Date: November 4, 2015 CONSENT CALENDAR
Subject: APPROVAL OF PROGRAM SUPPLEMENT AGREEMENT NO. N043,
WITH THE STATE OF CALIFORNIA FOR USE OF SURFACE
TRANSPORTATION PROGRAM (STP) FEDERAL-AID FUNDS FOR THE
RAMON ROAD PAVEMENT REHABILITATION, CITY PROJECT NO. 14-
02, FEDERAL AID PROJECT NO. STPLN-5282 (043)
From: David H. Ready, City Manager
Initiated by: Public Works and Engineering Department
SUMMARY
Approval of Program Supplement Agreement No. N043 will formally authorize the
reimbursement of up to $395,729 in federal-aid funds for the Ramon Road Pavement
Rehabilitation, City Project No. 14-02, Federal Aid Project No. STPLN-5282 (043).
RECOMMENDATION:
Adopt Resolution No. "A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF PALM SPRINGS, CALIFORNIA APPROVING PROGRAM SUPPLEMENT
AGREEMENT NO. N043 TO ADMINISTERING AGENCY-STATE AGREEMENT FOR
FEDERAL-AID PROJECTS NO. 08-5282R WITH THE STATE OF CALIFORNIA, IN
THE AMOUNT OF $395,729, FOR THE RAMON ROAD PAVEMENT
REHABILITATION, CITY PROJECT NO. 14-02, FEDERAL-AID PROJECT NO. STPLN-
5282 (043), AND AUTHORIZING THE CITY MANAGER TO EXECUTE THE
AGREEMENT ON BEHALF OF THE CITY OF PALM SPRINGS."
STAFF ANALYSIS:
In early 2013, the Riverside County Transportation Commission (RCTC) approved a
Call for Projects for RCTC and its member jurisdictions using RCTC's allocation of
Moving Ahead for Progress in the 215t Century (MAP-21) funds made available through
the current federal transportation bill, the Surface Transportation Program (STP).
On March 28, 2013, the Public Works and Engineering Department responded to
RCTC's Call or Projects for MAP-21 funding, requesting consideration of funding for
pavement rehabilitation and associated improvements on Ramon Road extending
ITEM NO. al
City Council Staff Report
November 4, 2015-Page 2
Program Supplement Agreement No. N043
generally from Sunrise Way to El Cielo Road. The purpose of the City's request is to
repair a severely weathered heavily traveled major arterial roadway. The proposed
improvements would grind and overlay the existing asphalt concrete pavement and
related improvements. The Public Works Department requested $395,729 in STP
federal funds for an estimated $500,000 project.
RCTC received a number of requests for MAP-21 funding from its member jurisdictions,
requesting a total of $52,000,000 in funding available in Fiscal Year's 2013/14 through
2015/16. The requests were evaluated by a Review Panel, and the City's request was
ranked in 13th place of the 23 requests that were approved. The RCTC Executive
Committee subsequently approved the list of projects to receive STP funding, and the
projects were later added to the Regional Transportation Improvement Plan.
The Ramon Road Pavement Rehabilitation, City Project No. 14-02, (the "Project"), will
cold mill the existing asphalt concrete pavement, prepare and repair existing cracks,
construct asphalt concrete overlay, install inductive loop vehicle detectors, and remove,
reconstruct, and upgrade curb ramps to conform to current ADA standards throughout
the Project limits. A location map is provided below. A vicinity map illustrating a 500-ft
radius from the roadway segment is included as Attachment 1.
me
saese�iD' V t V
CIE' lu
a
® ®
33f :°ti
nn ora rn nn A
P�y
r— -' :_ ► ♦! ::._ �n inn rin �n FV E
Location Map
The City operates under a "Master Agreement" with the state of California, identified as
the "Administering Agency — State Agreement No. 08-5282R" for use of federal-aid
funds on City projects. The Master Agreement is amended by each successive use of
federal funds on a project, and upon authorization or obligation of the use of federal
funds on a project, the City is provided with a "Program Supplement Agreement", or
amendment, to the Master Agreement.
In light of the City's authorization to proceed with the construction phase of the Project
using federal STP funds, Caltrans has submitted to the City for approval Program
Supplement Agreement No. N043 which will facilitate the City's use of federal funds for
the Project. A copy of Program Supplement Agreement No. N043 is included as
Attachment 2.
