Subject: AWARD OF CONTRACT FOR THE VISTA CHINO (STATE HIGHWAY
111)/SUNRISE WAY STREET IMPROVEMENTS, CITY PROJECT NO.
06-06
From: David H. Ready, Executive Director
Initiated by: Public Works and Engineering Department
SUMMARY
The Vista Chino (State Highway 111)/Sunrise Way Street Improvements, City Project
06-06, is a project being undertaken by the City on behalf of Vista Sunrise Apartments,
L.P., a partnership between McCormack Baron Salazar, Inc., and Desert AIDS Project.
The original project, Vista Sunrise Apartments (now the Rick Weiss Apartments) had
participation from the Desert Healthcare District, Riverside County and the Community
Redevelopment Agency in the development. Award of this contract will allow staff to
proceed with the planned widening of Vista Chino at Sunrise Way.
RECOMMENDATION:
1) Adopt Resolution No. , "A RESOLUTION OF THE COMMUNITY
REDEVELOPMENT AGENCY OF THE CITY OF PALM SPRINGS APPROVING
AGREEMENT NO. IN THE AMOUNT OF $344,044.50 WITH DATELAND
CONSTRUCTION COMPANY, INC., FOR THE VISTA CHINO (STATE
HIGHWAY 111)/SUNRISE WAY STREET IMPROVEMENTS, CITY PROJECT
N0. 06-06;" and
2) Authorize the Executive Director to execute all necessary documents.
STAFF ANALYSIS:
On July 16, 2003, the City Council approved Case 5.0934, PD-281, ("Vista Sunrise
Project"), an application by McCormack Baron Salazar, Inc., for the construction of 85
transitional housing units and family care center on property owned jointly by the City of
Palm Springs, Desert Health Care District, and the Desert AIDS Project. The.original
project also included the development of Riverside County Department of Health's
Family Care Center, which is now under construction by Riverside County as a
Item RA1 .
RDA Staff Report
June 20, 2007 - Page 2
Vista Chino at Sunrise Way Widening (City Project No. 06-06)
separately entitled project. The apartment property is located west of the Desert AIDS
Project, located at the southwest corner of Vista Chino (State Highway 111) and
Sunrise Way.
Included with the City's approval of the original Vista Sunrise Project was the
requirement to widen Vista Chino (State Highway 111) to the full General Plan width for
a major thoroughfare, across the frontage of the property extending to Sunrise Way.
This widening would match the existing street width of Vista Chino adjacent to the Palm
Springs Marketplace (Stater Brothers) Shopping Center east of Sunrise Way, and
significantly improve traffic circulation at this major intersection. In addition, there were
traffic improvements along Sunrise Way. Both elements of the plan, the apartments
and the health care clinic, contributed traffic impacts to the site, therefore requiring the
improvements.
On May 18, 2005, the City Council and Community Redevelopment Agency approved a
Public Improvement Reimbursement Agreement between the City and the Housing
Authority of Riverside County, as well as an Implementation Agreement with Vista
Sunrise Apartments, L.P., to separate the required off-site street widening
improvements from other property transfer issues associated with the Disposition and
Development Agreement approved for the Vista Sunrise Project. Given that Riverside
County had determined to proceed separately with construction of its medical center,
the Reimbursement Agreement allowed the City to take on the responsibility of
constructing the project's required off-site improvements, with reimbursement of half of
the project cost, up to a maximum of$126,000, to be reimbursed to the Agency from the
County once the medical center has been constructed.
The original Implementation Agreement and subsequent DDA Amendments reserved
$125,000 of the original $1,300,000 Agency cash contribution toward the estimated
$250,000 cost of the offsite improvements, to be shared with the County of Riverside.
The design and entitlement costs for the off-site improvements have been charged to
this "hold back." The Agency agreed to bear the cost if the bids exceeded the original
estimated amount.
McCormack Baron Salazar, Inc., contracted with DMC Design Group, to prepare the
plans, specifications and estimates for the widening of Vista Chino (State Highway 111),
extending to Sunrise Way. The project includes street widening, and relocation of the
existing traffic signal at Sunrise Way. The plans have been reviewed and approved by
Caltrans, having jurisdiction over State Highway 111, and the City has received an
Encroachment Permit to proceed with the project.
