STAFF REPORT
DATE: JULY 1, 2009 CONSENT CALENDAR
SUBJECT: CHANGE ORDER NO. 1 TO AGREEMENT NO. 5853 WITH G&M
CONSTRUCTION FOR THE SOUTH PALM CANYON DRIVE
WIDENING, CITY PROJECT NO. 05-03
FROM: David Barakian, Director of Public Works/City Engineer
BY: Public Works and Engineering Department
SUMMARY
Approval of Change Order No. 1 to the G&M Construction contract (Agreement No.
5853) revises the total contract amount for construction to $970,137.14, an increase of
$378,603.96 for additional construction being added to the South Palm Canyon Drive
Widening, City Project No. 05 03. The work being added is associated with the
construction of street improvements on South Palm Canyon Drive and Acanto Drive
required with Tract Map 30050 (the "ALTA" development).
RECOMMENDATION:
1) Approve Change Order No. 1 to Agreement No. 5853 with G&M Construction, in
an amount of $378,603.96 for a revised total contract amount of $970,137,14 for
the South Palm Canyon Drive Widening, City Project No. 05-03; and
2) Authorize the Assistant Executive Director or his designee to execute all
necessary documents.
STAFF ANALYSIS:
On May 27, 2009, the Agency approved a contract with G&M Construction to widen
South Palm Canyon Drive from two to four lanes between Murray Canyon Drive and
Bogert Trail, including a widened bridge structure and associated improvements within
Cherly Creek (Arenas Canyon North drainage channel). Whereas, north of Bogert Trail
there will exist two northbound and two southbound lanes on South Palm Canyon Drive;
south of Bogert Trail there will only exist one northbound and one southbound lane on
South Palm Canyon Drive. The designations of each of these street segments, north
ITEM N. C.
Community Redevelopment Agency Staff Report
July 1,2009-Page 2
S. Palm Canyon Dr.widening(City Project No. 05-03)
and south of Bogert Trail (secondary thoroughfare and collector respectively), are
consistent with the adopted Circulation Element of the Palm Springs General Plan 2007
Update. At the transition between the four lane and two lane roadway at Bogert Trail,
there will be a southbound lane-drop transition to transition from two southbound lanes
to one southbound lane.
The existing "ALTA" development (Tract 30060) has had a requirement to remove the
existing street improvements on South Palm Canyon Drive, and to reconstruct new
street improvements in accordance with the City's conditions of approval for the project
(Tentative Tract Map 30060). These off-site street improvements associated with Tract
30050 have been delayed pending RCPC approval of the design of certain off-site
regional flood control improvements that extend along the east side of South Palm
Canyon Drive from Acanto Drive to Bogert Trail.
On July 30, 2008, the City Council considered a request from the developer of Tract
30050 for relief from the obligation to construct the off-site regional flood control
improvements. At that time, the Council authorized staff to proceed with amending the
original Subdivision Improvement Agreement and Conditions of Approval for Tract
30050, to relieve the developer of those obligations. As park of a separate action, the
City Council and Agency will consider formally approving an Amended and Restated
Subdivision Improvement Agreement and revised Conditions of Approval for Tract
30050, implementing the Council's prior authorization.
The developer of Tract 30050 has proceeded with final design of their required off-site
street improvements. A portion of City Project No. 05-03 overlaps with required off-site
street improvements on South Palm Canyon Drive. The overlapping portion of City
Project No. 05-03 consists of a 2" rind and asphalt overlay of the existing asphalt
1 9 p Y
roadway extending from Bogert Trail approximately 800 feet south, adjacent to Tract
30050. These improvements would be demolished as a result of the Tract 30050 off-
site street improvements.
Given the overlapping street improvements on South Palm Canyon Drive and potential
for two separate contractors working independently at the same time with conflicting
work, the City and the developer of Tract 30060 (IRP El Portal Associates, LLC)
determined a mutual benefit existed for both parties to include the Tract 30050 off-site
street improvements under the City's contract for City Project No. 05-03.
The items of work and associated quantities for the Tract 30050 off-site street
improvements were provided by the design engineer for Tract 30050 (MSA Consulting).
Unit costs for these items of work were negotiated with the City's contractor, consistent
with the bid item prices in the original contract award. Unit costs for new items of work
were compared for consistency with related items of work in the original contract.