02
City Council Staff Report
November 4, 2015 - Page 3
Program Supplement Agreement No. N043
ENVIRONMENTAL IMPACT:
Section 21084 of the California Public Resources Code requires Guidelines for
Implementation of the California Environmental Quality Act ("CEQA"). The Guidelines
are required to include a list of classes of projects which have been determined not to
have a significant effect on the environment and which are exempt from the provisions
of CEQA. In response to that mandate, the Secretary for Resources identified classes
of projects that do not have a significant effect on the environment, and are declared to
be categorically exempt from the requirement for the preparation of environmental
documents. In accordance with Section 15301 "Existing Facilities," Class 1 projects
consist of the operation, repair, maintenance, permitting, leasing, licensing, or minor
alteration of existing highways and streets, sidewalks, gutters, bicycle and pedestrian
trails, and similar facilities; therefore, the Ramon Road Pavement Rehabilitation, City
Project No. 14-02, is considered categorically exempt from CEQA, and a Notice of
Exemption has been prepared and has been filed with the Riverside County Clerk. A
copy of the Notice of Exemption is included as Attachment 3.
This project is funded, in part, by federal funds, requiring local oversight by the State of
California, Department of Transportation ("Caltrans"). As a federally funded project, the
project is subject to environmental review pursuant to the National Environmental Policy
Act ("NEPA"). On December 11, 2014, Caltrans, acting as the lead agency pursuant to
NEPA, made an environmental determination that the project does not individually or
cumulatively have a significant impact on the environment as defined by NEPA and is
excluded from the requirements to prepare an Environmental Assessment ("EX) or
Environmental Impact Statement ("EIS'), and that it qualifies for a Categorical Exclusion
in accordance with 23 USC 327. Subsequently, on August 26, 2015, Caltrans
completed a NEPA re-validation confirming that the prior NEPA determination for the
Project remains valid and no further environmental documentation was required. A
copy of the NEPA environmental documents is included as Attachment 4.
FISCAL IMPACT:
Approval of Program Supplement Agreement No. N043 with Caltrans will formally
authorize the disbursement and use of up to $395,729 in federal-aid funds for the
Project. These funds will be allocated to the Capital Project Fund (Fund 261) in
Account No. 261-4491-50322. The City Council previously appropriated $51,000 from
the Local Measure A Fund (Fund 134) in the 2014-2015 Fiscal Year, and an additional
$100,000 in the 2015-2016 Fiscal Year for the Project.
03
City Council Staff Report
November 4, 2015- Page 4
Program Supplement Agreement No. N043
SUBMITTED:
Marcus L. Fuller, MPA, P.E., P.L.S. David H. Ready, Esq., P9b�
Assistant City Manager/City Engineer City Manager
Attachments:
1. Vicinity Map.
2. Program Supplement Agreement No. N043
3. CEQA: Notice of Exemption
4. NEPA: Categorical Exclusion and Revalidation
5. Resolution
04
ATTACHMENT 1
05
N
^OfyPLM SPq,i
Department of Public Works and Engineering W E
Vicinity Map
C4[Il OYP`P•
Lt1t 5
� J
a� ���[,Jt ANDREAS RDi��l �f�J U
N ETAHQUITZCANYONWAY 5
[:]D'
GALLS LILETA
a�
BARISTO RD
_Z �u
W
J 0^RAM_O_N�RD " p
rcum)
W,.,.,,...SUNSHINE OR N a
o
¢,� SCNSHINE WAY LL v. �p�Q�>�z 3 z
Z W W -- - -- - ' �kiix -j Z J r
z a w o W z 5 F
U z ` — Qoy��y� W U J W 2 U 7
.. C--m--m W rJ W O
SAN LUCAS RD N 0
MESQUITE AVE
S RIVERSIDE DR� _ "T� ,`lit
SAN LORENZO RD
ME AAF
¢ CIM CREST UR ,i
¢ ¢ o fn-ID-1 0 .:r
ALTA.LOYAOR
W N O V
0 gQ
W O �'� SONORA RD
Legend W Z LOMAVISTACIR
Site v� { SAN MARTIN CIR
500'Radius + AVERY DR �� � `Fj
CITY OF PALM SPRINGS
06
ATTACHMENT 2
n7
STATE OF CALIFORNIA-CALIFORNI4 STATE TRANSPORTATION AGENCY EDMUND G.BROWN Jr.,Governor
DEPARTMENT OF TRANSPORTATION
Division of Local Assistance
1120 N STREET 5Sri•
P.O.BOX 942874.MS# 1
Sacramento,CA 94274-0001
TtY 711
(916)654-3883
Fax(916)654-2408 File 08-RIV-0-PSP
STPLN-5282(043)
October 19, 2015 Ramon Road from approximately
650 feet west of Sunrise Way to
approximately 700 feel east of Coml
Mr. Savat Khamphou
Assistant City Engineer/Assistant Public Works Director
City of Palm Springs
3200 E. Tahquizt Canyon Way
Palm Springs, CA 92262
Dear Mr. Khamphou:
Enclosed are two originals of the Program Supplement Agreement No. D43-N to Administering Agency-State
Agreement No. 08-5282R and an approved Finance Letter for the subject project. Please retain the signed Finance
Letter for your records.
