HomeMy WebLinkAbout7/11/2007 - STAFF REPORTS - 2.F. .+. ?A LM SA?
iy
4
U y
A
e
°q<,F°Ra�P City Council Staff Report
JULY 11, 2007 CONSENT CALENDAR
Subject: AWARD OF CONTRACT FOR THE GOLF CLUB DRIVE CULVERT
RECONSTRUCTION PROJECT, CITY PROJECT 05-18.
From: David H. Ready, City Manager
Initiated by: Public Works and Engineering Department
SUMMARY
The City of Palm Springs has received federal aid funds for reconstruction of the
existing damaged culvert on Golf Club Drive at Palm Canyon Wash. Approval of this
item will award a contract services agreement to Bonadiman-McCain, Inc., to construct
this Emergency Relief Project.
RECOMMENDATION:
1) Adopt Minute Order No. "DETERMINING THAT CEDAR DEVELOPMENT
INC. IS NOT A "RESPONSIBLE BIDDER" UNDER THE DEFINITION IN PALM
SPRINGS MUNICIPAL CODE SECTION 7.01.040."
2) Adopt Minute Order No. "APPROVING AGREEMENT NO. IN THE
AMOUNT OF TWO HUNDRED SIXTY-FIVE THOUSAND ONE HUNDRED
THIRTEEN DOLLARS AND NO CENTS ($265,113.00) WITH BONADIMAN-
McCAIN, INC., FOR THE GOLF CLUB DRIVE CULVERT RECONSTRUCTION
PROJECT, CITY PROJECT 05-18" and
3) Authorize the City Manager to execute all necessary documents.
STAFF ANALYSIS:
In January 2005 the Golf Club Drive culvert was damaged by heavy rains (Declared
Federal and State Emergency) at the Palm Canyon Wash low water crossing. The
Federal Highway Administration of the U.S. Department of Transportation has approved
Emergency Relief (ER) federal aid funds, and on October 19, 2005 issued Authorization
for Preliminary Engineering.
ITEM NO,
The project will accomplish the reconstruction of the culvert system with more pipes of a
larger size to pass a grater flow under the roadway, and will provide a capacity nearly
equal to the actual storm flow measured on January 11, 2005 which caused the failure
of the existing culvert system. The new culvert will eliminate frequent roadway closures
on Golf Club Drive (between November 2004 and February 2005 the road was closed
five times). The work consists of removal and reconstruction of concrete slope
protection, concrete culvert inlet structure, removal of the existing three 18" pipes,
installation of nine 42"x 29" arch pipes and street improvements.
Caltrans' Authorization for Construction was received on March 26, 2007. The project
design has been prepared by Department staff, and on May 2, 2007, the City Council
approved the plans and specifications and authorized staff to advertise for construction
bids.
The project was advertised for bids on May 15 and May 22, 2007, and at 2:00 p.m. on
June 12, 2007, the Procurement and Contracting Division received construction bids
from the fallowing contractors:
1. Cedar Development Corporation $228,150.00
2. Bonadiman-McCain, Inc. $265,113.00
3. WEKA, Inc. $294,186.00
4. 4-Con Engineering, Inc. $297,615.00
5. J. D. Stine Constructors, Inc. $298,450.00
6. Harris Construction Engineering, Inc. $321,940.00
7. Jacobsson Engineering Construction, Inc. $328,324.00
8. Tri-Star Contracting, Inc. $389,390.00
9. Granite Construction Company $399,790.00
10. Dateland Construction Company, Inc. $425,747.50
11. Contreras Construction Co. $434,3%00
Refer to Attachment 1 for Bid Summary.
The Engineer's Estimate was $330,540. The low bid was submitted by Cedar
Development Corporation (C.D.C), located in Mira Loma with its principal officer
Serghon Gabriel Afram CEO/President. As required by the bid forms, C.D.C. has listed
two references for completed projects, but none of the projects were related to culvert
construction. One reference could not be contacted, and the other has described C.D.C.
as a contractor with "inexperienced, unknowledgeable crew, with many problems,
working mostly with subcontractors". Under the City's Procurement Ordinance, this
contractor does not fit the definition of responsible and may therefore not be awarded
the contract. Staff recommendation is to reject the bid submitted by Cedar Development
Corporation, and award the contract to the second lowest bidder, Bonadiman-McCain,
Inc.
Bonadiman McCain, Inc. from San Bernardino has storm drain and culvert related
experience and good references. Its principal officers are Jeff Bonadiman, President,
k��L
it
Bradley Austin, Vice President and Carlo Bonadiman, Secretary/Treasurer. The bid
amount is $265,113.00,
FISCAL_ IMPACT! Finance Director Review:
Sufficient funds for this project are available in account 261-4491-50254 for the 88.53%
federal funds and Gas Tax account 133-4298-50254 for the 11.47% local match.
