HomeMy WebLinkAbout12/3/2014 - STAFF REPORTS - 2.O. AOQ V P L M S,.
iy
c
U N
a
c4<fFORN�P City Council Staff Report
Date: December 3, 2014 CONSENT CALENDAR
Subject: AWARD OF CONSTRUCTION CONTRACT FOR SUNRISE WAY AT
BOYS & GIRLS CLUB/RALPH'S DRIVEWAYS TRAFFIC SIGNAL
INSTALLATION, CITY PROJECT 13-25
From: David H. Ready, City Manager
Initiated by: Public Works and Engineering Department
SUMMARY
Approval of this item will award the construction contract for the Traffic Signal
Installation at the Boys & Girls Club/Ralph's Driveways.
RECOMMENDATION:
1. Approve Agreement No. in the amount of $209,687, subject to the
protest provisions of Palm Springs Municipal Code Section 7.08.030, for the
Sunrise Way at Boys & Girls Club/Ralph's Driveways Traffic Signal Installation
with DBX, Inc., City Project No. 13-25; and
2. Authorize the City Manager to execute all necessary documents.
STAFF ANALYSIS:
City Council authorized staff to investigate the warrants for a traffic signal at the
intersection of Sunrise Way with the driveways at the Boys and Girls Club and Ralphs
Shopping Center. The study was funded by Measure J and was performed in 2013 in
conjunction with the 2013 Citywide Speed Study. The study showed a traffic signal is
warranted. On November 20, 2013 a Purchase Order was issued to Albert Grover &
Associates (AGA) for preparation of plans and specifications for the traffic signal. The
plans, specifications and estimate were completed and submitted to the City Council on
May 21, 2014. At the meeting, the City Council wanted further analysis.
A traffic simulation was presented on September 17, 2014 when City Council approved
the Plans Specifications and Estimates and authorized staff to proceed with bidding.
On October 25th, and November 1 st, 2014, the project was advertised for bids, and at
4:00 p.m. on November 25, 2014, the Procurement and Contracting Division received
construction bids from the following contractors:
ITEM NO.�_
City Council Staff Report
December 3, 2014 - Page 2
Sunrise Way at Boys & Girls Club/Ralph's Driveways Traffic Signal Installation (City Project No. 13-25)
1. DBX, Inc.; Temecula, CA $209,687
2. PTM General Engineering Services, Inc.; Riverside, CA $216,166
3. Steiny and Company, Inc.; Baldwin Park, CA $250,258
The engineer's estimate was $208,000.
The lowest responsive, responsible bidder is DBX, Inc., a corporation, and its officers
are: Jim Perry, President and Secretary.
FISCAL IMPACT:
Sufficient funding for this project is available in local Measure A funds in account
number 134-4498-59416.
SUBMITTED:
Prepared by: Recommended b4an
Savat Khamph u �� David J. Bara
Assistant Director of Public Works Director of Public Works/City Engineer
Approved by:
David H. Ready
City Manager
Attachment:
1. Agreement
02
AGREEMENT
THIS AGREEMENT made this _ day of 2014, by and between
the City of Palm Springs, a charter city, organized and existing in the County of Riverside,
under and by virtue of the laws of the State of California, hereinafter designated as the
City, and
hereinafter designated as the Contractor.
The City and the Contractor, in consideration of the mutual covenants hereinafter set
forth, agree as follows:
ARTICLE 1 -- THE WORK
The Contractor shall complete the Work as specified or indicated under the Bid
Schedule(s) of the City's Contract Documents entitled:
SUNRISE WAY AT BOYS & GIRLS CLUB/RALPH'S DRIVEWAY
TRAFFIC SIGNAL INSTALLATION, CITY PROJECT NO. 13-25
The Work comprises the installation of a new traffic signal and electrical system
complete, with associated improvements at the intersection of Sunrise Way at Boys and
Girls Club/Ralph's Driveway; traffic striping and signage; removal and replacement, and
construction of various concrete improvements; and all appurtenant work.
ARTICLE 2 -- COMMENCEMENT AND COMPLETION
The Work to be performed under this Contract shall commence on the date specified in
the Notice to Proceed by the City, and the Work shall be fully completed within the time
specified in the Notice to Proceed.
The City and the Contractor recognize that time is of the essence of this Agreement, and
that the City will suffer financial loss if the Work is not completed within the time specified
in Article 2, herein, plus any extensions thereof allowed in accordance with applicable
provisions of the Standard Specifications, as modified herein. They also recognize the
delays, expense, and difficulties involved in proving in a legal proceeding the actual loss
suffered by the City if the Work is not completed on time. Accordingly, instead of
requiring any such proof, the City and the Contractor agree that as liquidated damages or
delay (but not as a penalty), the Contractor shall pay the City the sum of $750 for each
calendar day that expires after the time specified in Article 2, herein. In executing the
Agreement, the Contractor acknowledges it has reviewed the provisions of the Standard
Specifications, as modified herein, related to liquidated damages, and has made itself
aware of the actual loss incurred by the City due to the inability to complete the Work
within the time specified in the Notice to Proceed.
03
SUNRISE WAY AT BOYS&GIRLS CLUB/RALPH'S DWY TRAFFIC SIGNAL AGREEMENT FORM
CITY PROJECT NO. 13-25 AGREEMENT AND BONDS-PAGE 1 '
OCTOBER 2014
ARTICLE 3 -- CONTRACT PRICE
The City shall pay the Contractor for the completion of the Work, in accordance with the
Contract Documents, in current funds the Contract Price(s) named in the Contractor's Bid
and Bid Schedule(s).