Please note that federal funding will be lost if you proceed with future phase(s) of the project prior to getting
the "Authorization to Proceed"with that phase.
Please review the covenants and sign both copies of this Agreement and return both to this office, Office of Project
Implementation - MS1 within 90 days from the receipt of this letter. If the signed Agreements are not received back in
this office within 90 days, funds will be disencumbered and/or deobligated. Alterations should not be made to the
agreement language or funding. ATTACH YOUR LOCAL AGENCY'S CERTIFIED AUTHORIZING RESOLUTION
THAT CLEARLY IDENTIFIES THE PROJECT AND THE OFFICIAL AUTHORIZED TO EXECUTE THE AGREEMENT.
A fully executed copy of the agreement will be returned to you upon ratification by Caltrans. No invoices for
reimbursement can be processed until the agreement is fully executed.
The State budget authority supporting the encumbered funds is only available for liquidation up to specific deadlines.
These deadlines are shown on the attached Finance letter as the "Reversion Date". Please ensure that your invoices
are submitted at least 60 days prior to the reversion date to avoid any lapse of funds. If your agency is unable to seek
reimbursement by this date you may request an extension through a Cooperative Work Agreement (CWA). A CWA is
subject to the final approval of the State Department of Finance. If approved, the CWA may extend the deadline for up
to two years.
Your prompt action is requested. If you have questions, please contact your District Local Assistance Engineer.
Sinct;rely,
n JOHN HOOLE, Chief
Office of Project Implementation-South
Division of Local Assistance
Enclosure
c: DLA AE Project Files
(08)DLAE-Sean Yeung
08
DEPARTMENT OF TRANSPORTATION FINANCE LETTER Date: 1 011 5/2 01 5
LOCAL
O GRAM ACCOUNTING
Agency: OB•RIV-Q PSP
LOCAL PROGRAM ACCOUNTING BRANCH Project No: STPLNSTPLN Od3]-
EA No:
Attention: City of Palm Springs
FNNINCEITEMs PRO RRTA OR TOTALCOSTOF—FEDERAL PART--FED.ROMB%-FEDERAL FUNDS LOCACFUNDS -OTIERFUNDS
LUMP SUM WORN COST
M23E
Contract Items
Construction Pm RNa .. S442000.00 1444000.00 88.53% 3"i Se3.m S'A.69700 SOm
Agency Construction ProRM4 S5.000.m 55.000.0) E852% fs.acm W4410 50.00
Engineering
Totals: SU7,00000_. S4a;0ii0:90 o.00% SMS,729A0 531,x71,110 fo.m
Fed.Partic: 100.00% This Finance Letter was created based on specific financial information provided by the responsible local agency.The following
encumbrance history is prepared
by Local Assistance Accounting Office and is provided hem for local agency's information and action.
Signature: �?n .. _ For questions regarding finance letter.contact,
Tab: HO Local Assistance Area Engineer Printed Name: Patrick Louie
Telephone No 916 653.7349
Remarks: Based on agency finance letter dated 06/18/15 for construction Reimbursement ratio-88 53%.
ACCOUNTING INFORMATION 9TPL14.5297I0137
Cooperative Work Agreement
APPROP ENCUMBRANCE APPROP EXPENONURE ENCUMBRANCE REVERSION APPROVED EXPIRATION
AM PROD A UNR STATE PROD. FEMTATE AMOUNT YEAR AMOUNT BALANCE DATE AMOUNT DATE
0674000719 15IMF 2MODIOM0 - F $39672900 1415 - SOm $395,72800 W&WO
a
ca
Page 1 of 1
PROGRAM SUPPLEMENT NO. N043 Adv Project ID Date: October 5,2015
to 0814000219 Location: 08-RIV-0-PSP
ADMINISTERING AGENCY-STATE AGREEMENT Project Number: STPLN-5282(043)
FOR FEDERAL-AID PROJECTS NO 08-5282R E.A. Number:
Locode: 5282
This Program Supplement hereby adopts and incorporates the Administering Agency-State Agreement for Federal Aid
which was entered into between the Administering Agency and the State on 02/07/07 and is subject to all the terms and
conditions thereof.This Program Supplement is executed in accordance with Article I of the aforementioned Master
Agreement under authority of Resolution No. approved by the Administering Agency on
(See copy attached).
