CQ41FORN`P City Council Staff Report
DATE: April 4, 2018 CONSENT CALENDAR
SUBJECT: APPROVAL OF TIME EXTENSIONS OF SUBDIVISION IMPROVEMENT
AGREEMENTS FOR VARIOUS PROJECTS
FROM: David H. Ready, City Manager
BY: Engineering Services Department
SUMMARY
A part of the City's approval of a final subdivision map is the concurrent approval of a
subdivision improvement agreement between the City and the Subdivider. The
agreement secures the costs of on-site and off-site public improvements, and provides
a 2-year period to complete the improvements. Although the economy shows positive
signs of improvement, many investors remain cautious, and construction progress is at
times slow. Hence, some projects remain incomplete and it is necessary to extend the
subdivision improvement agreements to ensure the City retains an ability to pursue the
securities in the event a developer defaults.
RECOMMENDATION:
Adopt Resolution No. "A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF PALM SPRINGS, CALIFORNIA, AUTHORIZING TIME EXTENSIONS OF
VARIOUS SUBDIVISION IMPROVEMENT AGREEMENTS."
STAFF ANALYSIS:
Subdivision improvement agreements are approved as part of the City Council's
approval of a final map for subdivision of property for residential purposes. The
agreement between the City and Subdivider obligates the Subdivider to construct all the
necessary public improvements, which are secured with bonds or other suitable security
to ensure the improvements are constructed and laborers and suppliers are paid. The
City retains the ability to call the securities in the event necessary public improvements
are not completed and the Subdivider has defaulted on the property.
During the economic recession, some residential projects stopped construction and
remained on indefinite hold, and only recently have commenced completion of housing
construction within the project. Over the years, the City Council has approved time
ITEM NO. -1 'T-
City Council Staff Report
April 4, 2018-- Page 2
Time Extension for Various Subdivision Agreements
extensions for various subdivision improvement agreements. Terms of the subdivision
improvement agreements require that the Subdivider complete the public improvements
within a certain time frame (generally two years from the City's approval of the
improvement plans). Although construction on most projects has resumed, some
Subdividers required more time to commence and complete construction. Therefore, it
is staff's recommendation that the City Council acknowledge that factors beyond the
Subdivider's control have delayed completion of the projects, and requires an additional
time extension to various subdivision improvement agreements.
Staff has pursued resolving completion of the subdivision improvements at these
projects, however, in certain cases the developer is not prepared to commence
completion of the improvements. In these cases, staff will coordinate with the City
Attorney's office to initiate legal action to pursue completion of the improvements, or
other appropriate remedies available to the City. However, to ensure these legal
remedies remain available to the City, it is important that the City Council approve this
action to preserve the City's rights to file claims against the Subdivider's bonds in the
event the Subdivider is unwilling or unable to complete the public improvements.
Annually, the City Council has approved en masse of time extension to various
subdivision improvement agreements. Most of the projects that have previously
received time extensions have now completed the required public improvements and
are no longer listed as part of this annual time extension. However, the following nine
projects are in various stages of completing required public improvements, and staff
recommends that the City Council approve time extensions to the subdivision
improvement agreements for the following projects:
Tract Map 28966, "Preserve Estates". extend to June 18, 2019
Tract Map 28966 is a subdivision of 15 new residential lots on one private street located
at the south end of Via Monte Vista shown here in Figure 1. Yj
„<
6 I
F
ja} (j
akvP V. ..t�wi *-
s
t�
Figure 1
02
City Council Staff Report
April 4, 2018 -- Page 3
Time Extension for Various Subdivision Agreements
At the March 2, 2016, City Council meeting, the City Council deferred approval of an
extension of time to the Subdivision Improvement Agreement for Tract Map 28966, and
requested that staff identify the property owner to confirm lack of any conflict of interest
for any member of City Council approving the extension of time. Staff was able to
confirm the current property owner of Tract Map 28966 is Tripalmsview Properties, LLC
and it's manager is Shaul Mezrahi, and Council approved a 1-year time extension
during the March 16, 2016 meeting to June 18, 2017. Since this extension, staff issued
a letter on October 25, 2016, to the Developer advising of the outstanding Public
Improvements and security bonds being held.
