Subject: APPROVAL OF PLANS, SPECIFICATIONS AND ESTIMATE (PS&E)
AND AUTHORIZATION TO BID THE PALM SPRINGS ROOF REPAIR
AND REPLACEMENT PROJECT, CITY PROJECT NO. 16-05
From: David H. Ready, City Manager
Initiated by: Engineering Services Department
SUMMARY
The construction documents (Plans, Specifications and Estimate) are completed and in
accordance with Section 7.03.040 of the Procurement and Contracting Code, the City
Council is required to approve and adopt plans, specifications and working details, and
authorize the bid request for all public projects in excess of $100,000. Approval of this
project will allow staff to proceed with this public project, with an estimated cost of
$675,000.
RECOMMENDATION:
Approve the plans, specifications and estimate and authorize staff to advertise and
solicit bids for the Palm Springs Roof Repair and Replacement Project, City Project No.
16-05.
STAFF ANALYSIS:
As part of the Fiscal Year 2016/17 budget, the City Council appropriated $275,000 as
budget through Measure J Capital Project Fund for the Palm Springs Roof Repair and
Replacement Project, City Project No. 16-05 (Project).
During the rainy season early last year, several complaints were received by the
Department of Maintenance & Facilities regarding suspected roof leaks at various city
facilities. Large holes in the existing roofing system were the main cause of these
complaints. The complaints were generated from the following city facilities:
1. City Hall, located at 3200 E. Tahquitz Canyon Way
2. Swim Center, located at 405 S. Pavilion Way
3. Leisure Center, located at 401 S. Pavilion Way
4. Pavilion, located at 401 S. Pavilion Way
5. Demuth Community Center, located at 3601 E. Mesquite Avenue -�
ITEM NO.�_
City Council Staff Report
June 7, 2017 -- Page 2
Approve RFB CP16-05, Palm Springs Roof Repair and Replacement Project
Based on this need, the Engineering Services Department initiated a new public works
capital project to repair and replace the existing roofing systems at the five specified
locations. Staff requested proposals from the city's various on-call civil engineering firms
to provide the necessary professional services to prepare contract documents (plans
and specifications) for the Project.
On September 28, 2016, in accordance with their on-call agreement, the City Manager
authorized Harris & Associates (Harris) to proceed with preparation of design plans and
specifications at a cost not to exceed of $20,040. On December 19, 2016, Harris
submitted an extra work cost proposal for $2,310 for the preparation of a construction
estimate for the Project. A total of $22,350 has been budgeted to Harris for the design
phase.
The scope of work consists of removing the existing roof system and accessories,
removing and reinstalling utilities and equipment, surface preparation, roof installation
(fibertitie membrane), roof accessories, substrate, wood beam cap, repairs, and
inspections and all appurtenant work. Below are images from the construction drawings
shown in Figures 1 through 5.
� OPEN
F 7
E
- -
�- -� OPEN -- �tg OPEN y
OPEN
�<.
- i
® ® ® ® Ml
'OPEN
i
City Hall
Figure 1
Q �Y
City Council Staff Report
June 7, 2017 -- Page 3
Approve RFB CP16-05, Palm Springs Roof Repair and Replacement Project
0 o m-
A
52 .
y x
9 f
i�
t fA
A
1
Swim Center
Figure 2
803
TYP.
TY P.
y
OPEN =—, --_
s
� ozo
803
_, ��&� 803 TYR
TYP.
TYP
8 77
TYP.
Leisure Center 03
Figure 3
City Council Staff Report
June 7, 2017 -- Page 4
Approve RFB CP16-05, Palm Springs Roof Repair and Replacement Project
-7Y],
t I
I
.z .
Pavilion
Figure 4
1 AI
L,Uit 083
cv � � 902
_........,.. y
ri 803
I
864 847 834
t
IYP. 17 * 806
( — 803
h � �
864 803
804
� I
i
f
III
Demuth Community Center 04
Location 5
City Council Staff Report
June 7, 2017 -- Page 5
Approve RFB CP16-05, Palm Springs Roof Repair and Replacement Project
The contract documents (plans and specifications) prepared by Harris have been
reviewed and approved by the City's Building Department. The project has also been
reviewed by the City's Planning Department under its Minor Architectural Review
procedures. The Planning Department has determined the architectural changes to the
roof repair and replacement are appropriate and has issued approvals through Case
No's. 3.3613, 3.3377, and 5.0793. The contract documents are ready to formally solicit
construction bids for the Project.
