FORN�P City Council Staff Report
DATE: March 1, 2017 CONSENT CALENDAR
SUBJECT: ACCEPTANCE OF THE CALLE PALO FIERRO SEWER LINE
REPLACEMENT, CITY PROJECT NO.16-14
FROM: David H. Ready, City Manager
BY: Engineering Services Department
SUMMARY
Formal City Council acceptance of the Calle Palo Fierro Sewer Line Replacement, City
Project No.16-14, is required to document the completion of the public works
improvement, and to allow the City's filing of a Notice of Completion with the Riverside
County Recorder in accordance with Section 9200 of the California Civil Code.
RECOMMENDATION:
1) Accept the public works improvement identified as the Calle Palo Fierro Sewer Line
Replacement, City Project No. 16-14, as completed in accordance with the plans and
specifications; and
2) Authorize the City Engineer to execute and file for recordation with the Riverside
County Recorder a Notice of Completion for Calle Palo Fierro Sewer Line
Replacement, City Project No. 16-14.
STAFF ANALYSIS:
The City has approximately 230 miles of sewer mainline in its sewer collection system
that conveys untreated sewage to the Wastewater Treatment Plant ("WWTP") where it
is treated for reuse and reclaimed water purposes. On November 4, 2015, the City
Council approved a Wastewater Services Agreement (O&M) with Veolia Water West
Operating Services, Inc., ("Veolia"), providing for Veolia's operation and maintenance of
the City's sewer collection system and WWTP.
As part of Veolia's services, Veolia monitors the sewer collection system by routinely
video-taping, recording, and providing condition ratings for each sewer line segments
and sewer manholes. During its routine maintenance and inspection of the sewer
collection system, Veolia identified the sewer line segment between sewer manhole
ITEM NO. 1-•E-
E12039 and E12045 in need of replacement due to several areas along the sewer line
that are cracked, broken, and deformed. Veolia confirmed that soil has intruded into the
sewer line at two locations where the sewer line has broken and tree roots have
intruded into the sewer flow. Additionally, Veolia identified a sag in the sewer line where
its video camera could not access.
Veolia has rated this segment of sewer line at 5, in accordance with Veolia's Pipeline
Assessment Certification Program ("PACP"). The PACP ratings range from 1 to 5 with
repairs required for ratings of 3 or higher; a rating of 5 is the worst condition and
requires replacement. A location map of the proposed sewer line replacement between
manholes E12039 and E12045 is shown in Figure 1 and a Vicinity Map showing a 500
feet radius of the project location is provided as Attachment 1.
r
. .
A.
o a
o
2.
Figure 1
Section 5.3 of the Operations and Maintenance Agreement, allows Veolia to undertake
such a capital project. On October 5, 2016, the City Council authorized the City
Engineer to issue a Notice to Proceed (NTP) Authorizing Veolia West Operation
Services, Inc. (Veolia) in the amount of $90,568, for the Calle Palo Fierrc Sewer Line
Replacement, City Project No. 16-14, (the "Project"). Veolia has completed the
replacement of approximately 200 linear feet of 12" sewer main (manhole to manhole)
on the segment between sewer manholes E12039 and E12045 on Calle Palo Fierro
north of Sonora shown as the highlighted segment in Figure 1. The line segment was
replaced due to several areas along the sewer line that were cracked, broken, had
02
severe root intrusion, and the line was also unreachable by CCTV video camera to
perform maintenance.
With any capital project undertaken by Veolia, Veolia operates as the general contractor
under its own contractor's license. As the general contractor, Veolia is responsible for
ensuring all construction is performed in accordance with State and federal rules and
regulations, and is liable for all risks and damages that may occur. Accordingly, Veolia
obtains general liability insurance for each project, which is passed as a direct cost to
the City.