The Administering Agency further stipulates that as a condition to the payment by the State of any funds derived from
sources noted below obligated to this PROJECT,the Administering Agency accepts and will comply with the special
covenants or remarks set forth on the following pages-
--------
PROJECT LOCATION:
Ramon Road from approximately 650 feet west of Sunrise Way to approximately 700 feet east of Compadre Road
TYPE OF WORK: Road rehabilitation LENGTH: 1.0(MILES)
Estimated Cost -- -
Federal Funds Matching Funds
M23E $395.729.00 LOCAL OTHER
$447,000,001 $51,271.0d
$0.00
CITY OF PALM SPRINGS STATE OF CALIFORNIA
Department of Transportation
By
Title — Chief, Office of Project Implementation
Division of Local Assistance
Date — ----
Attest _ Date ..___.___..__.-------____-._—.---
I hereby certify upon my personal knowledge that budgeted funds are available for this encumbrance:
Accounting Officer Date __./62r1 d7( $395.729.00
Chapter Statutes Item f Year Program BC i Category Fund Source A AMOUNT
Program Supplement 08-5282R-NO43-ISTEA Page 1 of 3 1
STATE OF CALIFORNIA.DEPARTMENT OF TRANSPORTATION R/W Utilities(4E1/4SBVE1)
PROGRAM SUPPLMENT AND CERTIFICATION FORM
PSCF(REV 0112010)
Page I of
TO STATE CONTROLLER'S DATE PREPARED PROJECT NUMBER
Claims Audits 1OR/2D15 0814000219
3301"C"Street,Rm 404 REQUISITION NUMBER/CONTRACT NUMBER
Sacramento,CA 96816 ROS 081600000190
FROM
Department of Transportation
UBJECT'
Encumbrance Document
VENDOR/ LOCAL AGENCY
CITY OF PALM SPRINGS
$ 395,729.00
PROCUREMENT TYPE
Local Assistance
CHAPTER STATUTES ITEM YEAR PECIPECT TASKISUBTASK AMOUNT
25 14 2660-102-890 14-15 2030010810 2620/0400 $ 395,729.00
ADA Nob For mmvldWis with Sensory disabilities,this dowrrlent is available in altemate formals.For information,call t915)654-6410 of TDD(916)-3880 or write
Records and Forms Management,1120 N Street,MS-89,Sarrdment0,CA 95814
l �
uu-niv-tirar STPLN-5282(043) 70/05/2015
SPECIAL COVENANTS OR REMARKS
�• A. The ADMINISTERING AGENCY will advertise, award and administer this project in
accordance with the current published Local Assistance Procedures Manual.
B. ADMINISTERING AGENCY agrees that it will only proceed with work authorized for
specific phase(s) with an "Authorization to Proceed" and will not proceed with future
phase(s) of this project prior to receiving an "Authorization to Proceed" from the STATE
for that phase(s) unless no further State or Federal funds are needed for those future
phase(s).
C. Award information shall be submitted by the ADMINISTERING AGENCY to the
District Local Assistance Engineer within 60 days of project contract award and prior to
the submittal of the ADMINISTERING AGENCY'S first invoice for the construction
contract.
Failure to do so will cause a delay in the State processing invoices for the construction
phase. Attention is directed to Section 15.7 "Award Package" of the Local Assistance
Procedures Manual,
D. ADMINISTERING AGENCY agrees, as a minimum, to submit invoices at least once
every six months commencing after the funds are encumbered for each phase by the
execution of this Project Program Supplement Agreement, or by STATE's approval of an
applicable Finance Letter. STATE reserves the right to suspend future
authorizations/obligations for Federal aid projects, or encumbrances for State funded
projects, as well as to suspend invoice payments for any on-going or future project by
ADMINISTERING AGENCY if PROJECT costs have not been invoiced by
ADMINISTERING AGENCY for a six-month period.
If no costs have been invoiced for a six-month period, ADMINISTERING AGENCY
agrees to submit for each phase a written explanation of the absence of PROJECT
activity along with target billing date and target billing amount.