City staff negotiated a final contract price of $425,772.66 for the Tract 30050 off-site
street improvements with the City's contractor, which was subsequently approved by the
I.,' G
Community Redevelopment Agency Staff Report
July 1,2009-Page 3
S. Palm Canyon Dr.Widening (City Project No. 05-03)
the cost of the Tract 30050 off-site street improvements, including a 10% contingency
fund in the event changes are required during construction.
FISCAL IMPACT.-
Funds from the developer of Tract 30050 have been deposited with the City for their
share of the extra work, to be added to the current funding for this project made
available through Community Redevelopment Agency funds, in account 811-8192-
65171 (S. Palm Canyon Widening Bond).
SUBMITTED:
DAVID J. BARAKIAN THOMAS J. W LSON
Director of Public Works/City Engineer Assistant Executive Director
Attachments:
1. Contract Change Order#1
n
L
COMMUNITY REDEVELOPMENT AGENCY OF THE CITY OF PALM SPRINGS
CONTRACT CHANGE ORDER
To: G&M Construction Date: June 4, 2009
211 West Mesquite Avenue Project No.: 05-03
Palm Springs, CA 92264 Project: S. Palm Canyon Dr. Widening
Change Order No.: One (1)
Contract Purchase No.: Pending
Account Number: 811-8192-65171
Agreement No.: 5853
CHANGES IN WORK/COST
Changes to City Project No. 05-03:
Item No
3. Earthwork -275 CY @ $18.00/CY ($4,950.00)
5. Cold Plane AC -20,240 SF @ $0.20/SF ($4,048.00)
7. 4" Misc. Base -19,827 SF @ $0.40/SF ($7,930.80)
8. 6" Misc. Base 7,350 SF @ $0.75/SF $5,512.50
9. 2" AC Overlay -20,240 SF @ $0.83/SF ($16,799.20)
10. 5" AC Pavement -19,827 SF @ $1.60/SF ($31,723.20)
25. Adjust Manhole 2 EA @ $500.00/EA ($1,000.00)
New Items
A. 3" AC Pavement 7,350 SF @ $1.40/SF $10,290.00
B. Install Redwood Header 600 LF @ $5.80/LF $3,480.00
Subtotal (decrease amount) ($47,168.70)
"ALTA" Tract 30050 Off-Site Street Improvements
a. Mobilization Lump Sum $40,000.00
b. Traffic Control Lump Sum $15,000.00
c. Earthwork 1663 CY @ $18.00/CY $29,934.00
d. Pulverize AC Pavement 71,873 SF @ $0.50/SF $35,936.50
e. 4" Misc. Base 31,888 SF @ $0.40/SF $12,75520
f. 6" Misc. Base 37,048 SF @ $0.75/SF $27,786.00
g. A3 Curb and Gutter 115 LF @ $16.50/LF $1,897.50
h. Adjust Sewer Manhole 5 EA @ $500.00/EA $2,500.00
i. 2.5" AC Pavement 31,888 SF @ $1.27/SF $40,497.76
j. 3" AC Pavement 37,048 SF @ $1.27/SF $51,86720
k. 70mm Orco Pavers 314 SF @ $12.00/SF $3,768.00
I. 8" Wedge Curb 1,310 LF @ $16.00/SF $20,960,00
M. 6" Barrier Curb 1,250 LF @ $14.50/LF $18,125,00
n. Mow Curb 1,100 LF @ $12.00/LF $13,200.00
o. Cross Gutter/Spandrel 1,389 SF @ $7.50/LF $10,417.50
p. 6" Curb Transition 30 LF @ $16.00/LF $480.00
q. 8" Curb Transition 20 LF @ $16.00/1-F $320.00
r. 2"x4" Redwood Header 550 LF @ $5.80/1-F $3,190.00
S. Rip Rap Dissipator 240 SF @ $12.50/SF $3,000.00
CONTRACT CHANGE ORDER
(Continued)
t. Adjust Water Valves 9 EA @ $350.00/EA $3,150.00
U. 6" PCC Pavement 866 SF @ $5.50/SF $4,763.00
V. Earth Berm w/Pyramat 9,150 SF @ $5.00/SF $45,760.00
W. Earth Swale 8' x 6" 1,005 LF @ $10.00/SF $10,050.00
X. Earth Swale Tx 6" 800 LF @ $6.00/1-F $4,800.00
y. 2.5" Decomposed Granite 20,500 SF @ 1.25/SF $25,625,00
Subtotal $425,772.66
TOTAL NET CHANGE ORDER INCREASE AMOUNT $378,603.96
REASONS FOR CHANGES:
A portion of City Project No. 05-03 overlaps with required off-site street improvements on
South Palm Canyon Drive, adjacent to the"ALTA"development(Tract No. 30050)which is
located on South Palm Canyon Drive between Bogart Trail and Acanto Drive, Tract 30050
has obligations to construct certain offsite street improvements on South Palm Canyon
Drive and Acanto Drive in accordance with the Conditions of Approval for Tentative Tract
Map 30050. The Tract 30050 off-site street improvements generally consists of removing
the existing asphalt roadway and reconstructing at a horizontal alignment shifted westerly
with an elevated vertical alignment.