The Project was administered and contracted to Veolia, who subcontracted to G&M
Construction the construction of the sewer line. Veolia has determined that G&M has
satisfactorily completed the Project on November 15, 2016, has conducted a final
inspection and found the work to be in compliance with the plans, specifications and
standards of the City of Palm Springs as evidenced by letter from Veolia dated February
21, 2017, and included as Attachment 2.
Staff recommends that the City Council accept the Project, as required by Section 9200
of the California Civil Code, and authorize the City Engineer to file and record a Notice
of Completion within 15 days of the City Council's action. A copy of the Notice of
Completion to be submitted to the County is included as Attachment 3.
ENVIRONMENTAL IMPACT:
Section 21084 of the California Public Resources Code requires Guidelines for
Implementation of the California Environmental Quality Act ("CEQA"). The Guidelines
are required to include a list of classes of projects which have been determined not to
have a significant effect on the environment and which are exempt from the provisions
of CEQA. In response to that mandate, the Secretary for Resources identified classes of
projects that do not have a significant effect on the environment, and are declared to be
categorically exempt from the requirement for the preparation of environmental
documents. In accordance with Section 15301 "Existing Facilities," Class 1 projects
consist of the operation, repair, maintenance, permitting, leasing, licensing, which
includes restoration or rehabilitation of deteriorated or damaged structures, or facilities
to meet current standards of public health and safety. Therefore, in accordance with
Section 15301(d), staff determined that repair of the sewer line on Calle Palo Fierro is
considered categorically exempt from CEQA.
FISCAL IMPACT:
The Project was funded through Wastewater Treatment Funds under account no. 420-
6800-57041. The project had no contract change orders. Five percent retention is held
for final payment until 30 days after the filing of the Notice of Completion. The total
amount for construction was $90,568.
Table 1 below is a summary of the total costs incurred for the Project.
03
FY 15116 FY 16/17
Phase Expenditure Expenditure Final Cost
Administration & Design $19,500 $19,500
Construction Contract $90,568 $90,568
Total Cost $19,500 $90,568 $110,068
Table 1
The Project was funded through the following sources as shown in Table 2:
Fund Name Account Actual
VWVfP Funds 420-6800-57041 $110,068
Total Expenditures for Project $110,068
Project Budget $110,068
Remaining Balance $0
Table 2
The City is holding retention of $4,528.40 for Veolia, pending acceptance of the
improvements and filing of the Notice of Completion with the County Recorder's office.
Since this project is a maintenance effort, the Finance Department does not need to add
the cost of this project to the City's fixed asset system, as no new assets have been
created in compliance with Governmental Accounting Standard Board (GASB) 34
Standards for Financial Reporting of Infrastructure Assets.
SUBMITTED
Marcus L. Fuller, MPA, P.E., P.L.S. David H. Ready, Esq., Ph.
Assistant City Manager/City Engineer City Manager
Attachments:
1. Vicinity Map (500' Radius)
2. Letter from Veolia
3. Notice of Completion
04
Attachment 1
05
n
�' ~OFy PLM Se9
Engineering Services Department w E
Vicinity Map (500' Radius)
C44FOR��P•
S
■
ib
mom
Ella
� � ,
At �'
Ilk
ZVI 12 No
At
CITY OF PALM SPRINGS
06
Attachment 2
07
Qvr=OL1A
WATER
February 21, 2017
City of Palm Springs
3200 E. Tahquitz Canyon Way
Palm Springs, CA 92262
Attn: Savat Khamphou
RE: Notice of Completion
Calle Palo Fierro Sewer Line Replacement, City Project No. 16-14
Dear Mr. Khamphou,
As of November 15, 2016, Veolia Water West Operating Services, Inc. has completed all
work associated with the Calle Palo Fierro Sewer Line Replacement Project, City Project No.
16-14 in accordance with the plans and City of Palm Springs standards.
I have attached a copy of the Notice of Completion document for the project. I recommend
that the Notice of Completion be accepted by the City and filed and recorded with the
Riverside County Recorder.