ADMINISTERING AGENCY agrees to submit the final report documents that collectively
constitute a "Report of Expenditures" within one hundred eighty (180) days of PROJECT
completion. Failure of ADMINISTERING AGENCY to submit a "Final Report of
Expenditures" within 180 days of PROJECT completion will result in STATE imposing
sanctions upon ADMINISTERING AGENCY in accordance with the current Locat
Assistance Procedures Manual.
E. Administering Agency shall not discriminate on the basis of race, religion, age,
disability, color, national origin, or sex in the award and performance of any Federal-
assisted contract or in the administration of its DBE Program Implementation Agreement.
The Administering Agency shall take all necessary and reasonable steps under 49 CFR
Part 26 to ensure nondiscrimination in the award and administration of Federal-assisted
contracts. The Administering Agency's DBE Implementation Agreement is incorporated
by reference in this Agreement. Implementation of the DBE Implementation Agreement,
including but not limited to timely reporting of DBE commitments and utilization, is a legal
Program Supplement 08-5282R-N043-ISTEA L
Page 2 of 3
uo-rtv�r-rar 1 010 5/2 01 5
STPLN-5282(043)
SPECIAL COVENANTS OR REMARKS
obligation and failure to carry out its terms shall be treated as a violation of this
Agreement. Upon notification to the Administering Agency of its failure to carry out its
DBE Implementation Agreement, the State may impose sanctions as provided for under
49 CFR Part 26 and may, in appropriate cases, refer the matter for enforcement under 18
U.S.C. 1001 and/or the Program Fraud Civil Remedies Act of 1986 (31 U.S.C. 3801 et
seq.).
F. Any State and Federal funds that may have been encumbered for this project are
available for disbursement for limited periods of time. For each fund encumbrance the
limited period is from the start of the fiscal year that the specific fund was appropriated
within the State Budget Act to the applicable fund Reversion Date shown on the State
approved project finance letter. Per Government Code Section 16304, all project funds
not liquidated within these periods will revert unless an executed Cooperative Work
Agreement extending these dates is requested by the ADMINISTERING AGENCY and
approved by the California Department of Finance.
ADMINISTERING AGENCY should ensure that invoices are submitted to the District
Local Assistance Engineer at least 75 days prior to the applicable fund Reversion Date to
avoid the lapse of applicable funds. Pursuant to a directive from the State Controller's
Office and the Department of Finance; in order for payment to be made, the last date the
District Local Assistance Engineer can forward an invoice for payment to the
Department's Local Programs Accounting Office for reimbursable work for funds that are
going to revert at the end of a particular fiscal year is May 15th of the particular fiscal
year. Notwithstanding the unliquidated sums of project specific State and Federal funding
remaining and available to fund project work, any invoice for reimbursement involving
applicable funds that is not received by the Department's Local Programs Accounting
Office at least 45 days prior to the applicable fixed fund Reversion Date will not be paid.
These unexpended funds will be irrevocably reverted by the Department's Division of
Accounting on the applicable fund Reversion Date.
G. As a condition for receiving federal-aid highway funds for the PROJECT, the
Administering Agency certifies that NO members of the elected board, council, or other
key decision makers are on the Federal Government Exclusion List. Exclusions can be
found at www.sam.gov.
H. STATE and ADMINISTERING AGENCY agree that any additional funds which are
made available for any new phase(s) of work by future Federal obligations will be
encumbered on this PROJECT by use of a Federal Highway Administration-approved
"Authorization to Proceed" (E-76) STATE Finance Letter. ADMINISTERING AGENCY
agrees that Federal funds available for reimbursement will be limited to the amounts
obligated by the Federal Highway Administration.
Program Supplement 08-5282R-N043-ISTEA Page 3 of 3 1 3
ATTACHMENT 3
14
NOTICE OF EXEMPTION
To: ❑ Office of Planning and Research From: City of Palm Springs
1400 Tenth Street, Room 121 3200 E.Tahquitz Canyon Way
Sacramento,CA 95814 Palm Springs, CA 92262
® Clerk of the Board
County of Riverside
P.O. Box 751
Riverside,CA 92502-0751
Project Title: Ramon Road Pavement Rehabilitation, City Project No. 14-02
Project Applicant: City of Palm Springs
Project Location(Specific): Ramon Road from Sunrise to Compadre
Project Location(City): City_of_Palm Springs Project Location(County): Riversi
Project Description: The scope of work consists of cold milling existing asphalt concrete (AC) pavement; installation of AC in
designated pavement cracks; construction of asphalt concrete overlay; removal and reconstruction of AC pavement; installation
of inductive loop vehicle detectors; removal, reconstruction, and upgrade of ADA curb ramps; traffic striping and markings and
all other appurtenant work.
