HomeMy WebLinkAbout10/1/2014 - STAFF REPORTS - 2.Q. aOIc9ALM SAR iy c+ V N • c �fIORAilR 'a C'41IFORN�P• City Council Staff Report Date: October 1, 2014 CONSENT CALENDAR Subject: APPROVAL OF PLANS, SPECIFICATIONS AND ESTIMATE (PS&E) AND AUTHORIZATION TO BID FOR THE SUNRISE WAY/BOYS AND GIRLS CLUB/RALPHS SHOPPING CENTER DRIVEWAY TRAFFIC SIGNAL, CITY PROJECT NO. 13-25 From: David H. Ready, City Manager Initiated by: Public Works and Engineering Department SUMMARY The 2014/2015 budget includes Measure A funds for a traffic signal at the intersection of Sunrise Way/Boys and Girls Club/Ralphs Shopping Center Driveways. The construction documents (Plans, Specifications and Estimate) are completed and, in accordance with Section 7.03.040 of the Procurement and Contracting Code the City Council is required to approve and adopt plans, specifications and working details, and authorize the bid request for all public projects in excess of $100,000. Approval of this project will allow staff to proceed with this public project, with an estimated construction cost of approximately $203,000. RECOMMENDATION: 1. Approve the Plans, Specifications, and working details for the Sunrise Way/Boys and Girls Club/Ralphs Shopping Center Driveway Traffic Signal, City Project 13- 25, and authorize staff to advertise and solicit bids. STAFF ANALYSIS: City Council authorized staff to investigate the warrants for a traffic signal at the intersection of Sunrise Way with the driveways at the Boys and Girls Club and Ralphs Shopping Center. The study was funded by Measure J and was performed in 2013 in conjunction with the 2013 Citywide Speed Study. The study showed a traffic signal is warranted. On November 20, 2013 a Purchase Order was issued to Albert Grover & Associates (AGA) for preparation of plans and specifications for the traffic signal. The plans, specifications and estimate were completed and submitted to the City on May 5, 2014. ITEM NO. City Council Staff Report October 1, 2014 - Page 2 Sunrise Way/Boys and Girls Club/Ralphs Shopping Center Driveway Traffic Signal (CP 13-25) Authorization to Bid On May 21, 2014 the plans and specifications were submitted to Council requesting approval. At that time Council questioned the signal timing proposed with respect to the adjacent signal at Ramon Road and Sunrise Way as well as traffic queue lengths on the shopping center site to be sure the on-site intersection of the drive aisles is not blocked due to signal operation. The design consultant prepared and demonstrated a traffic simulation to Council on September 17. The simulation used real time signal cycle lengths and peak hour traffic volumes to create a visual demonstration using mathematical modeling through the application of computer software. After the presentation Council directed staff to bring the request for approval of Plans and Specifications and authorization to advertise for construction bids back to Council. The plans and specifications have been prepared by AGA, are ready for Council approval and the subsequent advertisement for construction bids. Section 7.03.040 of the Procurement and Contracting Code requires that for public projects in excess of $100,000 Council approve and adopt the plans, specifications and working details, and authorize staff to advertise for construction bids. The Engineer's Estimate for this project is $203,000. Approval of the recommended action will allow staff to proceed with bidding of this project. The plans, specifications, and estimates are available for viewing in Public Works and Engineering Department. FISCAL IMPACT: Funding for this project is available through local Measure A funds in account 134-4498- 59416. SUBMITTED: Prepared by: Approved by: David J. Barakian David H. Ready Director of Public Works/City Engineer City Manager 02