With City Council approval, staff will advertise the project in the Desert Sun, submit the
Notice Inviting Bids to plan rooms, and provide the bid documents available free of
charge to prospective bidders. A copy of the contract documents are on file with the
Public Works & Engineering Department. The following tentative schedule has been
identified for the bid process:
Notice Inviting Bids to be posted: June 8, 2016
Deadline for receipt of bids: 3:00 PM, July 13, 2017
Contract awarded by City Council: September 6, 2017
ENVIRONMENTAL IMPACT:
Section 21084 of the California Public Resources Code requires Guidelines for
Implementation of the California Environmental Quality Act ("CEQA"). The Guidelines are
required to include a list of classes of projects which have been determined not to have a
significant effect on the environment and which are exempt from the provisions of CEQA.
In response to that mandate, the Secretary for Resources identified classes of projects
that do not have a significant effect on the environment, and are declared to be
categorically exempt from the requirement for the preparation of environmental
documents. In accordance with Section 15301 "Existing Facilities," Class 1 projects
consist of repair, maintenance, or minor alteration of existing public facilities involving
negligible or no expansion; therefore, the Palm Springs Roof Repair and Replacement
Project, City Project No. 16-05, is considered categorically exempt from CEQA, and a
Notice of Exemption has been prepared and will be filed with the Riverside County Clerk.
A copy of the Notice of Exemption is included as Attachment 1.
FISCAL IMPACT:
A total of $275,000 is currently budgeted for the Project through Measure J Capital
Project Fund (Fund 260). The final construction estimate for the Project is $675,000 as
shown in Attachment 2. The total estimated cost is higher as overall construction costs
have increased due to economic growth. In the current construction climate, contractors
are no longer under-cutting bids due to scarcity of work.
The Project budget and incurred expenditures are listed in Table 1, which indicates an
additional budget of $441,024 will be required to fully fund the Project due to the current
estimated cost.
05
City Council Staff Report
June 7, 2017 -- Page 6
Approve RFB CP16-05, Palm Springs Roof Repair and Replacement Project
Table of Project Costs Amount
FY16/17 Measure J Fund 260 $275,000
Design Services $22,350)
Project Administration (through 5/30117 $3,674)
Project Administration Estimated $5,000)
Construction Inspection Estimated ($10,000
Construction Contract $675,000)
Additional Budget Required $441,024
Table 1
Staff recommends that the City Council authorize bidding of the Project to obtain final
costs, allowing staff to identify funding alternatives for City Council consideration at the
time a contract is scheduled for award.
SUBMITTED:
Thomas Garcia, P.E. Marcus L. Fuller, M A, P.E., P.L.S.
City Engineer Assistant City Manager
David H. Ready, Esq., Ph
City Manager
Attachments:
1. CEQA Notice of Exemption
2. Construction Estimate
06
Attachment 1
07
Palm Springs Roof Replacement Construction Cost Estimate
ITEM DESCRIPTION OTY UNIT UNIT PRICE EXTENSIONS*
1.0 City Hall
1.1 Demolition I LS $ 23,700.00 $ 29,388.00
1.2 Re-Roofing(FB O/Existing Roof System) 47,339 SF $ 4.00 $ 234,801.44
1.3 Roofing Accessories 47,339 SF $ 2.00 $ 117,400.72
1.4 Misc.Utilities(Mechanical/Electrical) I LS $ 25,000.00 $ 31,000.00
1.5 City Hall Subtotal $ 412,590.16
2.0 Swim Center
2.1 Demolition I LS $ 1,000.00 $ 1,240.00
2.2 Substrate Replacement 819 SF $ 4.00 $ 4,062.24
2.3 Re-Roofing(O/Existing Roof System) 1,490 SF $ 3.00 $ 5,542.80