Name of Public Agency Approving Project: City of Palm Springs
Name of Person or Agency Carrying Our Project:City of Palm Springs, Public Works& Engineering Department
F I L E D / P O S T E D
Exempt Status: (check one)
County of Riverside
Peter Aldana
❑ Ministerial(Sec.21080(b)(1); 15268); Assessor-County Clerk-Recorder
E-201500412
❑ Declared Emergency (Sec. 21080(b)(3); 15269(a)); 85/21/2015 01:01 PM Fee: g 5 .110
Page 1 of 1
❑ Emergency Project(Sec. 21080(b)(4); 15269(b)(c)); ''II ff q qnp''CC
ReQeyl��O L ZUW By Oev�'Y
® Categorical Exemption. State type and section number: 15301 (c) 'III )�'jli�I�ujyC�jf'IIII
❑ Statutory Exemptions.State code number. �L`
Reasons why project is exempt: The Project consists of the repair and maintenance of existing City streets, involving negligible
or no expansion of use beyond that existing at the time of the City's determination. Therefore, the Project is considered
Categorically Exempt from CEOA pursuant to Section 15301 ®of the CEQA Guidelines.
Lead Agency Contact Person: Savat Khamohou. P.E. Area CodelielephonelExtension: (760)323-8744,ext. 8744
If filed by applicant:
1.Attach certirr ant o emption finding.
2.Has a Noll of x pill n filed by the public agency approving the project?❑Yes ❑ No
Signature: Date: Title: Asst. Director of Public Works/Asst. City Engineer
® Signed by Lead Agency❑Signed by Applicant
Authority cited: Sections 21083 and 21110, Public Resources Code Date received for filing at OPR:
Reference: Sections 21108, 21152,and 21152.1, Public Resources Code.
1�
ATTACHMENT 4
16
CATEGORICAL EXEMPTIONICATEGORICAL EXCLUSION DETERMINATION FORM
08/RI lm Springs STPLN $282(043)
Dist-Co.-Rte. or LocalAgency) P.M./P.M. EA/Project No. Federal-Aid Project No. Local Project)/Project No.
PROJECT DESCRIPTION: (Briefly describe project including need,purpose,location,limits,right-of-way requirements,and
activities involved in this box.Use Continuation Sheet,if necessary.)
The local agency proposes work consist of milling of existing asphalt concrete pavement; installation of AC
in designated pavement cracks;construction of asphalt concrete overlay; removal and reconstruction of AC
pavement; installation of inductive loop vehicle detectors;removal, reconstruction, and upgrade of ADA
curb ramps; traffic stripping and markings and all other appurtenant work. The project limits are on Ramon
Road within the existing right-of-way from 670' west of Sunrise Way to 700' east of Compadre Road.
CEQA COMPLIANCE (for state Projects only)
Based on an examination of this proposal and supporting information,the following statements are true and exceptions do not apply
(See 14 CCR 15300 et seq.):
• If this project falls within exempt class 3,4,5,6 or 11,it does not impact an environmental resource of hazardous or critical concern
where designated,precisely mapped and officially adopted pursuant to law.
• There will not be a significant cumulative effect by this project and successive projects of the same type in the same place,over time.
• There is not a reasonable possibility that the project will have a significant effect on the environment due to unusual circumstances.
• This project does not damage a scenic resource within an officially designated state scenic highway.
• This project is not located on a site included on any list compiled pursuant to Govt Code Q 65962.5('Cortese List').
• This project does not cause a substantial adverse change in the significance of a historical resource.
CALTRANS CEQA DETERMINATION (Check one)
❑ Exempt by Statute.(PRC 21080[b]; 14 CCR 15260 et seq.)
Based on an examination of this proposal,supporting information,and the above statements,the project is:
❑ Categorically Exempt.Class . (PRC 21084;14 CCR 153W el seq.)
❑ Categorically Exempt General Rule exemption.(This project does not fall within an exempt class,but 8 can be seen with
certainty that there is no possibility that the activity may have a significant effect on the environment(CCR 15061[b](3].)
