®ts m sot of
vase amePmrassc pSdio furl.Riskofkm SuD PaamPURCNASERmWcdWvvy paint bmkupory ade(mlmm We pafaomrc of sry�«®ditim afW¢AgemisoL We SELLEftn mLLERapelimof
4.PAYMENI'TERA6.SELLER rvamthe EgMmSrip the PraWcp and be pnid taachmaporm bans, tle pmche&psi«ShslL wiWrn votimahmssd hmsocimmdY elm and peyebk. im aptibq
asilY,"L Hprymcnb acnotmtic bYWesst PURCHASE"
UR HASE emsWe to pion perm WSIreomW,«Im1maR wiWanootim«hmmQ shdlhc�hdmaefL sM frlsecmdforseasmablckp fora plus mtoLpockof
dWsi,iOs apply fiomrd"'Lodamf pvymmtPURCHA,"ISELLER'S pay SELLER'S lepf«s and Wmhe espeom-Its,Product,
atlermypl&e whose We PrdIkr col XWadmmke®mcdiam possesionaf
expEcesartspcelofonficivgar eaemdogmEf«m aoY OCSELLER'S EghmrtlmtBmabrerWLWrtamrcd and rmmse the Prodmm wiW Lwhhod kp paws;mlN«rraivWlsaYmeols mile acmtpmmtim frrthe
5.Nemhd'We prymmtcormsfy PURCHASER me of We Pmi,00r mill«rams so Ps iiiie widmm Slice«dmsod,f«andm bdelfof We PURCHASER
orrikr looiradER,or aped.0ypovWet in SELLERS Rootoid Li so tl;PURCHASER @tll pry soRm Es of Weret ,ossss anmch sale(sity W pmtm Pfiroorost the ak psimof apedor,isofaWselervd Wl
SELL R tosr, SELLER w addition m do VE,f«W sales,use and uWv toots exdaa ad c FOO,which H.,ro of retakingL d f.s repairs rccessry b pal der Products io stlende covdilio o stag:ch W SEtaxis,
SELLERmry pry«Itere9arb SErymmy gOvemnLASER,NyaWLIE Po iomme:tiw wsdthe pmhmtion, pars,cdlmaon sod 4prar mctdldM nymasm mnaetion Werewith)mde isp WE elm i,SELLER
sale,trmspommon,mE/«meby SELLER«PURCHASERofmyof CHProWrasorsavires hurtwildty soI fortle Pmducp andbTarim Goon the PURCHASER the depcicmy beMmv arch m2 preaMfi of mk mid ash
(wheals tle.cove nut'he regarded a or,ch a our so�s,,rosro).PURCHASER ages b pry W poPmY rod blmcc.PURCHASER hacby wsivm W trespm,d®age and dorm on tos g Ram soy net sotry,tcpommoq
arts tam Shirty maybe kvi 1,esxsxd«chmgd ageivst L rpm nrY of tic ProWc6 w L ots tle h2 of re ift,rr is,o r stair, ora SE and Wc.The rmdks pmviticd iv fNs pmegaph ere w tldipm m and oil
actua CELCNftorstrlALW or ARi Coog f«PURCHASER5 accoum 1®iudmsarany TIO .PURCHASER
S MECHANICAL WARRANTY. Sddy f« We FfIRC of PURCHASER SELLER watsEi Ws new IS CANCELWTIONv PURCHASER may tamrme Wk Age®m Rot ca o rs,s tyro®sing SELLER
eyrris-end pap msonfimmdbyi[mdprovihdm pURCHASER(mpsIsO(1,"Rohsframs 11 befi&lion thirty O0l dais pia xnvE tam of act far and peldn6 SELLER(«WEsp aid esyevar(WCIWmg
hf«mmmareitl and w«lmmsbip The wormy period Sup urlwdse(12)vmWs Ram Corny of tle ovedaM)immrN b'LLmpRammg ion xvk lepmd3 amlbcs®edusereasooade pofv derrm All sate
We Cacti rngwtrr ,SELLER(shall r y replete R acchsg b PIIRCHAS HE X WOMS SSEEI R 5 a�eoas steal he Irdd m SELLER wiWv to(10)days of We mmiomoo oL tle Ag«mat,m h
FAaORRS«dMlocaoo Wm SEI.I.F.R I&RE mr IES, vslacpslsoil ltyM&s,11URC iSOf mwd muuvt dcrosandrymsa owed.