2.4 Roofing Accessories 1,490 SF $ 2.00 $ 3,695.20
2.5 Beam Cap 150 LF $ 6.00 $ 1,116.00
2.6 Misc.Utilities(Mechanical/Electrical) I LS $ - $ -
2.7 Swim Center Subtotal $ 15,656.24
3.0 Leisure Center
3.1 Demolition I LS $ 6,250.00 $ 7,750.00
3.2 Re-Roofing 0 SF $ 3.00 $ -
3.3 Roofing Accessories 1,147 SF $ 2.00 $ 2,844.56
3.4 Misc.Utilities(Mechanical/Electrical) I LS $ I,S00.00 $ 1,860.00
3.5 Leisure Center Subtotal $ 12,454.56
4.0 Pavilion
4.1 Demolition I LS $ 6,250.00 $ 7,750.00
4.2 Re-Roofing 0 SF $ 3.00 $ -
4.3 Roofing Accessories 1,153 SF $ 2.00 $ 2,859.44
4.4 Misc.Utilities(Mechanical/Electrical) I LS $ 3,000.00 $ 3,720.00
4.5 Pavilion Subtotal $ 14,329.44
5.0 Demuth Community Center
5.1 Demolition I LS $ 9,500.00 $ 11,780.00
5.2 Re-Roofing(O/Existing Roof System) 13,946 SF $ 3.00 $ 51,879.12
5.3 Re-Roofing(Simulated Standing Seam) 4,800 SF $ 4.00 $ 23,808.00
5..4 Roofing Accessories 18,746 SF $ 2.00 $ 46,490.08
5.5 Misc.Utilities(Mechanical/Electrical) I LS $ 18,000.00 $ 22,320.00
5.6 Demuth Community Center Subtotal $ 156,277.20
6.0 ESTIMATED TOTAL CONSTRUCTION COSTS $ 611,307.60
*estimate extensions include 24%Contractor Mark-up for General Conditions&Overhead/Profit
7.0 SOFT COSTS
7.1 Construction Contingency Costs 10% $ 61,130.76
7.2 Testing and Inspections 0% $ -
7.3 Time/Inflation Escalation Index 0% $ -
7.4 Permitting 0% $ -
7.5 TOTAL SOFT COSTS $ 61,130.76
8.0 TOTAL ESTIMATED COST $ 672,438.36
Jeff Katz Architecture May 31.2017
08
Attachment 2
09
NOTICE OF EXEMPTION
To: ❑ Office of Planning and Research From: City of Palm Springs
1400 Tenth Street, Room 121 3200 E.Tahquitz Canyon Way
Sacramento, CA 95814 Palm Springs,CA 92262
® Clerk of the Board
County of Riverside
P.O.Box 751
Riverside,CA 92502-0751
Project Title: Palm Sorings Roof Repair and Replacement Protect.City Prolect No. 16-05
Project Applicant: fCy of Palm Springs
Project Location (Specific): Various facilities.
1. City Hall located at 3200 E.Tahquitz Canyon Way
2, Swim Center located at 405 S. Pavilion Way
3. Leisure Center located at 401 S. Pavilion Way
4. Pavilion located at 401 S.Pavilion Way
5. Demuth Community Center located at 3601 E.Mesquite Avenue
Project Location(City): City of Palm Springs Project Location(County): Riverside
Project Description: The scope of work includes roof repairs and replacement at various city facilities. The work consists of
removing the existing roof system and accessories, removing and reinstalling utilities and equipment, surface preparation, roof
Installation(fibertits membrane), roof accessories,substrate,wood beam cap,repairs, and inspections.
Name of Public Agency Approving Project: City of Palm Springs
Name of Person or Agency Carrying Our Project:City of Palm Springs, Engineering Services Department
3200 E.Tahquitz Canyon Way,Palm Springs,CA 92262
Exempt Status:(check one)
❑ Ministerial(Sec.21080(b)(1); 15268);
❑ Declared Emergency(Sec.21080(b) (3); 15269(a));
❑ Emergency Project(Sec.21060(b)(4);15269(b)(c));
® Categorical Exemption. State type and section number: 15301 Class 1 (a)-Existing Facilities
❑ Statutory Exemptions.State code number.
Reasons why project Is exempt: Class 1 consists of operation, repair, maintenance, permitting, leasing, licensing, or minor
alteration of existing public or private structures,facilities, mechanical equipment, or topographic features, involving negligible or
no expansion of use beyond that existing at the time of the lead agency's determination. Interior or exterior alterations involving
such things as interior partitions, plumbing, and electrical conveyances. Therefore, the Palm Springs Roof Repair and
Replacement Project, City Project No. 1645,is considered categorically exempt from CEOA.