David J. Barakian Tom ,�lson
Director of Public Works/City Engineer Assistant City Manager-Development Services
APPROVED:
DAVID H. READY
City Manager
ATTACHMENTS. 1. Bid Summary
2. Minute Orders (2)
BID SUMMARY(Page 1.)
GOLF CLUB DRIVE,CULVERT RECONSTRUCTION
CITY PROJECT 05-18 __
BID Bid Schedule Engineer's Estimate CEDAR DEVELOPM,COR BONADIMAWWCAIN INC.
ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL
1 Mobilization 1 L$ $10 500 $16,500 816 500
2 Traffic Control 1 LS $10000 $10,000 $8,900
3 Remove existing concrete structures(inlet str.,slope protections, 1 LS $20,000 $12,500 $5,053
aprons,etc
4 Remove existing as halt concrete pavement 6,400 SF $1.50 $9,600 $1 50 S9 600 $1.00 $6 400
5 Remove existing 18"corrugated metal pipe 345 LF $8.00 $2 760 $20.00 $6 900 $10.00 $3 450
6 Install 42"x29"corrugated steel pipe-arch,including excavation, 1,140 LF 5110 00 $125,400 $70.00 $79,800 $110.00 $125.400
,trenching,backfilling and compaction complete in place.
Construct Portland cement concrete inlet structure per detail on
7 plans,compaction and other incidentals and appurtenances, 1 LS $30,000 $ib 000 $16,000
complete in place.
G Contruct 6"thick Portland cement concrete slope protections at 2 1 31490 SIT $20 00 $69.600 $5 00 $17.450 $5,00 $17,450
slope upstream and 3 1 slope downstream,and aprons, including
all necessary grading and incidentals complete in place
9 Construct 3"asphalt concrete pavement 6,400 SF $3.00 519,200 $3 75 $24X0 $3.00 $19,200
10 Construct 6"class 2-aggregate base 314"max 6,400 SF $2.00 $12,800 $1 00 $6,400 $1,00 $6,400
11 Reconstruct grouted rip-rap spillway as required to restore to 1 LS $12,980 $24.000 $38,600
eexistin condition as per Ian.
12 Traffic striping and markings 1 LS 11 $1,500 1 $5,000 1 51.760
$330,540 $223,150 $265,113
BID Bid Schedule WEKA INC. 4-CON ENGINEERING INC. J.D.STINE CONST.INC.
ITEM DESCRIPTION QUANTITY UNIT JUNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL
1 Mobilization 1 LS $16500 516,500 $16,500
2 Traffic Control 1 LS $9 000 $10 000 $32 000
3 Remove existing concrete structures(Inlet str,slope protections, 1 LS 512,471 $35 000 $6,000
aprons,etc
4 Remove existing as halt concrete pavement 6 400 SF $0 50 $3,200 $1 50 $9 G00 $1.00 56,400
5 Remove existing 18"corrugated metal pipe 345 LF $30 00 $10 350 $20.00 $6 900 $13.00 $4 485
6 Install42"x29"corrugated steel pipe-arch,including excavation, 1,140 LF 5115 00 $131,100 $121.00 $137,940 $65.25 $74,385
.trenching,backfilling and compaction complete In place.
Construct Portland cement concrete inlet structure per detail on
7 plans,compaction and other incidentals and appurtenances, 1 LS S27,000 $15,000 $17,809
complete In place
6 Contruct G"thick Portland cement concrete slope protections at 2.1 31490 SF $8.50 $29,665 $7.50 $26,176 $9,40 $32.806
slope upstream and 3.1 slope downstreem,and aprons,including
all necessary radin and incidentals complete in place
9 Construct 3"asphalt concrete pavement 6 400 SF $2,75 $17.600 $3 00 $19,200 $1.80 $11,520
10 Construct 6"class 2 aggregate base 3/4"max 6 400 SF $1,25 $8,000 $2 00 $12,800 $2.28 $14,592
C 11 Reconstruct grouted rip-rap spillway as required to restore to 1 LS $2G,000 $5,000 $79,203
preexistingcondition as per Ian.
L-� 12 Traffic striping and markings 1 LS $3,300 S3 500 $2,750
$294,186 $297,615 $298,450
BID SUMMARY(Page 2_)
GOLF CLUB DRIVE CULVERT RECONSTRUCTION
CITY PROJECT 05-18
BID Bid Schedule I HARRIS CON.ENG.INC. JACOBSSON ENG.C.INC. TRI STAR CONTR-INC.
ITEM DESCRIPTION QUANTITY1 UNIT JUNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL
1 Mobilization 1 LS $16,500 $16500 $16,500
2 Traffic Control 1 LS $12 000 $22,130 $15,500
3 Remove existing concrete structures(inlet str,slope protections, 1 LS $25,000 $12,395 $12,500
aprons,etc
4 Remove existing asphalt concrete pavement 6,400 SF $0.50 $3,200 $0 60 $3 840 $5 00 $32,000
5 Remove existin 18"corrugated metal i e 345 LF $50 00 $20 700 $11.90 $4,106 $20 00 $6,900
6 Install 42"x29"corrugated steel pipe-arch,including excavation, 1140 LF $70.00 $79,800 $96 25 $109,725 $161.00 $183,540
trenching, b@ckfilling and compaction,complete in place.