In 2014, City Council approved Parcel Map (PM) 36706, which is an apportionment and
extension of TM 28966. A series of lot line adjustments needed to be completed prior to
the completion of PM 36706. Parcel Map 36706 was submitted for review and approval
in 2015. PM was subsequently approved in Plan Check review on April 12, 2017. Due to
the revisions of TM 28966 and PM 36706 utility relocations or extensions needed to be
completed prior to the completion of on-site Public Improvement for TM 28966.
During discussion and approval of another 1-year time extension to June 18, 2018 at
the March 1, 2017, Council meeting, staff was directed to initiate discussions with the
developer and the efforts with the current property owner to complete the remaining on-
site Public Improvements.
Staff has met and discussed the required on-site Public Improvements with Developer
and staff has been provided a construction cost and is working on a construction
schedule with the Developer to complete the required improvements in 2018. Upon the
completion of the require Public Improvements, this would allow the recordation of
Parcel Map 36706, which is a re-apportionment and extension of 28966.
Following the completion of on-site Public Improvements the subdivider is required to
enter into a maintenance and warranty phase for the duration of one-year. Therefore,
staff recommends a 2-year time extension be approved to allow the Developer to
complete the required improvements and the maintenance and warranty phase. If on-
site Public Improvements are not complete within this time frame staff will initiate filing a
claim against the security to force completion of these improvements.
Property Information:
Owner: Tripalmview Properties, LLC
03
City Council Staff Report
April 4, 2018 -- Page 4
Time Extension for Various Subdivision Agreements
Tract Map 32233, "Escena", extend to April 16, 2018
Tract Map 32233 is one phase of residential development and includes 72 residential
lots located within the Escena development shown here in Figure 2.
N'.
n 4�L
III �/►�,,, � �'�►.' :�-•
Figure 2
On-Site Public Improvements are substantially complete. This development is currently
under active construction anticipated to continue for an additional year. The property
owner has deferred final paving improvements until completion of housing construction.
Following the completion of on-site Public Improvements the subdivider is required to
enter into a maintenance and warranty phase for the duration of one-year. Therefore,
staff recommends a 2-year time extension be approved to allow the Developer to
complete the required improvements and the maintenance and warranty phase. If on-
site Public Improvements are not complete within this time frame staff will initiate filing a
claim against the security to force completion of these improvements.
Property Information:
Owner: Beazer Homes
04
City Council Staff Report
April 4, 2018 -- Page 5
Time Extension for Various Subdivision Agreements
Tract Map 32233-1, "Escena", extend to April 2, 2019
Tract Map 32233-1 is the first phase of residential development and includes 43
residential lots located within the Escena development shown here in Figure 3.
t. w
+
k;
V W
e'
y .
< ~Z M
Figure 3
All public improvements are completed with the exception of construction of the final
layer of asphalt concrete pavement on the private street, with associated final
adjustment of sewer manholes and water valves. This work had been deferred by the
current property owner (Standard Pacific Corporation) until completion of housing
construction. Staff has initiated discussion with the Developer and current property
owner to complete the remaining improvements.
Staff recommends another 1-year time extension be approved to reserve the City's
ability to filing a claim against the Developers surety to force completion of these
improvements.
Property Information:
Owner: Standard Pacific Corporation
05
City Council Staff Report
April 4, 2018-- Page 6
Time Extension for Various Subdivision Agreements
Tract Map 32233-2, "Escena", extend to April 2, 2019
Tract Map 32233-2 is the second phase of residential development and includes 145
residential lots located within the Escena development shown here in Figure 4.
ti O 1
y�__ •a,
7• rp, jr
kip-Am
Figure 4
Public improvements are substantially complete with ongoing construction anticipated to
continue for an additional year. The property owner has deferred final paving
improvements until completion of housing construction.
Following the completion of on-site Public Improvements the subdivider is required to
enter into a maintenance and warranty phase for the duration of one-year. Therefore,
staff recommends a 2-year time extension be approved to allow the Developer to
complete the required improvements and the maintenance and warranty phase. If on-
site Public Improvements are not complete within this time frame staff will initiate filing a
claim against the security to force completion of these improvements.