N/A NIA
Print Name:Environmental Branch Chief Print Name:Project ManagerlDlA Engineer
NIA NIA
Signature Dale Signature Date
NEPA COMPLIANCE
In accordance with 23 CFR 771.117,and based on an examination of this proposal and supporting information,the State has
determined that this project:
• does not individually or cumulatively have a significant impact on the environment as defined by NEPA and is excluded from the
requirements to prepare an Environmental Assessment(EA)or Environmental Impact Statement(EIS),and
• has considered unusual circumstances pursuant to 23 CFR 771.117(b).
CALTRANS NEPA DETERMINATION (Check one)
® 23 USC 326: The State has determined that this project has no significant impacts on the environment as defined by NEPA,and
that there are no unusual circumstances as described in 23 CFR 771.117(b).As such,the project is categorically excluded from
the requirements to prepare an environmental assessment or environmental impact statement under the National Environmental
Policy Act.The State has been assigned,and hereby certifies that it has carried out the responsibility to make this determination
pursuant to Chapter 3 of Title 23,United States Code,Section 326 and a Memorandum of Understanding dated June 07,2013,
executed between the FHWA and the State.The State has determined that the project is a Categorical Exclusion under:
❑23 CFR 771.117(c):activity(c)(26)
❑23 CFR 771.117(d):activity(d)l
❑Activity_ listed in Appendix A of the MOU between FHWA and the State
❑ 23 USC 327: Based on an examination of this proposal and supporting information,the State has determined that the project is a
CE under 23 USC 327.
Aaron Burton Ile Sean Yeung
P >Wl s—ilPrint Name:Pro ManagenDLA Engineer
bi
Signature Date Signature D e
Date of Categorical Exclusion Checklist completion: 12/10/14 Date of ECR or equivalent:12/10/14
Briefly list environmental commitments on continuation sheet. Reference additional information,as appropriate(e.g.,CE checklist,
additional studies and design conditions).
February 12,2014
Page 1 of 2 17
CATEGORICAL EXEMPTION/CATEGORICAL EXCLUSION DETERMINATION FORM
Continuation Sheet
08/RIV/Palm Springs STPLN 5282(043)
Dist.-Co.-Rte. or Local Agency) P.M./P.M. EA/Project No. Federal-Aid Project No. Local Pro ect ro ect No.
Continued from page 1:
Project Description:
The local agency proposes work consist of milling of existing asphalt concrete pavement;installation of AC in designated pavement
cracks;construction of asphalt concrete overlay;removal and reconstruction of AC pavement;installation of inductive loop vehicle
detectors;removal,reconstruction,and upgrade of ADA curb ramps;traffic stripping and markings and all other appurtenant work. The
project limits are on Ramon Road within the existing right-of-way from 670'west of Sunrise Way to 700'east of Compadre Road.
Permits:
NPDES
February 12,2014
Page 2 of 2
is
NEPA/CEQA RE-VALIDATION FORM
DIST.ICO.IRTE. 08/RIV/Palm Springs
PMIPM N/A RECEWED
E.A.or Fed-Aid Project STPLN 5282(043) -
Other Project No.(specify) NIA CALTRANS ICT 8
PROJECT TITLE Ramon Road Pavement Rehabilitation Project A I —TA,7N
ENVIRONMENTAL Categorical Exclusion
APPROVALTYPE
DATE APPROVED 12/11/14
Check reason for consultation:
REASON FOR ®project proceeding to next major federal approval
CONSULTATION ❑Change in scope, setting,effects,mitigation measures, requirements
(23 CFR 771.129) ❑3-year timeline(EIS only)
❑N/A Re-Validation for CEQA onl
DESCRIPTION OF The project is proceeding to next major federal approval.There are is no change in scope,
CHANGED CONDITIONS setting,effects,mitigation measures,or requirements.
NEPA CONCLUSION-VALIDITY
Based on an examination of the changed conditions and supporting information:[Check ONE of the three statements below,
regarding the validity of the original document/determination(23 CFR 771.129).If document is no longer valid,indicate whether
additional public review is warranted and whether the type of environmental document will be elevated.]
IS] The original environmental document or CE remains valid. No further documentation will be prepared.
❑ The original environmental document or CE Is In need of updating;further documentation has been prepared and
❑is included on the continuation sheet(s)or❑ is attached.With this additional documentation,the original ED
or CE remains valid.
Additional public review is warranted(23 CFR 771.111(h)(3)) Yes❑ No❑
❑ The original document or CE is no longer valid.