Construct Portland cement concrete inlet structure per detail on
7 plans,compaction and other incidentals and appurtenances, 1 L$ $19,500 $13,750 $18,850
com fete in place.
8 Contruct 6"thick Portland cement concrete slope protections at 2'1 3,490 SF $10.00 $34,9D0 $13.65 $47,639 $10.00 $34,9DD
slope upstream and 3.1 slope downstreem,and aprons including
all necessaa qradinqand incidentals complete in place.
9 Construct 3"asphalt concrete pavement 6,400 $F $4 60 $29 440 $4.25 $27,200 $5 00 $32,000
10 Construct 6"class 2 aggregate base 3/4"max 6,400 SF 52.25 $14,400 $1.8D $11.520 $3.00 $19,200
11 Reconstruct grouted rip-rap spillway as required to restore to 1 LS $62,000 $55,920 $9,000
preexisting condition as per plan
12 ITraffic striping and markings 1 LS $4,500 $3,600 $6.500
5321,940 $328,324 $389,390
BID Bid Schedule GRANITE CON.CO. DATELAND CON.CO.INC. CONTRERAS CON.CO.
ITEM DESCRIPTION QUANTITY UNIT JUNITPRIICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL
1 Mobilization 1 LS $16 500 $16 500 $16 500
2 Traffic Control 1 LS $45,580 $23 700 $15.000
3 Remove existing concrete structures(inlet str.,slope protections, 1 LS $34,00D $54,250 $35,000
aprons etc
4 Remove existing asphalt concrete pavement 0,400 SF $0 50 $3 200 $2,75 $17.600 $2.00 $12,800
5 Remove existing 1 S"corrugated metal pipe 345 LF 54.00 51,380 $50 00 $17 250 $30.00 $10350
6 Install42"x29"corrugated steel pipe-arch, including excavation, 1,140 LF $165.00 $188,100 $160 00 $182,400 $120.00 $136,800
trenchingbackfillm and compaction, complete In lace
Construct Portland cement concrete inlet structure per detail on
7 plans compaction and other incidentals and appurtenances, 1 LS $12,000 $32,000 $18,000
complete in place..
8 Contruct 6"thick Portland cement concrete slope protections at 2:1 3,490 $F $7.00 $24,430 $5.75 $20,067 50 $30.00 $104,700
( slope upstream and 3 1 slope downstreem,and aprons, including
all necessary grading and incidentals complete in RaCe
(" 9 Construct 3"asphalt concrete pavement 6.400 SF $4 00 $25,600 $2 10 $13,440 $5.00 $32,000
�j 10 Construct 6"class 2 aggregate base 3/4"max) 6,400 SF $3 00 $19,200 $1 10 $7 040 $3.00 $19,2D0
-11 Reconstruct grouted rip-rap spillway as required to restore to 1 LS $27.000 $30,000 $18,000
preexisting condition as Rer plan.
12 Traffic striping and markings 1 LS $2,800 $11,500 515,000
$399,790 $425,747.50 $434,350
\t
ATTACHMENT
MINUTE ORDERS
4'
,,
,I
MINUTE ORDER NO.
' DETERMINING THAT CEDAR DEVELOPMENT INC.
IS NOT A "RESPONSIBLE BIDDER" UNDER THE
DEFINITION IN PALM SPRINGS MUNICIPAL CODE
SECTION 7.01.040.
I, James Thompson, City Clerk of the City of Palm Springs, California, hereby
certify that this Minute Order determining that Cedar Development Inc. is not a
"responsible bidder" under the definition of Palm Springs Municipal Code Section
7.01.040 was adopted by the City Council of the City of Palm Springs, California,
in a meeting thereof held on the 11�h day of July, 2007.
James Thompson, City Clerk
City of Palm Springs, California
O Ya
i
MINUTE ORDER NO.
APPROVING AGREEMENT NO. IN THE
AMOUNT OF TWO HUNDRED SIXTY-FIVE
THOUSAND ONE HUNDRED THIRTEEN DOLLARS
AND NO CENTS ($265,113.00) WITH BONADIMAN-
McCAIN, INC., FOR THE GOLF CLUB DRIVE
CULVERT RECONSTRUCTION PROJECT, CITY
PROJECT NO. 05-18.
I, James Thompson, City Clerk of the City of Palm Springs, California, hereby
certify that this Minute Order approving Agreement No. in the amount of
two hundred sixty-five thousand one hundred thirteen dollars and no cents
($265,113.00) with Bonadiman-McCain, Inc., for the Golf Club Drive Culvert
Reconstruction Project, City Project No. 05-18 was adopted by the City Council
of the City of Palm Springs, California, in a meeting thereof held on the 11t" day
of July, 2007.
James Thompson, City Clerk