On May 2, 2007, the City Council approved the plans and specifications and authorized
construction bidding. On May 8 and 15, the project was advertised for bids, and at 2:00
P.M. on June 6, 2007, the Procurement and Contracting Division received construction
bids from the following contractors:
0C2
RDA Staff Report
June 20, 2007- Page 3
Vista Chino at Sunrise Way Widening (City Project No. 06-06)
1. Contreras Construction Co_; Indio, CA
2. Alliance Streetworks, Inc.; Anaheim, CA
3. Dateland Construction Company, Inc.; Coachella, CA
4. Granite Construction Company; Indio, CA
5. Imperial Paving Co.; Whittier, CA
Refer to Attachment 1 for the Bid Summary.
The Engineer's Estimate was $300,000. The low bid was submitted by Dateland
Construction Company, Inc. The company is a California corporation, and its principal
officers are James Richert, President, and Judi Claytor, Secretary.
FISCAL IMPACT:
Funding for this project is available through Community Redevelopment Agency funds,
in account $82 8382-65146,
wlj�z
David J. Barakian ohn S. a o d
Director of Public Works/City Engineer itedor ity&Economic Development
Ca�14�2 �,
David H. Ready Thomas J. Wils
Executive Director Assistant City Manager
ATTACHMENTS;
1. Bid Summary
2. Resolution
OCK'3
ATTACHMENT
BID SUMMARY
1
1
VISTA CHINO AT SUNRISE WAY WIDENING
CITY PROJECT 06.06
BID SUMMARY
Bid Schedule Engineers Estimate CONTRERAS CONSTRUCTION CO. ALLIANCE STREETWORKS, INC.
10 ITEN DESCRIPTION UANTI UNIT UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL
1 Mobilization 1 LS $15,00000 $15,00000 $15,000.00 $15,000.00 $15,000.00 $15,00000
2 Traffic Control 1 LS $10.000.00 $10,00000 $7,600.00 $71500.00 $20,500.00 $20,5DO.00
3 Remove Existing A.C. Pavement 9,300 SF $1.00 $9,300.00 $150 $13,95000 $3.00 $27,90000
4 Remove Existing P.C.C. Sidewalk, Davevmy, 3700 SF $2.00 $7,400.00 $3 50 $12,950 00 $2.00 $7,400 00
Curb Ram
5 Remove Existing 6" P.C.0 Curb 100 LF $8 00 $600.00 $10.00 $1,000.00 $12.00 $1.200.00
6 Remove Existing 6" P CC Curb&Gutter 50 LF $10.00 $500.00 $10 00 $500 00 $15 00 $750.00
7 Remove Existing 8" P.C.C.Curb&Gutter 370 LF $12 00 $4,440 00 $10.00 $3,700.00 $11.00 $4,070.06
8 Remove Existing P.C.0 Spandrel and Cross- 820 SF $16.00 $13,120.00 $6 00 $4,920.00 $2 00 $1,640.00
Gutter
9 Remove Existing Catch Basin 2 EA 51,50000 $3,00000 $4,500.00 $9,000.00 $3,200.00 $6,400.00
10A Relocate Existing Monument Sin 1 E4 $5,000.00 $5,00000 $0.00 $000 $000
10B Re move Exis ling Monument Sign 1 EA $2,50000 $2,50000 $1,500.00 $1,500.00 $2,000.00 $2,000.00
11 Construcl Type A2-8 Curb&Gulter 360 LF $25.00 $9,000 00 $35 00 $12,600 00 $22 OD $7,920.00
12 Construct P.C.C. Spandrel&Cross-Gutter 1130 SF $12.50 $14,125.00 $12.00 $13,560 GO $7 00 $7,91000
13 Construct P.C.C. Driveway Approach 300 SF $7 50 $2,250 00 $9.00 $2,700.00 56.00 $1,800.00
14 Co nstrucl 4"P.C.0 Sidewalk 2400 SF $5.00 $12,000.00 $6.00 $14,40000 $500 $12,000.00
15 Co nstrucl Curb Ramp 1 EA $1,000 OD $100000 $2,800.00 $2,800.00 $4,000.00 $4,000.00
16 Construct Class 2 A re ate Base AB 42o CY $25.00 $1 g500 00 $50 00 $21,OOO OD $60 GO $25,200.00
17 Construct 2"A C. Overlay 200 TON $110.00 $22,ODO.00 $210.00 $42,000 OD $150 00 $30,000 00
18 Construct 4'%"A.0 Pavement 320 TON $9000 $28,80000 $16000 $51,200.01) $125.00 $40,000.00
19 Construct Catch Basin =21%V=6' 2 EA $4,000.00 MOOD 00 $12,00000 $24,0000O $11,0D000 $22,000.00
20 Construct 18"RCP Storm Drain 30 LF $200.00 $6,000 OD $175.00 $5,250.00 -400.00 $12,000 00
21 Construct P.C.C. Storm Drain Collar 2 EA $1,000.00 $2,000 GO $1,000.00 $2,000.00 $2,500 OD $5,000.00
22 Sheeting,Shorin and Bracing 1 LS $3,500.00 $3,50000 $5,000.00 $5,000 OD $1,5000O $1,500.00
23 Adjust Manhole Cover to Grade 2 EA $750 00 $1,500 00 $1,500.00 $3,000.00 $800.00 $1,600.00
24 Traffic Stri in , Si na a&Markin s 1 LS $6,000.00 $6,00000 $12,00000 $12,00000 $7,500 OD $7,500.00
25 Traffic Signal& Electdcal System Modification 1 LS $105.200.00 $105,200.00 $91,000.00 $91,000 00 $105,000 00 3105,000 0D
(Complete)
$302,936.00 $372,530A0 $370,290.00
Total Excluding Bid item 10A or 106: $295,435.00 $371,030.00 $368,290.00
r�
CD
VISTA CHINO AT SUNRISE WAY WIDENING
CITY PROJECT 06-06
BID SUMMARY
Bid Schedule DATELAND CONSTRUCTION,INC. IMPERIAL PAVING CO. GRAN ITE CONSTRUCTION CO.