ARTICLE 4 — THE CONTRACT DOCUMENTS
The Contract Documents consist of the Notice Inviting Bids, Instructions to Bidders, the
prevailing rate of per diem wages as determined by the Director of the California
Department of Industrial Relations, the accepted Bid and Bid Schedule(s), List of
Subcontractors, Non-collusion Affidavit, Bid Security or Bid Bond, Bidder's General
Information, Public Contract Code Section 10285.1 Statement, Public Contract Code
Section 10162 Questionnaire, Public Contract Code Section 10232 Statement, this
Agreement, Worker's Compensation Certificate, Performance Bond, Payment Bond,
Standard Specifications, Special Provisions, the Drawings, Addenda numbers
to , inclusive, and all Change Orders and Work Change Directives which may
be delivered or issued after the Effective Date of the Agreement and are not attached
hereto.
ARTICLE 5 -- PAYMENT PROCEDURES
The Contractor shall submit Applications for Payment in accordance with the Standard
Specifications as amended by the Special Provisions. Applications for Payment will be
processed by the Engineer or the City as provided in the Contract Documents.
ARTICLE 6 -- NOTICES
Whenever any provision of the Contract Documents requires the giving of a written
Notice, it shall be deemed to have been validly given if delivered in person to the
individual or to a member of the firm or to an officer of the corporation for whom it is
intended, or if delivered at or sent by registered or certified mail, postage prepaid, to the
last business address known to the giver of the Notice.
ARTICLE 7 -- MISCELLANEOUS
Terms used in this Agreement which are defined in the Standard Specifications and the
Special Provisions will have the meanings indicated in said Standard Specifications and
the Special Provisions. No assignment by a party hereto of any rights under or interests
in the Contract Documents will be binding on another party hereto without the written
consent of the party sought to be bound; and specifically, but without limitation, monies
that may become due and monies that are due may not be assigned without such
consent (except to the extent that the effect of this restriction may be limited by law), and
unless specifically stated to the contrary in any written consent to an assignment, no
assignment will release or discharge the assignor from any duty or responsibility under
the Contract Documents.
The City and the Contractor each binds itself, its partners, successors, assigns, and legal
representatives, to the other party hereto, its partners, successors, assigns, and legal
SUNRISE WAY AT BOYS&GIRLS CLUB/ LP 'S DWY TRAFFIC SIGNAL AGREEMENT FORM 04
CITY PROJECT NO. 13-25 OCTOBER 2014 AGREEMENT AND BONDS-PAGE 2
representatives, in respect of all covenants, agreements, and obligations contained in the
Contract Documents.
IN WITNESS WHEREOF, the City and the Contractor have caused this Agreement to be
executed the day and year first above written.
ATTEST:
CITY OF PALM SPRINGS,
CALIFORNIA
By APPROVED BY THE CITY COUNCIL:
City Clerk
APPROVED AS TO FORM: Date
By
City Attorney Agreement No.
Date
CONTENTS APPROVED:
By
City Engineer
Date
By
City Manager
Date
05
SUNRISE WAY AT BOYS&GIRLS CLUB/RALPH'S DWY TRAFFIC SIGNAL AGREEMENT FORM
CITY PROJECT NO. 13-25 AGREEMENT AND BONDS-PAGE 3
OCTOBER 2014
Corporations require two notarized signatures: One signature must be from Chairman of Board, President, or any
Vice President. The second signature must be from the Secretary, Assistant Secretary, Treasurer, Assistant
Treasurer,or Chief Financial Officer.
CONTRACTOR: Name: Check one:_Individual_Partnership_Corporation
Address:
By: By:
Signature(notarized) Signature(notarized)
Name: Name:
Title: Title:
(This Agreement must be signed in the above This Agreement must be signed in the above
space by one of the following: Chairman of the space by one of the following: Secretary, Chief
Board, President or any Vice President) Financial Officer or any Assistant Treasurer)
State of C State of I
County of iss County of ss
On On
before me, before me,
personally appeared personally appeared
who proved to me on the basis of satisfactory who proved to me on the basis of satisfactory
evidence to be the person(s) whose name(s) evidence to be the person(s) whose name(s)
is/are subscribed to the within instrument and is/are subscribed to the within instrument and
acknowledged to me that he/she/they executed acknowledged to me that he/she/they executed
the same in his/her/their authorized capacity(ies), the same in his/her/their authorized capacity(ies),
and that by his/her/their signatures(s) on the and that by his/her/their signatures(s) on the
instrument the person(s), or the entity upon behalf instrument the person(s), or the entity upon behalf
of which the person(s) acted, executed the of which the person(s) acted, executed the
instrument. instrument.
I certify under PENALTY OF PERJURY under the I certify under PENALTY OF PERJURY under the
laws of the State of California that the foregoing laws of the State of California that the foregoing
paragraph is true and correct. paragraph is true and correct.
WITNESS my hand and official seal. WITNESS my hand and official seal.
Notary Signature: Notary Signature:
Notary Seal: Notary Seal:
SUNRISE WAY AT BOYS&GIRLS CLUB/RALPH'S DWY TRAFFIC SIGNAL
CITY PROJECT NO. 13-25 AGREEMENT FORM OCTOBER 2014 AGREEMENT AND BONDS-PAGE 4 06