Rai i tons,my PraAet L prom Wemf rmLJR m SELLER w6ict pt REMEDIES The rights and rumeWes of We PURCHASER w s ors,n wiW We gwd5 W sources
WmmtYmunation Shell show b hone furW tmhr vomral ti avd servkO opcmtor a PErroof Is, awoou We psovided M SELLER FR M1eseSdc m emkave sod IaiW m We sigh&sort teossdics rNrmlY Spend in Ibis
SELLEK SELLER
LE povded Wm if it waWd to imprmEiiS fon de Protect L pony Wrmf If be temroW b 17.ENSenr.
50.L6R SELLER SELLER a rtpemorave m PUR to io,,sw o mpl=tI,,p Ron Product lihiot SELWM SELLS PECTION.PURCHASER k Etitkd m make tEsmnbk ivspcWm of Prodmm m SELLERS,Ro,,
efler ivsp tivo Wm SELLER Isost, adLWisossig tYmrepav«W SELWeP tandem Waeof,SFLIER SELLER rcmes Weright bdetemice tberusSVdEea o[the aquestmdmal«tmepproptieteeme fa such
shop fca tle treoyortoEon map of(e)rmmtrrry We ProWra m SELLER kr insp tiro or sa4vg its imIIENA i Allwsofi,RodEwamtcgaesHimtdrrlmmLLmi�pvt of tlr gmtW pn«of We Prodmts
tepesenmtivebNejob ak act@)rtvvdpg Om rcpised aaepled ProdaabPURCHASER haveva,KiFis in rksAgrmmsh 01 paid by SELLER
to ER
detaminod ado Wy[ntim tM SELLER ismtliffile Sda Wit wsormry,PURCHASER stW pay/tax sap.For IS WAIVA.R Am�fs'Ime by SEf.1.F.Rmmt PURCFGSER's shier pd'ammr of my proviam of this
t1risw mhc svirosrhospgbEEawmnmty,PURCHASEREmoulx ipc�m5EL1ERwi,sst,a Or Agc®mt wrtl mtcmemmm awarvedip Egmmmrbugompy Eficarch pondon Lmy dhapaviSm of
Wit wmrmv k writing m kkr Wso thkry(30)dryz aM We done PURCHASER dismvas the has kr u Wre Agmcem.
wursoty clvm sdmmevevt Sort tlm Whlyf30)drys abn We cryiradm ofWeWmavty Period to aaWtionm 19,cumllANCE WRH LAWS If yplimbk law;adivmtt,rtgWmims L wmtlitios,rtquvo mvWmg
soot dM limiptieu«ftrsE a Stet rteper m Wis wanmty,SEWER Sall have m liability w reRea ma% riBeml Rom,L Or rtictitiE to,Wm add for by Ibis Agamm,SELLER will.sursfy nsW rerlammmm
(skis Rd rrslt(i)fWme Of We Prodmu,or dsmgs m Wav,he to PURCHASERS nc0,,mcc«wi11fW PURCHASERS Scam rtqum aoctayEce.
miaonWs;abr&«improper ssooW,ivedlmaq yylicmim ormmtmmm(a&ailkdm sissy-1 L M FORCE MANURE BSELI.ER is rendtsW tmale,wholly«w.9 part'by—a Fecc Majvacm
ocisiskwElm soy or ws,Ibm SELLER SELLER'S Ottiess Mo s roc PURCHASER);(u)sty ProWrcp Wm taut hem tlmrd w curry m cry of ur ahligatiom Imaamtiv,tbsv on SELLER'S to4ce k wntivg m PURLTiASER withal e
urPmd U;(rymyyP =m amag iwwnvmsdhariatioq(w)Themam ofdidCCDMP and rdvC ors remmebkrae oWC«mmEm,W ofGd,Imsismcha64geEmsrkE,,t �mdnl.••Fact Maorom
dmegcd while in vnmil LrWcrxise si`li i s of(v)dccompoari000CPr hers shall Wrlude,bn sot he tamd o, sop of God,laws and rupatimo,Burka,civic SER or PLTR«sorest,
byatc&icdmtiuh Sam W emmion«wErbsime sic«ducmmodioomofmmpnmve,rso, s tmddin; Iighmiors fim,tors Flosahw muLslLm,catso root pun Gihv wins,pots scoots,
PURCHASER aPURCHASEmy
or t,Wams O O,lick m prom tllo are met Iicro and Rios rcplxW dmio6 maimermw suet&ME mbc,.ts,Ixeekagc n emidcm ei OFEplmon Ll d6o SE,wets,police&toms ovoESm mMBoa and my
meliq filmy dramg MAW mil the like,excryt whore axh psis n M Perforator,o�o m SELLER'S emimam ts dbe n W osstlm ue aomeemnnfly within the coned afWo SELLER.LfiR Iftlie hlny isosi to OL PURCHASER'
mrvW o SELLERS
E R m which cox,SELLER sbep tidy oo liabk o o We po ton son of reek tRoo,aflhxe pros action a inaction,the in emitim b so actjnmsen[k tone,SELLER Wall be&titled m rdntlnosrmot or toss
faced on SELLER'S rtimam of wtm We remddog mica tk of dwEi pals Smuts tsve i rt.psovihd,Wm 21,INDEPENDENT
E DENT mhedWe.