Property Information:
Owner: Alta Verde/Lennar
C6
City Council Staff Report
April 4, 2018 -- Page 7
Time Extension for Various Subdivision Agreements
Tract Map 32233-4, "Escena", extend to April 2, 2019
Tract Map 32233-4 is the fourth phase of residential development and includes 59
residential lots located within the Escena development shown here in Figure 5
f'
S
y-
Y
NJ
Figure 5
All public improvements are completed with the exception of construction of the final
layer of asphalt concrete pavement on the private street, with associated final
adjustment of sewer manholes and water valves. The current property owner (Standard
Pacific Corporation) had deferred this work until completion of housing construction.
Staff has initiated discussion with the Developer and current property owner to complete
the remaining improvements.
Staff recommends another 1-year time extension be approved to reserve the City's
ability to filing a claim against the Developers surety to force completion of these
improvements.
Property Information:
Owner: Standard Pacific Corporation
C7
City Council Staff Report
April 4, 2018-- Page 8
Time Extension for Various Subdivision Agreements
Tract Map 32233-5, "Escena". extend to December 18, 2019
Tract Map 32233-5 is the fifth phase of residential development and includes 128
residential lots located within the Escena development shown here in Figure 6.
Kre • -� � auk� �
.i as
Figure 6
Public improvements are substantially complete with ongoing construction anticipated to
continue for an additional year. The property owner has deferred final paving
improvements until completion of housing construction.
Following the completion of on-site Public Improvements the subdivider is required to
enter into a maintenance and warranty phase for the duration of one-year. Therefore,
staff recommends a 2-year time extension be approved to allow the Developer to
complete the required improvements and the maintenance and warranty phase. If on-
site Public Improvements are not complete within this time frame staff will initiate filing a
claim against the security to force completion of these improvements.
Property Information:
Owner: Toll Brothers
08
City Council Staff Report
April 4, 2018-- Page 9
Time Extension for Various Subdivision Agreements
Tract Map 33561, "Palermo", extend to April 2, 2019
Tract Map 33561 is a residential condominium development approved for 211
condominium units located at the northeast corner of Indian Canyon Drive and San
Rafael Drive shown here in Figure 7.
moms odn,11111411110111111 mows
�s_ �►
Figure 7
This is a large condominium project that was developed into multiple phases, and only
the north half of the site associated with 117 of the 211 condominium units has been
completed within this subdivision. The original Subdivider deferred completion of the
underground utilities and onsite street improvements until subsequent building phases
within this subdivision, however, the property was the subject of a bank foreclosure and
the current property owner is the Palermo Community Association, and the timing for
construction of the remainder of the property is unknown.
Staff recommends that a 2-year time extension be approved. During this extension, staff
will make contact with the current property owner and review the remaining on-site
public improvements and intent of ultimate buildout.
Property Information:
Owner: Palermo Community Association (HOA)
09
City Council Staff Report
April 4, 2018 -- Page 10
Time Extension for Various Subdivision Agreements
Tract Map 36548, "Dakota". extended to November 4, 2018
Tract Map 36548 is a subdivision of 39 new residential lots on private streets located at
the south end of Belardo Road shown here in Figure 8.
t• ♦ .
LLL
r'
•. ,►*` has �`.
r ,
'.rVrr -W � ZE,
r
Figure 8
This subdivision was approved by the City Council on November 4, 2014, and
construction on a portion of the on-site public improvements has commenced.
Completion of the underground utilities and onsite street improvements is continuing
concurrent with subsequent building phases within this subdivision by the Subdivider.
The initial 2-year time for completion identified in the subdivision improvement
agreement expires November 4, 2017, and staff recommends that a 1-year time
extension be approved to allow the Subdivider to complete the remaining onsite public
improvements. The Subdivier has initiated a request for security bond release for the
public improvements that are complete.
Following the completion of on-site Public Improvements the subdivider is required to
enter into a maintenance and warranty phase for the duration of one-year. Therefore,
staff recommends a 2-year time extension be approved to allow the Developer to
complete the required improvements and the maintenance and warranty phase. If on-
site Public Improvements are not complete within this time frame staff will initiate filing a
claim against the security to force completion of these improvements.
Property Information:
Owner: PS Dakota
10
City Council Staff Report
April 4, 2018-- Page 11
Time Extension for Various Subdivision Agreements
Tract Map 366738, "Skye", extended to September 2, 2019
Tract Map 36738 is a subdivision of 40 new residential lots on private streets located at
on the south side of Ramon Road between Fern Canyon and Belardo Road shown here
in figure 9.