ID ITEN DESCRIPTION QUANTi UNIT UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL
1 Mobilization 1 LS $1500D 00 $15,000.00 $15,000.00 $15,00000 $15,00000 $115,00D.00
2 TrafFc Control 1 LS $32,70D 00 $32,700.00 $27,00000 $27,000.00 $73.322.00 $73,322.00
3 Remove Existuip A.C. Pavement 9,300 SF $1.75 $16,275.00 $5 50 $51,15D a $3.00 $27,90D 00
4 Remove Existing P.C.0 Sidewalk, Driveway, 3700 SF $2.10 57.770.00 $1.6D $5,920.00 $3.00 $11,i00.00
Curb Ram
5 Remove Existing 6"P C C Curb 100 LF $5.25 $525.00 $5.OD $500 00 $3.00 $30D 00
6 Remove Existing 6"P C.C.Curb&Gutter 50 1 LF $7.00 $350 00 $10 OD $50D.00 $6.00 $300.00
7 Remove Existing 8"P C C Curb & Gutter 370 1 LF $7 10 $2,627 00 $10 OD $3,700.00 $6 00 $2,220.00
6 Remove Existing P C C. Spandrel and Cross- 820 SF $2 25 $1,845.00 $3 25 $2,665.00 $3.00 $2,460.00
Ginter
9 Remove Existing Catch Basin 2 EA $4,700 00 $9,400.00 $700.00 $1,400.00 $2.400 00 $4,800 00
1DA Relocate Existing Monument Sin 1 EA $5,70D.00 $5,700.00 $0.00 $0.00
10B Remove Existi riq Monument Sin 1 EA $0.00 $2,600.00 $2.800.00 $1,00000 $1,00000
11 Construct Type A2-8 Curb&Gutter 360 LF $21 25 $7,650.00 $35 00 $12,600 00 $60.00 $21,600.00
12 Construct P C.0 Spandrel&Cross-Gutter 11130 SF $6.75 $7,627.56 $11.00 $12,430.00 $i8.00 $20,340.00
13 Construct P C.0 DrivewaV Approach 30D SF s6.75 $2,025 00 $10.00 $3,000.00 $13.50 $4,050 00
14 Construct 4"P C C. Sidewalk 2400 SF $5.75 $13,800.00 $7.50 $18,000 00 $9.00 $21,600.00
15 Construct Curb R amp 1 EA $2.700.00 $2,700 00 $3,000.00 $3,000.00 $2,270 00 $2.270 00
16 Construct Class 2 A_qqFegate Base AB 420 CY $24.00 $10,080.00 $53.00 $22,260 00 $121.00 $50,820.00
17 Construct 2"A C Overlay 200 TON $98.00 $19.600.00 $105.00 $21,000 00 $100.00 $20,ODO.00
18 Co n struct 4W A.C. Pavement 320 TON $9200 $29,44000 $105.00 $33,600.00 $10000 $32,0D000
19 Construct Catch Basin(W=21',V=6') 2 EA $9,700.00 $19,400.00 1,11100 $18.600 OD $15.0 DO.00 $30,000.00
20 Construct 18"RCP Storm Drain 30 LF $456.00 $73,680 OD $300.00 $9,000 00 $425 00 $12,750.00
21 Construct P.C.0 Storm Drain Collar 2 EA $6.800.00 $13.600 00 $2,00D 00 $4,000.00 $500.00 $1,00D 00
22 Sheeting, Shoring and Bracing 1 LS $17,000.00 $17,000.00 $600 00 $60D GO $2,50D 00 $2,50D.00
23 Adjust Manhole Cover to Grade 2 FA $875 00 $1,750.00 $1,800.00 $3,600.00 $1,240 00 $2,480.00
24 Traffic Stn m , r na e&Markings 1 LS 8 500.00 8 500.00 5.00000 5 000.00 10.00D.00 10_000.00
25 Traffic Signal& Electacal System Modification 1 LS $85,000.00 $85,000.00 $77,000.00 $77,000.00 $91,799 00 $91,799A0
Coin Iete
$344.0".51) $354,325.00 $461.611.0D
Total Excluding Bid Item 10A or 10B: $338,344.50 $351,525.00 $460,611.0D
rr
A
i
ATTACHMENT 2
RESOLUTION
r
f
r
r
r
Resolution No.