Additional public review is warranted(23 CFR 771.111(h)(3)) Yes❑ No❑
Supplemental environmental document is needed. Yes❑ No❑
New environmental document is needed. Yes❑ No❑ (If"Yes,"specify type: )
CONCURRENCE WITH NEPA CONCLUSION
I„fwcur wph,�he NEP t s -allOve -
Sfgnatul"e.Environmen al Branch Chief Date Signature:P ojepfl4a ager/DLAE Date
r ,�
CEQA CONCLUSION :(Only mandated for projects on the State Highway System)
Based on an examination of the changed conditions and supporting information,the following conclusion has been reached
regarding appropriate CEQA documentation: (Check ONE of the five statements below,indicating whetherany additional
documentation will be prepared, and if so, what kind.If additional documentation is prepared,attach a copy of this signed form and
any continuation sheets.)
❑ Original document remains valid. No further documentation is necessary.
❑ Only minor technical changes or additions to the previous document are necessary. An addendum has been
or will be ❑ prepared and is ❑ included on the continuation sheets or ❑ will be attached. It need
not be circulated for public review.(CEQA Guidelines,§15164)
❑ Changes are substantial,but only minor additions or changes are necessary to make the previous document
adequate. A Supplemental environmental document will be prepared,and it will be circulated for public review.
(CEQA Guidelines,§15163)
❑ Changes are substantial,and major revisions to the current document are necessary. A Subsequent
environmental document will be prepared,and it will be circulated for public review.(CEQA Guidelines,§15162)
(Specify type ofsubsequent document, e.g., Subsequent FEIR.)
❑ The CE is no longer valid. New CE is needed. Yes❑ No❑
CONCURRENCE WITH CEQA CONCLUSION
I concur with the CEQA conclusion above.
N/A NIA
Signature:Environmental Branch Chief Date Signature:Project Manager/DLAE Date
Page 1 of I Revised June 2011
19
ATTACHMENT 5
20
RESOLUTION NO.
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
PALM SPRINGS, CALIFORNIA APPROVING PROGRAM
SUPPLEMENT AGREEMENT NO. N043 TO
ADMINISTERING AGENCY-STATE AGREEMENT FOR
FEDERAL-AID PROJECTS NO. 08-5282R WITH THE
STATE OF CALIFORNIA, IN THE AMOUNT OF $395,729,
FOR THE RAMON ROAD PAVEMENT REHABILITATION
(FROM SUNRISE TO EL CIELO), CITY PROJECT NO. 14-
02, FEDERAL-AID PROJECT NO. STPLN-5282 (043), AND
AUTHORIZING THE CITY MANAGER TO EXECUTE THE
AGREEMENT ON BEHALF OF THE CITY OF PALM
SPRINGS
WHEREAS, the City of Palm Springs has submitted to the California Department of
Transportation a request for authorization to proceed with the construction phase of the
Ramon Road Pavement Rehabilitation, City Project No. 14-02, Federal Aid Project No.
STPLN-5282 (043), requiring obligation of $395,729 of Surface Transportation Program
("STP") federal-aid funds; and
WHEREAS, the California Department of Transportation has prepared Program
Supplement Agreement No. N043 to administering Agency-State Agreement No. 08-
5282R with the state of California, obligating $395,729 of federal-aid funds for the
Ramon Road Pavement Rehabilitation, City Project No. 14-02, Federal Aid Project No.
STPLN-5282 (043)
THE CITY COUNCIL OF THE CITY OF PALM SPRINGS DOES HEREBY RESOLVE
AS FOLLOWS:
SECTION 1. Program Supplement Agreement No. N043 to administering Agency-State
Agreement No. 08-5282R with the state of California, obligating $395,729 of federal-aid
funds for the Ramon Road Pavement Rehabilitation, City Project No. 14-02, Federal Aid
Project No. STPLN-5282 (043) is approved.
SECTION 2. The City Manager is authorized to execute and administer the Program
Supplement Agreement as may be necessary.
� 1
Resolution No.
Page 2
ADOPTED THIS 4th day of November, 2015.
David H. Ready, City Manager
ATTEST:
James Thompson, City Clerk
CERTIFICATION
STATE OF CALIFORNIA )
COUNTY OF RIVERSIDE ) ss.
CITY OF PALM SPRINGS )
I, JAMES THOMPSON, City Clerk of the City of Palm Springs, hereby certify that
Resolution No. is a full, true and correct copy, and was duly adopted at a regular
meeting of the City Council of the City of Palm Springs on November 4, 2015, by the
following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
James Thompson, City Clerk
City of Palm Springs, California
22