Given the overlapping street improvements on South Palm Canyon Drive and potential for
two separate contractors working independently at the same time with conflicting work,the
City and the developer of Tract 30050 (I RP El Portal Associates, LLC) determined a mutual
benefit existed for both parties to include the Tract 30050 off-site street improvements
under the City's contract for City Project No. 05-03.
The items of work and associated quantities for the Tract 30050 off-site street
improvements were provided by the design engineer for Tract 30050 (MSA Consulting).
Unit costs for these items of work were negotiated with the City's contractor, consistent with
the bid item prices in the original contract award. Unit costs for new items of work were
compared for consistency with related items of work in the original contract.
Items a - y listed above under the heading "'ALTA' Tract 30050 Off-Site Street
Improvements" represents the additional items of work and costs required to construct the
Tract 30050 off-site street improvements.
Note: No additional mark ups will be added to any item on this Change Order.All unit
costs represent total payment for the work identified.
2
CONTRACT CHANGE ORDER
(Continued)
D. SOURCE OF FUNDS
The overlapping portion of City Project No. 05-03 consists of a 2"grind and asphalt overlay
of the existing asphalt roadway extending from Bogert Trail approximately 800 feet south,
adjacent to Tract 30050. These improvements would be demolished as a result of the
Tract 30050 off-site street improvements. The value of these improvements, in
accordance with the original bid is as follows:
Cold Plane Existing A.C. Pavement: 20,240 SF @ $0.20 / SF = $4,048,00
Construct 2"A.C. Overlay: 20,240 SF @ $0.83 / SF = $16,799.20
Total: $20,847.20
As the awarded contract included this work, and had the Tract 30050 off-site street
improvements been constructed under separate contract by the Tract 30050 developer,
these improvements would have been demolished and the corresponding public
investment lost. Therefore, the corresponding value of these improvements is to be
applied as a credit against the cost of the Tract 30050 off-site street improvements. The
Tract 30050 developer has deposited sufficient funds to cover the Tract 30050 off-site
street improvements cost(considering the$20,847.20 credit) of$404,925.46. A separate
10% contingency fee of$40,492.54 has also been deposited to cover changes in the work
during construction related to the Tract 30050 off-site street improvements.
Note: The net decrease to City Project No. 05-03 items of work is $47,168.70 of which the
credit to the Tract 30050 developer of$20,84720 is included. The remaining net decrease
of $26,321.50 is the result of changing the originally specified pavement section of 5"
asphalt concrete (ac) over 4" crushed miscellaneous base (cmb) to 3" ac over 6" cmb for
the new southbound taper south of Bogert Trail to be consistent with the new pavement
section for South Palm Canyon Drive identified on the Tract 30050 off-site street
improvement plans prepared by MSA Consulting, and shortening the southbound taper
thereby reducing required earthwork for its construction.
SUMMARY OF COSTS CONTRACT TIME
Original Contract Amount: $591,533.18 Original Completion Date: TBD
This Change Order: $378,603.96 Days Added for this C.C.O.: —20--
Previous Change Order(s): $0.00 Previous Days Added: —0--
Revised Contract Amount: $970,137.14 Revised Completion Date: TBD
SIGNATURES ON NEXT PAGE
3
CONTRACT CHANGE ORDER
(Continued)
I have received a copy of this Change Order and the above AGREED PRICES are
acceptable to the Contractor.
CONTRACTOR APPROVAL
G&M Construction
Approved by: Date
Printed Name and Title
AGENCY APPROVAL
Submitted by:
Date
Senior Public Works Inspector
Recommend by:
Date
City Engineer
Approved as to Form by:
Date
Agency Attorney
Approved by:
Date
Assistant Executive Director
Attested by:
Date
Assistant Secretary