LaiAbIN.FlUm MI
Ism ----- ----
4 .
,.Lt--.
i
71
Figure 9
Construction and on-site Public Improvements are substantially complete; staff is
reviewing and will be generating a punch list of remaining items. Public Improvements
are anticipated to be complete by the end of 2018.
Following the completion of on-site Public Improvements the subdivider is required to
enter into a maintenance and warranty phase for the duration of one-year. Therefore,
staff recommends a 2-year time extension be approved to allow the Developer to
complete the required improvements and the maintenance and warranty phase. If on-
site Public Improvements are not complete within this time frame staff will initiate filing a
claim against the security to force completion of these improvements.
Property Information:
Owner: Palm Ridge /Woodbridge
11
City Council Staff Report
April 4, 2018-- Page 12
Time Extension for Various Subdivision Agreements
ENVIRONMENTAL IMPACT:
The requested City Council action is not a "Project" as defined by the California
Environmental Quality Act (CEQA). Pursuant to Section 15378(a), a "Project' means the
whole of an action, which has a potential for resulting in either a direct physical change
in the environment, or a reasonably foreseeable indirect physical change in the
environment. The requested action is to adopt a Resolution authorizing extension of
time for performance of obligations identified in various subdivision improvement
agreements, and is exempt from CEQA pursuant to Section 15378(b), in that a "Project'
does not include: (9) Organizational or administrative activities of governments that will
not result in direct or indirect physical changes in the environment.
FISCAL IMPACT:
None.
SUBMITTED:
Prepared by:
Thomas G rcia Marcus L. Fuller
Director of Engineering Services Assistant City Manager
Approved by:
David H. Ready, Esq.
City Manager
1. Resolution
12
ATTACHMENT 1
13
RESOLUTION NO.
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
PALM SPRINGS, CALIFORNIA, AUTHORIZING TIME
EXTENSIONS OF VARIOUS SUBDIVISION
IMPROVEMENT AGREEMENTS
WHEREAS, the City Council has approved various subdivisions for development
projects throughout the City; and
WHEREAS, included with the City Council's approval of each subdivision is approval of
a Subdivision Improvement Agreement between the City and Subdivider identifying
certain obligations of the Subdivider, including an obligation to complete subdivision
improvements within two years of commencement of work; and
WHEREAS, certain residential subdivisions throughout the City are in various stages of
completion and require additional time for completion of subdivision improvements; and
WHEREAS, it is in the public's best interest to secure the City's security associated with
the subdivision improvement agreements by granting an extension of time for
completion of subdivision improvements.
THE CITY COUNCIL OF THE CITY OF PALM SPRINGS, CALIFORNIA, DOES
HEREBY RESOLVE AS FOLLOWS:
Section 1 . The City Council does hereby approve an extension of time for completion
of subdivision improvements for the following subdivision improvement agreements, as
follows:
Agreement No. 4814, Tract Map 28966, extended to June 18, 2019
Agreement No. 6517, Tract Map 32233, extend to April 16, 2018
Agreement No. 5086, Tract Map 32233-1, extend to April 2, 2019
Agreement No. 5087, Tract Map 32233-2, extend to April 2, 2019
Agreement No. 5089, Tract Map 32233-4, extend to April 2, 2019
Agreement No. 6476, Tract Map 32233-5, extend to December 18, 2019
Agreement No. 5246, Tract Map 33561, "Palermo", extend to April 2, 2019
Agreement No. 6626, Tract Map 36548, "Dakota", extended to November 4, 2018
Agreement No. 6743Tract Map 366738, "Skye", extended to September 2, 2019
14
Resolution No.
Page 2
ADOPTED this 4th day of April, 2018.
David H. Ready, City Manager
ATTEST:
Anthony J. Mejia, MMC, City Clerk
CERTIFICATION
STATE OF CALIFORNIA )
COUNTY OF RIVERSIDE ) ss.
CITY OF PALM SPRINGS )
I, ANTHONY J. MEJIA, City Clerk of the City of Palm Springs, hereby certify that
Resolution No. is a full, true and correct copy, and was duly adopted at a regular
meeting of the City Council of the City of Palm Springs April 4, 2018, by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
Anthony J. Mejia, MMC, City Clerk
City of Palm Springs, California
15