Lead Agency Contact Person: Tom Garcia Area Code/Telephone/Extension: Q601 322$338
If filed by applicant:
1.Attach certified document of exemption finding.
2.Has a Notice of Exemption been filed by the public agency approving the project?❑Yes ❑ No
Signature; — - Date: 5/2/2017 Title: City Enalneer
® Signed by Lead Agency[]Signed by Applicant
Authority cited: Sections 21083 and 21110, Public Resources Code Date received for filing at OPR:
Reference: Sections 21108,21152,and 21162.1, Public Resources Code.
10
Attachment 2
Palm Springs Roof Replacement Construction Cost Estimate
ITEM DESCRIPTION OTY UNIT UNIT PRICE EXTENSIONS*
1.0 City Hall
1.1 Demolition I LS $ 23,700.00 $ 29,388.00
1.2 Re-Roofing(FB O/Existing Roof System) 47,339 SF $ 4.00 $ 234,801.44
1.3 Roofing Accessories 47,339 SF $ 2.00 $ 117,400.72
1.4 Misc.Utilities(Mechanical/Electrical) I LS $ 25,000.00 $ 31,000.00
1.5 City Hall Subtotal $ 412,590.16
2.0 Swim Center
2.1 Demolition I LS $ 1,000.00 $ 1,240.00
2.2 Substrate Replacement 819 SF $ 4.00 $ 4,062.24
2.3 Re-Roofing(O/Existing Roof System) 1,490 SF $ 3.00 $ 5,542.80
2.4 Roofing Accessories 1,490 SF $ 2.00 $ 3,695.20
2.5 Beam Cap I50 LF $ 6.00 $ 1,116.00
2.6 Misc.Utilities(Mechanical/Electrical) I LS $ - $ -
2.7 Swim Center Subtotal $ 15,656.24
3.0 Leisure Center
3.1 Demolition I LS $ 6,250.00 $ 7,750.00
3.2 Re-Roofing 0 SF $ 3.00 $ -
3.3 Roofing Accessories 1,147 SF $ 2.00 $ 2,844.56
3.4 Misc. Utilities (Mechanical/Electrical) I LS $ 1,500.00 $ 1,860.00
3.5 Leisure Center Subtotal $ 12,454.S6
4.0 Pavilion
4.1 Demolition I LS $ 6,250.00 $ 7,750.00
4.2 Re-Roofing 0 SF $ 3.00 $ -
4.3 Roofing Accessories 1.153 SF $ 2.00 $ 2,859.44
4.4 Misc.Utilities(Mechanical/Electrical) I LS $ 3,000.00 $ 3,720.00
4.5 Pavilion Subtotal $ 14,329.44
5.0 Demuth Community Center
5.1 Demolition I LS $ 9,500.00 $ 11,780.00
5.2 Re-Roofing(O/Existing Roof System) 13,946 SF $ 3.00 $ 51,879.12
5.3 Re-Roofing(Simulated Standing Seam) 4,800 SF $ 4.00 $ 23,808.00
5..4 Roofing Accessories 18,746 SF $ 2.00 $ 46,490.08
5.5 Misc.Utilities(Mechanical/Electrical) I LS $ 18,000.00 $ 22,320.00
5.6 Demuth Community Center Subtotal $ I S6,277.20
6.0 ESTIMATED TOTAL CONSTRUCTION COSTS $ 611,307.60
*estimate extensions include 24%Contractor Mark-up for General Conditions&Overhead/Profit
7.0 SOFT COSTS
7.1 Construction Contingency Costs 10% $ 61,130.76
7.2 Testing and Inspections 0% $ -
7.3 Timetinflation Escalation Index 0% $ -
7.4 Permitting 0% $ -
7.5 TOTAL SOFT COSTS $ 61,130.76
8.0 TOTAL ESTIMATED COST $ 672,438.36
Jeff Katz Architecture May 31,2017
12
RECEIVED CITY OF PALM SPR1f4C`. �i17
2011 JUN 26 AM 9: 02
STATE OFCALIFORNIA-THE RESOURCES AGENCY
DEPARTMENT OF FISHAND GAME UFFICEOi IIIECii ' �t`:
ENVIRONMENTAL FILING FEE CASH RECEIPT
Receipt#: 17-158132
State Clearinghouse#(if applicable):
Lead Agency:CITY OF PALM SPRINGS Date: 0511 8/2 01 7
CountyAgency ofFiling: RIVERSIDE LbarrnerBNo: E-201700613
Project Title: PALM SPRINGS ROOF REPAIR 8t REPLACEMENT PROJECT
Project Applicant Name: CITY OF PALM SPRINGS PhveNaotdre (760)322-8339
Project ApplicantAddress: 3200 E.TAHQUITZ CANYON WAY, PALM SPRINGS, CA 92262