fartmeoIs potsd"o"is, team mry of thevmmrs tact ELLS (i)Wps,SOLEWSIWdh regmd m EI.INDEPENDEM soitspooisk, uss t, lyrWvCood Wm SELLER isEmoor,or lcotmactL,sort
It petty dyer.ibs, go arl Of sin«mt&menm yr d SEI.LER's daBq SELLER'S IialEtry SsW be dE as, ,SELLER vL ur psimipwk,pumas,PSEm.ashsidisiE,to so, s,mployar,a aubmmectrns me
OEEBE mkly tI We�gmktl ESS ORNe LEER, watmtiea THE PAR'FHS AGREE THAT ALL mv�.syaes,pmvv;joimwrmvss«eslq—OfPURCH bo W wrywhmmcvc.
OTHER W"I RAMTRS,EXPAND$OR D11PLH?D,D1CT.II. WARA VA OF FITNESS FORA 32 SEVER thtsr'th gtIR mry protons of Wa A000sss he held m he invalid«Esofacmbk ostler
PARTTCUWR PURPOSE AND A�RCIWNTABp.r1Y, WBQ'IHER WRITTEN, ORAL OR grliEblc Isw Wm the vdidity of roc r®sidvg putiw tlmmf Bull mr ur aEecmi M art ivvtliWw«
STA'1"1I1'ONY.ARE B.YCLUDED TO ME P[IIL6T ER'IENr PFR/ASSBLE BY LAW.AD wmrmties rmmfaaagtiryad Sall rtmem iv fuR 6ce sd�2EmMme,sry®valid«1mG�tlepwitim hap be
sodubr!Ibot hoorst tosoll soma,aPURCHASER btsbpSE ion SELLER'S
WU Agemm mWfinE assoso hm lie®f"mad'qyh-stele law.®v��m®paamble nWe psva'mt�es
imltddg Wt not harts m my fy"lurt m pry my Burgs Ae m SELLER SELLER'S 9oomd dyer Gr the VI IMOIven
ProC NFI ENrpmr NFOMA O& wwanmry obfgaoo sort isor forms,,to ,mpria. 23.CT1010E0 I11010E OF VF ra'Th¢Agemmt steal be gaemW and cowmadw,iO ssoc
]. CONFIDENTIAL INf'fIRMATION. AlAll mopuNic inf afro sod dons famslN m PURCHASER wiW pe laws of We SYm of Umh,wiWm rtgmd m in&b Iegmdvg mo0icb a etoe'e N Lew.The paves
hneuxtrr,including bon yr limimctbpnce,am,Type and dmron ofthe PaoWvp is tle sdc propmy ofSELLER ZL WelasdictiEmdvmmoftle5mx mporticaummcetd WStl[Lake Cut its,M
evd&botihdr PURCHASERS owocovfidout SELSOklywoo tssriu wph this Ageemeet aodk mtmbe Ofthr SLLEIL NT PURCHASER shallvr aagnLtfaMfa Ibis Agramwt wiWm WepiLLERECE,mot
ma delamwomeveilabkmmry thidl W poordWom SELLER'S wins SELURmeot oLWe SELLERAq atmmp mmakemch so assist®ent«trmomsits lbe tall mdvois, SELLER steal hone
o.PAIuits. The Ptoduem WWlba pu., ormi,W,swill