If you have any questions or concerns regarding the project, please feel free to contact me
at 562-397-5706 or by email, michelle.mcleyCcoveolia.com.
WSIncerel ,
Michelle McLey
Veolia Water W t Operating S vices, Inc.
Veolla Water West operating Services.Inc.
4375 Mesquite Ave.,Palm Springs,CA 92264
Tel 562 397-5706 08
v .veolianorthamertca.com
Attachment 3
Recording Requested By:
City of Palm Springs
When Recorded Mail To:
Name JKathleen D.Hart,Interim City Clerk
Street
Address 3200 E.Tahquitz Canyon Way
Ciry&State Palm Springs,CA 92262
SPACE ABOVE THIS LINE FOR RECORDERS USE
NOTICE OF COMPLETION
(CA Civil Code§§818M190.8100-8118,9200-9208)
NOTICE IS HEREBY GIVEN THAT:
1. The undersigned is an owner of an interest of estate in the hereinafter described real property,the nature of which interest or estate is:
Fee (e.g.fee,leasehold,joint tenancy,etc.)
2. The full name and address of the undersigned owner or reputed owner and of all co-owners or reputed co-owners are:
Name Street and No. City State
City of Palm Springs 3200 E.Tahquitz Canyon Way Palm Springs CA 92262
3. The name and address of the direct contractor for the work of improvement as a whole is:
Veolia Water West Operating Services,Inc.
4. This notice is given for(check one):
0 Completion of the work of improvement as a whole.
❑ Completion of a contract for a particular portion of the work of improvement(per CA Civ.Code §8186).
5. If this notice is given only of completion of a contract for a particular portion of the work of improvement(as provided in CA Civ.Code
§8186),the name and address of the direct contractor under that contract is:
Not Applicable
6. The name and address of the construction lender,if any,is:
Not applicable
7. On the 15 day of November ,2016 ,there was completed upon the herein described property a work of improvement as a
whole(or a particular portion of the work of improvement as provided in CA Civ.Code§8186)a general description of the work provided:
City Project No.16-14 Palo Fierro Sewer Line Replacement Project
8. The public work herein referred to is situated in the City of Palm Springs County of Riverside
State of California,and is described as follows:
Replacement of approximately 20OLF of 12"sewer main(manhole to manhole)on the segment between sewer manholes E12039 and E12045
9. The street address of said property is:
Calls Palo Fierro and Sonora Ave
10. If this Notice of Completion is signed by the owners successor in interest,the name and address of the successor's transferor is:
Not applicable
I certify(or declare)under penalty of perjury under the laws of the State of California that the foregoing is true and correct.
Date: By:
Signature of Owner or Owner's Authorized Agent-Assistant City Manager/City Engineer for City of Palm Springs
Marcus Fuller
C Porter Law Group,Inc.2013 Print Name
Page 1 of 2 10
VERIFICATION
I, Marcus Fuller state:I am the Assistant City Manager/City Engineer ("Owner', "President",
"Authorized Agent","Partner',etc.)of the Owner identified in the foregoing Notice of Completion. I have read said Notice of Completion and know the
contents thereof;the same is true of my own knowledge.
I declare under penalty of perjury under the laws of the Stale of California that the foregoing is true and correct.
Executed on (date),at Palm Springs (city), CA (State).
Signature of Owner or Owner's Authorized Agent
A Notary Public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this
certificate is attached,and not the truthfulness,accuracy,or validity of that document.
STATE OF CALIFORNIA
COUNTY OF Riverside
On (date), before
me, Notary Public(name and title of
officer)personally appeared who proved
to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are
subscribed to the within instrument and acknowledged to me that he/she/they executed the
same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the
instrument the person(s),or the entity upon behalf of which the person(s)acted,executed the
instrument.
I certify under PENALTY OF PURJURY under the laws of the State of California that the
foregoing paragraph is true and correct.
Witness my hand and official seal.
Page 2 of 2 Signature 1