Project Applicant: LOCAL PUBLIC AGENCY
CHECKAPPLICABLE FEES:
❑Environmental Impact Report
❑Negative Declaration
❑Applicanon Fee W'aiet-Dtversunt(Slate WaterResourcesControl Boardonly)
❑Project Subject to Certified RegulaioryPrograms
❑CountyAdrrimislranon Fee $0.00
❑Project that is exempt from fees(DFG No Effect Determination (Form Attached))
®Project drat is esemrptfmm fees(Notice o)Esemption)
Total Received $50.00
.Signature and title ofperson receiving payment Deputy
,Votes:
NOTICE OF EXEMPTION
To: ❑ Office of Planning and Research From: City of Palm Springs
1400 Tenth Street, Room 121 3200 E. Tahquitz Canyon Way
Sacramento, CA 95814 Palm Springs, CA 92262
® Clerk of the Board
County of Riverside
P.O. Box 751
Riverside, CA 92502-0751
Project Title: Palm Springs Roof Repair and Replacement Project City Project No 16-05
Project Applicant: City of Palm Springs F I L E D / P O S T E D
County of Riverside
Project Location (Specific): Various facilities. Peter Aldana
1. City Hall located at 3200 E.Tahquitz Canyon Way Assessor-County Clerk-Recorder
E-201700613
05/18/2017 04:25 PM Fee: $ 50 00
2. Swim Center located at 405 S. Pavilion Way Page 1 0f
3. Leisure Center located at 401 S. Pavilion Way Removed JU� 2 1 201By: Deputy
4. Pavilion located at401 S. Pavilion Way 'III ��r� �«�� � 'I III
5. Demuth Community Center located at 3601 E. Mesquite Avenue ��yy�r`(�` `;,,��' r ,FI
Project Location (City): City of Palm Springs Project Location (County): Riverside
Project Description: The scope of work includes roof repairs and replacement at various city facilities. The work consists of
removing the existing roof system and accessories, removing and reinstalling utilities and equipment, surface preparation, roof
installation (fibertite membrane), roof accessories, substrate,wood beam cap, repairs, and inspections.
Name of Public Agency Approving Project: City of Palm Springs
Name of Person or Agency Carrying Our Project: City of Palm Springs, Engineering Services Department
3200 E. Tahquitz Canyon Way, Palm Springs, CA 92262
Exempt Status: (check one)
❑ Ministerial (Sec. 21080(b) (1); 15268);
❑ Declared Emergency(Sec. 21080(b) (3); 15269(a));
❑ Emergency Project(Sec. 21080(b) (4); 15269 (b)(c));
® Categorical Exemption. State type and section number: 15301 Class 1 (a)—Existing Facilities
❑ Statutory Exemptions. State code number:
Reasons why project is exempt: Class 1 consists of operation, repair, maintenance, permitting, leasing, licensing, or minor
alteration of existing public or private structures, facilities, mechanical equipment, or topographic features, involving negligible or
no expansion of use beyond that existing at the time of the lead agency's determination. Interior or exterior alterations involving
such things as interior partitions, plumbing, and electrical conveyances. Therefore, the Palm Springs Roof Repair and
Replacement Project, City Project No. 16-05, is considered categorically exempt from CEQA.
Lead Agency Contact Person: Tom Garcia Area Code/Telephone/Extension: (760) 322-8339
If filed by applicant:
1.Attach certified document of exemption finding.