SELLERS martlmdpre tice,mdtfiss , tho"10ph«opoo aaggordhmvia to PLCK,Lm Egbm add obligWommcwrcctim wiW this Agmoen4 ivwhok
rams Such tt mdOf&oval;sprd EE1..Pump.eon..Sip h pmmW w aLsdemO with mmufarnres' in pert rpm ION ON mEm&PURCHASER
9.1) praoom,NDTE herwix rgeedwwdmg T5.LIMITATLON ER I.IABD,TIY TO THE RY'f'ENI'PEAMISS G R NI LAW,SELLER SHALL
EOt— N'GSAND TECLIHCALDIX'tIistrod ATION WhE if Woo SERrcqurSmappoml ofduwing HAVE NOFUNTECTOYG LLI'1'YINC'ONNR IIONWRHTNCS AGREE DEFE E,INESSOFTHE
bef rmocvr�m s, m)fires e.Ssifa®t mN be dda)'M if b&o fir dmwiogs me sot sLLER m COST OFUE OF T HNG ANY DEFECTS,HEREUNDER.RE THE ABSENCE OF ANY DEFECT,IN BXCFSR OF
SFI r FR*St fostrssriiI (14)drys of Iatipt M PURCHASER of such Aewmgs for eppovW SELLER Sfp THE VALUE OF ITI PRODUCES SOLD SELLER
B NOTWCTI LEE SI ALI ANY EsrE F BE
form$EN gmasl srm4mr«,gavel ably,and if rtgme{womg diegam,versos dmvag, OR RESPONSIBILITIES ASSUMED By SEI.IRR IiBREUND8IL SELLER von 59A11 a'NO EVEN'C BE
suppllooE and apti lase Wmnsoaos, it RoSr,,o,, r4r4mmt(m FnpJiA lmenaeel SELLER Sip FIBRE S®LETOPUR,,LjGR OR ANY IHHID PARTY.WHE[HERARLSHIGU RO FOB, LL
supply err(d)mmplee son of hawing and oPV Wu%inOarlife AddOmtl ors wpl W dirt f«M TORT (AFED RO M LOSS W SI81Cf IJABDITY, OR QOWN, �, FOR LOSS OF
PflRladASER EIav®cfiks,Hlcgor�lWk 1Y dprwW brpovided kpd(JP%anlGammady ACREAtSTHI PENSE , LOSS BY REASON E PFERR SHIONS. NONOPEBATION OR
Ip.SET'OFF.This Agcmmt Sap he a�lisly Wctrpmdm[of tll aura amtr&m hnvem We tmrEE sod W IIiC11FAS®ERP@Ig OF OPFRAID)N.SFAV,,HsTFRRUPIWN$COST OF HIRCL OR SOR
,,
LwYmem&rem SELLER Los SELL $ill a pad Stew Oe and W In«he oroHacii.orapron any money O`FHER fINIAR POWER,COST L,MONEY,1.055 OF USE OF CAPITAL OR REVENUE OR ANY
elm«cla®edb orl--s SELLERS))—W—t6oPaLutmrofmy aura trEurtm adorn LOSS INDIRECT,pV®FFHER ARISING
FROM
DEVE,EXEMPLARY,OR CONSEQUENTIAL
which it 0 arddvd a seemly pmp.�:b)nr b o¢We pogm m any co,,E oEarts asoo tie compury wiW LOSS OR UCTSOE WHETHER ARISmC FROM DEFECTS,DELAY,OR FROM ANY OTHER
which it l apphel:and c)b limit&cats b the pagan m Mm s,o emplgar who fi naossary m prat GUSE WHATSOEVER.