Page 2
RESOLUTION NO.
A RESOLUTION OF THE COMMUNITY
REDEVELOPMENT AGENCY OF THE, CITY OF
PALM SPRINGS APPROVING AGREEMENT NO.
IN THE AMOUNT OF $344,044.50 WITH
DATELAND CONSTRUCTION COMPANY, INC.,
FOR THE VISTA CHINO (STATE HIGHWAY
111)/SUNRISE WAY STREET IMPROVEMENTS,
CITY PROJECT NO. 06-06
WHEREAS, the Community Redevelopment Agency of the City of Palm Springs,
California, ("Agency"), is constituted under the Community Redevelopment Law
(California Health and Safety Code Section 33000 (et. seer.) to carry out the
purpose of redevelopment in the City of Palm Springs, ("City"); and
WHEREAS, pursuant to Section 33447 of the Community Redevelopment Law,
the Agency may finance the construction of public improvements that will
enhance the environment of residential neighborhoods containing housing for
persons and families of low or moderate income, including very low income
households; and that will be of benefit to the project area; and
WHEREAS, pursuant to Section 33447 of the Community Redevelopment Law,
public improvements eligible for financing including street improvements; and
WHEREAS, on July 16, 2003, the City Council approved Case 5.0934, PD-281,
("Vista Sunrise Project'), an application by McCormack Baron Salazar, Inc., for
the construction of 85 transitional housing units and family care center on
properties owned by the City of Palm Springs, Desert Health Care District, and
the Desert AIDS Project. The property is located around the Desert AIDS
Project, located at the southwest corner of Vista Chino (State Highway 111) and
Sunrise Way; and
WHEREAS, included with the City's approval of the Vista Sunrise Project was the
requirement to widen Vista Chino (State Highway 111) to the full General Plan
width for a major thoroughfare, across the frontage of the property extending to
Sunrise Way; and
WHEREAS, On May 18, 2005, the City Council and Community Redevelopment
Agency approved a Public Improvement Reimbursement Agreement between the
City and the Housing Authority of Riverside County, as well as an Implementation
Agreement with Vista Sunrise Apartments, L.P., to separate the required off-site
street widening improvements from other property transfer issues associated with
the Disposition and Development Agreement approved for the Vista Sunrise
Project.
Resolution No.
Page 3
THE COMMUNITY REDEVELOPMENT AGENCY OF THE CITY OF PALM
SPRINGS, CALIFORNIA, DOES HEREBY RESOLVE AS FOLLOWS:
Section 1. Agreement No. , in the amount of $344,044.50 with Dateland
Construction Company, Inc., for the Vista Chino (State Highway 111)/Sunrise
Way Street Improvements, City Project No. 06-06, is hereby approved.
Section 2. The Executive Director of the Agency, and/or his designee, is
authorized to execute all necessary documents.
ADOPTED this 20th day of June, 2007.
Ron Oden, Chairman
ATTEST:
James Thompson, Assistant Secretary
Resolution No.
Page 4
CERTIFICATION
STATE OF CALIFORNIA )
COUNTY OF RIVERSIDE ) ss.
CITY OF PALM SPRINGS )
I, JAMES THOMPSON, Assistant Secretary of the Community Redevelopment
Agency of the City of Palm Springs, hereby certify that Resolution No. is a
full, true and correct copy, and was duly adopted at a regular meeting of the
Community Redevelopment Agency of the City of Palm Springs on June 20,
2007, by the following vote:
AYES:
NOES,-
ABSENT:
ABSTAIN:
James Thompson, Assistant Secretary
Community Redevelopment Agency of
the City of Palm Springs, California