2.Has a Notice of Exemption been filed by the public agency approving the project? ❑ Yes ❑ No
Signature: Date: 5/2/2017 Title: City Engineer
® Signed by Lead Agency ❑Signed by Applicant
Authority cited: Sections 21083 and 21110, Public Resources Code Date received for filing at OPR:
Reference: Sections 21108, 21152, and 21152.1, Public Resources Code.
The Desert Sun
750 N Gene Autry Trail Certificate of Publication
Palm Springs, CA92262 RECEIVED
760-778-45781 Fax 760-778 I 11 OF PALM SPRING
State Of California ss: 2017 JUN 26 AM 9= 01
County of Riverside
OFFICE OF IHE CITY CLL
NO 0938: Cfry OF PALM SPRINGS
Advertiser: CITY OF PALM SPRINGS/LEGALS NOTICE INVITING BIDS
PO BOX 2743 PALM SPRINGS ROOF REPAIR AND REPLACEMENT PROJECT
CITY PROJECT NO.16-05
PALM SPRINGS CA 92263 N-1 NOTICE 15 HEREBY.GIVEN that sealed bids for the Palm Springs Roof Repair
and Replacement Project,City Project No..16-05,will be received by the Office
of the Procurement and.Contracting Manager of the City of.Palm 5prings,
Order# 0002201131 - California,until 3:00 P.M.on Thursday,July 13,2017,at which time they will be
opened and read aloud.The Engineer's estimate range is$610,000 to$710,060.
N-2 DESCRIPTION OF THE WORK:The Work comprises roof repairs and replace.
ment at five(5)various city facilities.The scope of work includes removing the
-existing roof system and accessories, removing and reinstalling utilities and
equipment,"surface preparation,,roof installation(fibertite''membrane),;roof ac-
cessories,substrate,wood beam cap,repairs,inspections and other.appurtenant
work. - -
The work shall be diligently prosecuted to completion before the expiration 6f:
80 working days.The Contractor may commence work In the areas specified In-
I am over the age of 18 years old, a citizen Of dependen Ity or simultaneously.Please reference the Spacial Provisions;Section
6- .1.1 Construction Schedule Sequencing. -the United States and not a party to, or have N-3 AWARD OF CONTRACT: ..
(a)The City reserves the.right after opening bids to reject any or all bids,to
interest in this matter. I hereby certify that the waive any informality(non-responsiveness) in a bid, or make award to the
lowest responsive, responsible bidder, and reject all other bids,.as it may best
attached advertisement appeared In said - serve the interest;of the City.If there are multiple and/or alternative Bid Schad-
Wes;Bidders are required to bid on all Bid Schedules.
newspaper(set in type not smaller than non (b)As a condition of award,the successful hinder will be required to submit
ayment and performance bonds and insurance
pariel) in each and entire issue of said Pa As a condition of award or after April 1,2015,the contractor and any sub-
contractor listed on the bid must be registered with the Department of Industri-
newspaper and not in any supplement thereof of Relations pursuant to Section 1725.5 of the California Labor Code.''
N-4,BID SECURITY:each bid shall be accompanied by,a certified or cashier's
On the following dates, to wit: check or Bid Bond in the amount of 10 percent of the total bid price payable to
the City of Palm Springs.. -
N-5 BIDS TO REMAIN.OPEN:The Bidder shall guarantee the Total Bid Price for a
Newspaper: The Desert Sun pperlod of 120 calendar days from the date of bid opening.
N-6 CONTRACTOR'S LICENSE CLASSIFICATION;The Contractor shall possess a Yal-
-id Class B General or C39.Roofing Contractor lie the time of submitting
6/10/2017 6/17/2017 bids.
N-7 CALIFORNIA WAGE RATE REQUIREMENTS:The Contractor shall pay the.gen-
eral prevailing rate of per them wages as determined by the Director of the De-
partmem of Industrial Relations of the State of California for the locality where
the work is to be Performed.. All contractors and subcontractors must furnish
electronic certified.pay roll records directly to the Labor Commissioner(via the
Division of Labor Standards Enforcement)as further described in Article 5 of the
I acknowledge that I am a principal clerk of the Construction Contract(Mutual Obligations).A copy of said wage rates is available on-line at:
www, ir.ca.gov/dlsr/DPreWageDetermiriation.htm "
printer of The Desert Sun, printed and The Contractor and any subcontractors shall pay not-less than said specified
rates and shalf and
a copy of said wage fates and other notices prescribed by
published weekly in the City of Palm Springs, reggwation attne pro act site.