autltmisfu&ofWeprogmm.PURCNA$ERagrceemexmve and be bound bytle etmsofaty mpwaee license REV6fONDATE-AGL4CN5, 2IXI9
PROPOSAL
Ovivo USA,U-C
4255 Lake Park Blvd.n Suite 100 w Salt lake Gty,Utah 84120-8201 USA
Tel:(801)931-3000 m Fax:(801)931-3080
www.ovivowater.com
19
ov ivo Proposal No.January
29, —CL
TERMS& Proposal Date:January 29 2013
CONDITIONS Page 9 of 9
Bringing water to life
NORTH AMERICAN
FIELD SERVICE RATE SHEET
Effective January 2013
Standard (Travel) Daily Rate(8 hour day) $ 1,200.00
Hourly Rate (4 hour minimum) $ 150.00
Standard (Labor) Daily Rate (8 hour day) $ 1,200.00
Hourly Rate (4 hour minimum) $ 150.00
Saturday Daily Rate(8 hour day) $ 1,800.00
Hourly Rate (4 hour minimum) $ 225.00
Sundays/Holidays * Daily Rate(8 hour day) $2,400.00
Hourly Rate (4 hour minimum) $300.00
Overtime ** Hourly Rate-Standard Day $225.00
Hourly Rate-Weekends & Holidays $300.00
* Except Christmas Day and New Years Day
** For all hours worked over eight(8) hours per day
UNLESS OTHERWISE ARRANGED;EXPENSES ARE CHARGED AT ACTUAL COST PLUS 10%
Please Note:
• All of the rates provided are portal to portal. In addition,travel and living expenses will be invoiced at
actual cost PLUS 10%and documentation will be provided for these expenses. If a fixed Per Diem rate
is required, it will be charged at$250.00 per day(lodging and meals) with the exception of the East
Coast where the price will be$300.00). Travel on Saturday, Sunday or Holidays, and after 8 hours per
day will be billed at the overtime rate.
• Use of Ovivo Fleet vehicles for travel will be charged at the rate of$0.565 per mile.
PROPOSAL
Ovivo USA,LLC
4255 Lake Park Blvd.•Suite 100•Salt Lake City,Utah 84120-9201 USA
Tel:(801)931-3000•Fax:(801)931-3080
www.oviwwaterxom
20
ID ask Name Duration Start Finish 27 1 Feb3 1_,Fe: t0 �Feh 17,'1 Feb_24 'i Mara 13 Mar 10 1 Mer 17 _i Mar 24 1 Mar 31,_1J Apr7,'13_IApr14 1,Apr21,'i Apr28
—' .___ __ ___.j_TFSS TFSS� r TFSSJ T]_TFSS �TFS� T] TFSS] TJ_TFSS�TI TF$S�„T TFSSLT_TFSS;T, TFS5 T TFSS'', T: TFSS T'
2
Consauctlon Window-Trickling Filters 87 days?. Mon B/3/13 Mon 9(3q/1S
3
i
4
Staff report preparation 17 days? Tue 4/2/13 Tue 4/18/13j -
i
8- - Q City Council Approval t day Wed 4/17/13 Wed 4/17/13i w
7 Q Notice To Proceed-preparation and issuance 3 days Thu 4/18/13 Mon 4/22/13 m .
8 Q Contract completion 21 days? Tue 4/23113
9 eQ Material consbuctlon 51 days? Wed 5122113 Tue 7/30/13I
TO Construction or ME-D5 5days? Wed 7/31//3 Tue 8/e/13
11Eg Regeneration time for ME-05 20 days? Wed Bl7/7S Tue 9/3/13
12 Construction of ME-06 5days? Wetl 9/4/73 Tue 9/10A3
13 Regeneration time for ME-OB 25 days? Wed9/11/13 Tue1D/15/131
Task ( / Milestone ♦ External Tasks -
Project:Trickling Biter-longest duraUo Date:Wed 2/8/13 Split Summary Ills.........V Exlemal Milestone
Progress Project Summary `J :: Deadline fs
!V Page 1
_May$,'1 Mey 12 ' M_eyy,1B,,, Mey 26on
9,'iJ Jun i8rl Ju_n 23Y Jun 3021_Jul 7,'13,.�Jul_14 1 Jul21,y,. Ju128'1 A�,4,'1 Aup it,'„Aup_18, Aup 25, Sep 1�1„,9epe 1 Sep 15 Sep 22,'.;.Sep 29,' .Oct 6,'13.Oct 1
FS�T�TFSS T TFSS TI.TFSS TI TFSSSf T�_TFSS Ti TFBS� T� TFS_5� TI TFSSJ TI TF$$�_TrTFTI TFSS Ti TFSS TTFSS T�.i_F58 �TFSS� iJ_ FSS,T�TFSS.TI TFSSI 71 7F55 T TFS§'. T TFSS T TFSS T
Task ® Milestone ♦ External Tasks -'—
Project:Trickling filter-longest durella S
Date:Wed 2/6113 plit Summary �1 External Milestone
Progress Project Summary — Deadline b
IV Page 2
N