LED LAMP RETROFIT INSTALLATION PROJECT
RECOMMENDATION:
It is recommended that City Council approve Contract Change Order No. 1 to S&K
Electric, Inc., for a decrease of $8,560.00, for a total contract amount of
$55,440.00, for the LED Lamp Retrofit Installation Project, City Project No. 01-02.
SUMMARY:
Contract Change Order No. 1 will adjust estimated quantities to reflect actual
quantities of LED traffic signal lamps installed during construction.
BACKGROUND:
On March 21, 2001, the City Council awarded S&K Electric, Inc., the contract for
the LED Lamp Retrofit Installation Project, City Project No. 01-02, This project
facilitates replacement of standard incandescent traffic signal lamps with energy-
efficient LED lights, and was made possible through the award of a California
Energy Commission (CEC) grant and loan.
Engineering staff originally conducted an overall count of traffic signal lamps
throughout the City that would be replaced through this project. That count was
increased to an amount that would be sufficient to cover actual quantities of traffic
signal lights replaced by the contractor, and was used to determine the amount of
the CEC grant and loan applied for by the City.
The proposed Contract Change Order will adjust the final contract price for this
project to reflect actual quantities of replaced traffic signal lights, and covers the
following items:
Increase to Contract Items:
Item 3, 8" LED Modules, the estimated quantity is increased by 52 to reflect an
actual total of 202 8" LED Modules installed by this project.
Decrease to Contract Items:
Item 2, 12" LED Modules, the estimated quantity is decreased by 300 to reflect an
actual total of 1,850 12" LED Modules installed by this project.
Item 4, LED Pedestrian Modules, the estimated quantity is decreased by 144 to
reflect an actual total of 456 LED Pedestrian Modules installed by this project.
Eighty-three(83) additional work days will be added by this Contract Change Order
as a result of delays in the receipt of materials from the manufacturer, and the
requirement that some of the pedestrian modules be returned and replaced with
a different model.
aA
LED Lamp Retrofit Installation Project
November 28, 2001
Page 2
Sufficient funds are available in account no. 261-4491-50187 (LED Traffic Signal
Lamps).
DAVID J. BARAKIAN
Director of Public Works/City Engineer
APPROVED: 2ti�
City Manager
ATTACHMENTS:
1. Minute Order
;2A
CITY OF PALM SPRINGS
CONTRACT CHANGE ORDER
To: S&K Electric,Inc. Date: October 30,2001
11245 El Nopal St. Project No.: 01-02
Lakeside,CA 92040 Project: LED Lamp Retrofit
Change Order No.: One(1)
Contract Purchase No.: 116446
Account Numbers: 4491-50187
Agreement #4351
Minute Order #6820
A. CHANGES IN WORK:
INCREASE TO CONTRACT QUANTITIES
Item No.
3. Install 8"LED Module 52 EA
DECREASE TO CONTRACT QUANTITIES
Item No.
2. Install 12"LED Module 300 EA
4. Install LED Pedestrian Module 144 EA
B. CHANGES IN COST:
INCREASE TO CONTRACT QUANTITIES
Item No.
3. Install 8"LED Module 52 @$20.00/EA = $1,040.00
DECREASE TO CONTRACT QUANTITIES
Item No.
2. Install 12"LED Module 300 @$20.00/EA = ($6,000.00)
4. Install LED Pedestrian Module 144 @$25.00/EA = ($3,600.00)
TOTAL NET CHANGE ORDER AMOUNT ($8,560.00)
C.REASONS FOR CHANGES:
Actual quantities placed for Bid Items 2,3 and 4 differed from the original estimate which resulted in a credit to the
contract.
Original completion date for this project was June 14,2001. The project was not completed until October 10,2001.
This was due to delays in the receipt of materials from the manufacturer, and the requirement that some of the
pedestrian modules be returned and replaced with a different model. These delays were in no way the fault of the
Contractor and therefore 83 working days are being added to the contract.
Page 1 of 2
2A3
D. SOURCE OF FUNDS:
Account No. 4491-50187 LED Lamp Retrofit Installation
Summary of Costs Contract Time
Original Contract Amount: $64000 Original Completion Date: June 14, 2001
This Change Order $(8,560.00) Days Added for this C.C.O.: -83-
Previous Change Order(s): $0 Previous Days Added: -0-
Revised Contract Amount: $55,440.00 Revised Completion Date: October 10, 2001
I have received a copy of this Change City Approval:
Order and the above AGREED PRICES
are acceptable to the contractor. Submitte Date / D!
Fie d Engi ring Supervisor
By ��i �4) en( Approved By — W.._ Date �) )
City Engineer
Date D Approved by Date
City Manager
Distribution:
Original Conformed Copies Conformed-File Copv
Engineering (1) Engineering File (1)
Finance (1) Engineering Field Inspector (1)
Contractor (1) Engineering Field Supervisor (1)
City Clerk (1) Purchasing Agent (1)
Page 2 of 2
�r4 Y
MINUTE ORDER NO.
APPROVING CONTRACT CHANGE ORDER NO. 1 TO
S&K ELECTRIC, INC., FOR A DECREASE OF $8,560.00,
FOR A TOTAL CONTRACTAMOUNT OF$55,440.00, FOR
THE LED LAMP RETROFIT INSTALLATION PROJECT,
CITY PROJECT NO. 01-02
I HEREBY CERTIFY that this Minute Order, approving Contract Change Order No. 1 to S&K
Electric, Inc., for a decrease of$8,560.00, for a total contract amount of$55,440.00, for the LED
Lamp Retrofit Installation Project, City Project No. 01-02, was adopted by the City Council of the
City of Palm Springs, California, in a meeting thereof held on the 28th day of November, 2001.
PATRICIA A. SANDERS
City Clerk