N B RETAINAGE FRO PAYMENTS: The Contractor may elect to receive.100 per-
County of Riverside, State of California. The cent of payments due under the Contract Documents from time to time;with-
out retention of any,portion of the payment by the Ciryry,by depositing securl-
Desert Sun was adjudicated a Newspaper of ties of equivalent value with the C in accordance:with the provisions of Sec-
tion 22300 of the PublicContract Code, - -
general CIfCUIatIOn On March 24, 1988 by the N-9 MANDATORY PRE-BID MEETING: Prospective bidders advised to attend the
mandatory pre-bid meeting to acquaint potential bidders with the project and
Superior Court of the County of Riverside, .existing site conditions that may affect the work. The.meetin will be held on
.State Of California Case NO. 191236.
Monday,June 26.2017,at 8:00 AM local time. The bidders shall meet at one of
'the projects site located at 401 S.Pavilion Way Palm Springs,CA to commence
site visits. Bidders will visit each of the five facilities accompanied by city staff,
The.City will only consider bids submitted:by those bidders who attend the
Mandatory Pre=Rid Meeting.` All other bids will be considered has.noo-
responsive and subject to rejection. .
N-30 OBTAINING-OR-INSPECTING CONTRACT DOCUMENT
(a)Contract Documents may be inspected without chargge'at the City of Palm
Springs Engineering Services Department, 3200 East Tahquitz Canyon Way,
I declare under penalty of perjury that the Palm Springs,CA 92262.
(b)'A digital co y of Sal d Contract Documents is available Without charge on-
foregoing IS true and correct. Executed On AVGBrbHSa?dI Ow at: ww.diopbox.mm/shM.mj67tj7zzozg2lJAAAOMSOm7kZDNAyC
this 17th day of JUKE, 2017 m Palm (c)Registration es-a.Bidder: If you are interested In submitting a bid, Bidders
// shall contact the Engineering Services Department by a-mail at bidinfo® almsp
Springs, Calif fT Ia. ringsca.9ov,or by phone at(760)323-8253,to officially register as a Bidder for
.� this.p role
ct with your company name,address,phone,fax,contact person and
e-mall.address.Bidders are encouraged to register to ensure receipt of any Ad-
denda issued by the City. -
(d)This Notice Inviting Bids,the plan Holders List,and other related information
for this project can be found on-line.at the City'.s webpage at:http?Avwwv palm
springgs-ca.gov/governor entide payments/procurement<ontratting
(e)All questions about the meaning or intent of the Bid Documents are to be
directed to the City Engineer. :Questions.shall be submitted:in writing to:city
of Palm.Sprin'qs'Engineering Services Department,by fax to(760)322-8325,,or
by a-mail to bidinfoOpalmspringsca.gov.,.Questions must be submitted In writ-
ing at least 5 working days prior to bid opening. Questions submitted Within5
j working days of bid opening will not be accepted.
N-11.LOCAL BUSINESS PROMOTION—In accordance with the provisions of Palm
Springs Ordinance No.1756,and Section 7.09:030 of the Palm Springs Municipal
D�. Code,-Local Business Preference Program",subsection(5)"Local Preference in
lar. Public works contracts(Sub-Contracting)",the prime contractor shall use good
faith efforts to.sub-contract:the supply of,materials and,equipment to,local
business'eiiterprfses and to sub-contract services to businesses whose work force
resides within the Coachella Valley. - -
li - N-12 ADDRESS AND MARKING OF BIDS:The envelope endosin9 the Bid shall 6e
sealed and addressed to the City of Palm Springs, and shall be delivered or
mailed to the Procurement and Contracting
-Division,City of Palm Springs,:3200
j East Tahquitz Canyon Way, Palm Springs, CA 92262 The envelope shall be
- plainly marked in the upper left hand corner with the name and address of the
Bidder and shall bear the words."Bid For"followed by the title of the Project
and the date and;hour of opening Bids.The certified or cashier's check or Bid
- Bond shall be enclosed in same envelopewith the Bid.. ..
By/s/Thomas Garcia,P.E. Date 6/8/T7
Gty FriVneer